Please explain links given in Attached image

Exclusive forum for iZenBirdge PMP® clients
kshitij_y
PMP
Posts: 229
Joined: Wed Dec 11, 2013 9:39 am

Please explain links given in Attached image

Postby kshitij_y Thu Feb 27, 2014 7:46 pm

Dear Saket

I have attached one image to this file , All WPD and WPI links i have understood, only for some of i have marked Red circles where i want to know what is linkage between this process

Eg. Peformance integrated change control to Control Risk, Manage communication ,manage project team

Please explain Thanks

Kshitij Yelkar
Attachments
Refined Data Model.png
Refined Data Model.png (42.25 KiB) Viewed 1713 times
User avatar
saket
Site Admin
Site Admin
Posts: 3113
Joined: Sat Dec 07, 2013 10:37 pm

Re: Please explain links given in Attached image

Postby saket Fri Feb 28, 2014 6:34 am

All these processes : Eg. Peformance integrated change control to Control Risk, Manage communication ,manage project team

Tales Work Performance report as an input, so the point is some of the 47 process , the one looks overall status of the project takes work performance report as an input.

In one of the risk hangout we had conversation on this matter...

Let me know if you have followup question on this.
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image
kshitij_y
PMP
Posts: 229
Joined: Wed Dec 11, 2013 9:39 am

Re: Please explain links given in Attached image

Postby kshitij_y Fri Feb 28, 2014 8:08 am

Yes, Monitor and control Project Work will create Work Performance Report as output and goes input to below 5 process Perform Integrated Change Control
Monitor and Control Risks
Control Procurements
Manage Project Team
Manage Communications


But there is arrow at the both the side of Perform Integrated Change Control and other 5 Process , I hope there is no link between that as they are only linked with Monitor and control Project Work ?


Regards
Kshitij Yelkar
User avatar
saket
Site Admin
Site Admin
Posts: 3113
Joined: Sat Dec 07, 2013 10:37 pm

Re: Please explain links given in Attached image

Postby saket Sat Mar 01, 2014 1:25 am

Just take it as Work Performance Information moving to both the processes , rather than thinking these two processes are interacting in this diagram.
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image
kshitij_y
PMP
Posts: 229
Joined: Wed Dec 11, 2013 9:39 am

Re: Please explain links given in Attached image

Postby kshitij_y Sat Mar 01, 2014 10:51 am

Thanks saket