Activity Cost Estimates. The projected cost of the schedule activity that includes the cost of all resources required
to perform and complete the activity, including all cost types and cost components.
during this estimation do we consider the Indirect and fixed cost as well..?
manishpn
Expert
Expert
Posts: 2196
Joined: Sat Jan 04, 2014 3:55 pm

Re: Activity Cost Estimates

Postby manishpn Tue Oct 31, 2017 12:36 pm

usually at the activity level we do not add indirect/Fixed cost as its practically difficult to associate such costs to an activity.

However project may have guidelines on how to split indirect cost across different activities,
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/

Return to “PMP® Queries and Tips”

Who is online

Users browsing this forum: Bing [Bot] and 5 guests