Complete final contract performance reporting and verify product is done in
_______ .
A. Conduct Procurements
B. Close Procurements
C. Plan Procurements
D. Administer Procurements

Manish sir do we do verify product in close procurement?
manishpn
Expert
Expert
Posts: 2412
Joined: Sat Jan 04, 2014 3:55 pm

Re: Close Procurement

Postby manishpn Thu Dec 07, 2017 3:16 pm

Not as per PMBOK , its a separate process in scope knowledge area, however in real life within the close procurement process you encapsulate contract related scope validation