Project management activity:
1. Are distinct from both project & product scope.
2. Include work to ensure that the product scope is achieved.
3. Are included in project scope at the project manager discretion.
4. Are part of product scope & not part of project scope.
My answer was 2, but as per rita Correct answer is 4. Comments please
Scope question from rita fast trak v8
Re: Scope question from rita fast trak v8
Project scope is WBS Baseline, and WBS baseline includes project management activity, thats the 100% rule.
So I would not agree with RIta.
What is the explanation provided by Rita?
So I would not agree with RIta.
What is the explanation provided by Rita?
Re: Scope question from rita fast trak v8
Project management activities include work to ensure that the product scope is achieved.
Re: Scope question from rita fast trak v8
I dont think option #4 is right