change request.

Posted: Sun Apr 09, 2017 6:26 pm
by Jahiru_Q
After receiving a change request, i found that it is not fall in business case, project charter, project scope statement and have no benefit for the organization. then does i say no indirectly or pass CR through CCB although i know it will never accepted.

Re: change request.

Posted: Mon Apr 10, 2017 8:01 pm
by manishpn
Usually PM should be able to convince the stakeholder if CR does not allign with projects business case, and if the stakeholder still insists and maybe if it is a poweul stakeholder then PM should take if formally to CCB