Q. Projec team is working on manufacturing a new product , but they are having difficulty creating charter ,
what is best desc of problem?
1) They have not identified project objective 2) They are working on process and not a project? Rita-42-17
indusharma
Super Member
Super Member
Posts: 349
Joined: Wed Dec 11, 2013 2:55 am

Re: Q. Projec team is working on manufacturing a new product

Postby indusharma Thu Dec 12, 2013 5:23 am

Design of a new product, Launch of a new product can be a project as these processes are creating something new…. which never exists before. But when we talk about manufacturing that means product has been designed, all the steps are already defined. And with start of manufacturing, it comes into operational cycle.

Project Charter is created for a project with objectives of project, giving authority to project manager and containing high level risk, requirements and scope of the project. In cases of operational work, project charter not required

Indu Sharma
PMP Trainer
Indu Sharma
PMP Trainer
iZenbridge Consultancy Pvt Ltd
kshitij_y
PMP
Posts: 229
Joined: Wed Dec 11, 2013 9:39 am

Re: Q. Projec team is working on manufacturing a new product

Postby kshitij_y Thu Dec 12, 2013 6:36 am

Thanks Indu