Scope question from rita fast trak v8

Postby Jahiru_Q Sat Apr 08, 2017 11:42 am

Project management activity:
1. Are distinct from both project & product scope.
2. Include work to ensure that the product scope is achieved.
3. Are included in project scope at the project manager discretion.
4. Are part of product scope & not part of project scope.
My answer was 2, but as per rita Correct answer is 4. Comments please
manishpn
Expert
Expert
Posts: 1923
Joined: Sat Jan 04, 2014 3:55 pm

Re: Scope question from rita fast trak v8

Postby manishpn Sat Apr 08, 2017 7:17 pm

Project scope is WBS Baseline, and WBS baseline includes project management activity, thats the 100% rule.
So I would not agree with RIta.

What is the explanation provided by Rita?
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
Jahiru_Q
Posts: 16
Joined: Fri Nov 04, 2016 8:16 pm

Re: Scope question from rita fast trak v8

Postby Jahiru_Q Sun Apr 09, 2017 4:06 pm

Project management activities include work to ensure that the product scope is achieved.
manishpn
Expert
Expert
Posts: 1923
Joined: Sat Jan 04, 2014 3:55 pm

Re: Scope question from rita fast trak v8

Postby manishpn Wed May 10, 2017 3:31 pm

I dont think option #4 is right
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/