Update Change log/ OPA after implement the approved change request

Postby Housam Bassal Mon Feb 20, 2017 5:59 pm

Bill is managing a website development project. He has recently received a feedback from one of the key project stakeholders. The feedback is overall positive but it contains some recommendations. After analyzing the recommendations, Bill accepts them, gets them approved and incorporates them into the project management plan.
What needs to be done with this feedback now?

A. Discard it as it is no longer required
B. Publish it on the corporate intranet
C. Add it to the organizational process assets
D. Send it back to the stakeholder

I think in question mentioned the following step:
Feedback/recommendations >> change Request >> impact analysis >> present to CCB >> approved CR >> implement the approved change request.

So I think the next step is communicate approved change request back to Stakeholder , and update change log. Which is part of OPA, hence the correct answer should be C.
Housam Bassal
Ecuador - Quito
LinkedIn: https://www.linkedin.com/in/housam-bassal-49984357
manishpn
Expert
Expert
Posts: 2125
Joined: Sat Jan 04, 2014 3:55 pm

Re: Update Change log/ OPA after implement the approved change request

Postby manishpn Tue Feb 21, 2017 2:55 pm

yes C is right option
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/