One day bangalore & kolkata

Closing

Exclusive forum for iZenBirdge PMP® clients
suresi00
Contributor
Contributor
Posts: 155
Joined: Mon Nov 20, 2017 4:05 pm

Closing

Postby suresi00 Mon Dec 11, 2017 10:07 pm

What is not the main purpose of a final project report?

o Preparing acceptance of the final product, service or result.
o Making stakeholders aware that the project has been closed out.
o Acknowledging what has been done and achieved by all contributors.
o If a project has been cancelled before completion: Explaining the causes.

Manish sir can you please explain the rationale for this question. Is it because the last step in close project of collecting all records ?
manishpn
Expert
Expert
Posts: 2451
Joined: Sat Jan 04, 2014 3:55 pm

Re: Closing

Postby manishpn Tue Dec 12, 2017 8:58 pm

suresi00 wrote:What is not the main purpose of a final project report?

o Preparing acceptance of the final product, service or result.
o Making stakeholders aware that the project has been closed out.
o Acknowledging what has been done and achieved by all contributors.
o If a project has been cancelled before completion: Explaining the causes.

Manish sir can you please explain the rationale for this question. Is it because the last step in close project of collecting all records ?


its quiet simple, atleast attempt

not sure what you mean by 'Is it because the last step in close project of collecting all records'
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
suresi00
Contributor
Contributor
Posts: 155
Joined: Mon Nov 20, 2017 4:05 pm

Re: Closing

Postby suresi00 Tue Dec 12, 2017 9:00 pm

I know now read RITA:-)
manishpn
Expert
Expert
Posts: 2451
Joined: Sat Jan 04, 2014 3:55 pm

Re: Closing

Postby manishpn Tue Dec 12, 2017 9:17 pm

so whats the answer as per you
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
suresi00
Contributor
Contributor
Posts: 155
Joined: Mon Nov 20, 2017 4:05 pm

Re: Closing

Postby suresi00 Tue Dec 12, 2017 9:24 pm

A , the final deliverable acceptance letter
manishpn
Expert
Expert
Posts: 2451
Joined: Sat Jan 04, 2014 3:55 pm

Re: Closing

Postby manishpn Tue Dec 12, 2017 10:12 pm

yes thats correct,
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/

Return to “PMP® Queries and Tips”

Who is online