Activity Duration Estimates

Postby Jahiru_Q Tue Mar 21, 2017 5:35 am

From pg-172
• 2 weeks ± 2 days, which indicates that the activity will take at least eight days and not more than twelve (assuming a five-day workweek); and
• 15 % probability of exceeding three weeks, which indicates a high probability—85 %—that the activity will take three weeks or less.

Is there any relationship of these two example or separate ?
manishpn
Expert
Expert
Posts: 2125
Joined: Sat Jan 04, 2014 3:55 pm

Re: Activity Duration Estimates

Postby manishpn Tue Mar 21, 2017 6:33 am

what page # of which book are you referring?
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
Jahiru_Q
Posts: 18
Joined: Fri Nov 04, 2016 8:16 pm

Re: Activity Duration Estimates

Postby Jahiru_Q Wed Mar 22, 2017 12:36 pm

PMBOK 5E- pg 172
manishpn
Expert
Expert
Posts: 2125
Joined: Sat Jan 04, 2014 3:55 pm

Re: Activity Duration Estimates

Postby manishpn Wed Mar 22, 2017 7:00 pm

these are seperate examples not related
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/

Return to “PMP® Queries and Tips”

Who is online

Users browsing this forum: No registered users and 2 guests