Using Contingency reserve

Exclusive forum for iZenBirdge PMP® clients
rathodmk
Posts: 14
Joined: Sat Jan 12, 2019 10:45 am

Using Contingency reserve

Postby rathodmk Fri Jun 14, 2019 2:18 pm

I have a doubt about the action "Using Contingency reserve"

Does it fall under "Monitor risk process" or under "Direct and manage project work" ?
manishpn
Expert
Expert
Posts: 2714
Joined: Sat Jan 04, 2014 3:55 pm

Re: Using Contingency reserve

Postby manishpn Fri Jun 21, 2019 1:07 pm

rathodmk wrote:I have a doubt about the action "Using Contingency reserve"

Does it fall under "Monitor risk process" or under "Direct and manage project work" ?



Monitor risk response only evaluates the effectiveness of risk responses , risk processes , tracking identified risk etc, hence it does not use the reserves
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/