Your project is in the final stages of testing and the team is interacting with the customer on daily basis to update him with the project status and incorporate his feedback. Which of the following would be the most critical process to be followed in this scenario?

Control Quality
Control Scope
Manage Communications
Control Risks

My answer was A but correct answer is B. I am not able to figure out that the above scenario happening in which process.
ujjal_show
Super Member
Super Member
Posts: 1094
Joined: Thu Sep 17, 2015 12:59 pm

Re: Q- Simplilearn

Postby ujjal_show Sun Jan 03, 2016 1:01 pm

project is in the final stages of testing" that means the team is in quality control activities.

But, they "interacting with the customer on daily basis" this is unusual in quality activities, because quality activities are international to the project.

Further it asking for "most critical process to be followed" that should be monitoring the scope and making changes to the scope - control scope.
User avatar
saket
Site Admin
Site Admin
Posts: 3125
Joined: Sat Dec 07, 2013 10:37 pm

Re: Q- Simplilearn

Postby saket Sun Jan 03, 2016 2:20 pm

Difficult ... but if i have to select i will select Validate Scope... i know that option is not available :)
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image
Anaisha09
Posts: 2
Joined: Tue Mar 28, 2017 9:52 am

Re: Q- Simplilearn

Postby Anaisha09 Wed Aug 02, 2017 8:40 pm

Correct answer is Control Scope. Since its the project team which is interacting with the customer on daily basis and the final testing is also going on, the probability of Gold Plating and Scope Creep is quite high. Hence as a Project Manager, I am responsible to keep a check on both these aspects. So, I would go with Control Scope
manishpn
Expert
Expert
Posts: 2343
Joined: Sat Jan 04, 2014 3:55 pm

Re: Q- Simplilearn

Postby manishpn Thu Aug 03, 2017 11:39 am

Anaisha09 wrote:Correct answer is Control Scope. Since its the project team which is interacting with the customer on daily basis and the final testing is also going on, the probability of Gold Plating and Scope Creep is quite high. Hence as a Project Manager, I am responsible to keep a check on both these aspects. So, I would go with Control Scope


I agree and very well explained
but validate scope process is also equally important to keep track of
Br,
Manish P