One day bangalore & kolkata

Mock Test Clarification needed on :Update project document

Exclusive forum for iZenBirdge PMP® clients
balaji1987
Beginner
Beginner
Posts: 25
Joined: Tue Nov 21, 2017 1:13 pm

Mock Test Clarification needed on :Update project document

Postby balaji1987 Mon Nov 27, 2017 6:25 am

You are a project manager and during the midway of execution you realize that some communications may no longer be necessary, an ineffective communication method may be replaced by another method or a new communication requirement may be identified. What will you do next?
Options:
A: Update project management plan
B: Update project document
C: Raise Change Requests
D: Update stakeholder management strategy

I got the answer to Update project document, But my choice was raising a CR, it's a control communication process and output was raising a CR.Please clarify

Also, in the above question A,B,C are o/p of control communication process Please let me know why i have to update the project docs
manishpn
Expert
Expert
Posts: 2447
Joined: Sat Jan 04, 2014 3:55 pm

Re: Mock Test Clarification needed on :Update project document

Postby manishpn Mon Nov 27, 2017 9:29 pm

this is not a good quality question, what justification was provided for option B against option C
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/

Return to “PMP® Queries and Tips”

Who is online

Users browsing this forum: No registered users and 3 guests