before closing the project

Postby Housam Bassal Mon Feb 06, 2017 2:59 pm

A project manager has made the final delivery to the customer and the team is in the process of completing administrative and contract closure. The team has also completed the final version of lesson learned in the corporate database. Which of the following is a critical activity that the project manager should complete before formally closing the project?

A. Confirm that all the requirements in the project are met
B. Ensure that all project management processes are complete
C. Obtain formal sign-off of the project from the customer
D. Index and archive the project records


I think the correct answer is D

as the team already has made the finial delivery , it mean hand off the completed product , hence gain final acceptance of product from customer already done. Also both options A, B had been done. Therefore the next critical step left is to index and archive the project records.
Housam Bassal
Ecuador - Quito
LinkedIn: https://www.linkedin.com/in/housam-bassal-49984357
manishpn
Expert
Expert
Posts: 2196
Joined: Sat Jan 04, 2014 3:55 pm

Re: before closing the project

Postby manishpn Mon Feb 06, 2017 9:43 pm

making final delivery to customer is not same as getting acceptance.
Before closing project there needs to be final sign off from customer.

I think option C is best choice
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/