Estimate Activity Durations

Postby sivapriya Mon Dec 30, 2019 6:44 am

Hello Sir,

During Estimate Activity durations (Schedule Management) We have 'Basis of Estimates' as one of the outputs.
Do we maintain a separate document for 'Basis of Estimates' or do we update them in 'Assumptions Log' itself?

Request your clarification in this regard.


- Sivapriya.
manishpn
Expert
Expert
Posts: 2819
Joined: Sat Jan 04, 2014 3:55 pm

Re: Estimate Activity Durations

Postby manishpn Thu Jan 02, 2020 6:56 pm

sivapriya wrote:Hello Sir,

During Estimate Activity durations (Schedule Management) We have 'Basis of Estimates' as one of the outputs.
Do we maintain a separate document for 'Basis of Estimates' or do we update them in 'Assumptions Log' itself?

Request your clarification in this regard.


- Sivapriya.


Basis of estimate a separate document, however project level assumption log is also updated, the assumption log is a project document, while basis of estimate is specific to schedule/cost estimate and this document is used to baseline schedule cost and updated during the control schedule/cost process.
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/

Return to “PMP® Queries and Tips”

Who is online

Users browsing this forum: No registered users and 3 guests