Schedule constraints

Postby suresi00 Mon Dec 04, 2017 11:39 am

Lead and Lag are tools to figure out the impact of dependencies on activities. They are not Schedule constraints. Is this statement right?
manishpn
Expert
Expert
Posts: 2371
Joined: Sat Jan 04, 2014 3:55 pm

Re: Schedule constraints

Postby manishpn Tue Dec 05, 2017 7:10 pm

yes thats correct
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist