Time and Material

Postby suresi00 Mon Dec 11, 2017 3:40 pm

Manish sir,

The e wages of hourly workers on a time and materials project is considered a/an_________________ cost.
Direct/variable
Direct/fixed
Indirect/variable
Indirect/fixed

What is the right answer. My answer was direct and fixed because the unit rate of the labor was fixed. But the correct answer was direct/ variable as the number of hrs change.
manishpn
Expert
Expert
Posts: 2542
Joined: Sat Jan 04, 2014 3:55 pm

Re: Time and Material

Postby manishpn Mon Dec 11, 2017 5:10 pm

T and M can never have fixed cost >...

It has to be direct and variable (in the sense that cost will be billed at actuals based on effort spent)
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist