In a phased project ,
project charter is created only once and will be reviewed after each phase during the kick off next phase

Is this a correct statement. I saw in scodo while doing a test project charter will be created in each phase .
Posts: 2467
Joined: Sat Jan 04, 2014 3:55 pm

Re: Project charter

Postby manishpn Sun Dec 10, 2017 8:33 pm

Project charter is usually done only once.
I dont agree with the statement that a new PC is needed for every phase
Manish P