Postby suresi00 Mon Dec 11, 2017 2:33 pm

One of the risks identified in the project’s risk register has a probability of 85%. As the project manager what would you do first upon making this discovery?
Make the risk a #1 priority in the risk register
Move the ’risk’ to the issue log
Risk data validation
Raise a red jeopardy on a stoplight report

Why do we move the risk to issue log? I though probability is high we should do impact analysis.
manishpn
Expert
Expert
Posts: 2403
Joined: Sat Jan 04, 2014 3:55 pm

Re: Risk

Postby manishpn Mon Dec 11, 2017 5:04 pm

suresi00 wrote:One of the risks identified in the project’s risk register has a probability of 85%. As the project manager what would you do first upon making this discovery?
Make the risk a #1 priority in the risk register
Move the ’risk’ to the issue log
Risk data validation
Raise a red jeopardy on a stoplight report

Why do we move the risk to issue log? I though probability is high we should do impact analysis.

high probability does not necessarily means the need to move the risk to issue log.
issue log however can be modified if PM wants to take specific additional actions on the risk
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/

Return to “PMP® Queries and Tips”

Who is online

Users browsing this forum: No registered users and 4 guests