WBS and Decomposition

Exclusive forum for iZenBirdge PMP® clients
rathodmk
Posts: 14
Joined: Sat Jan 12, 2019 10:45 am

WBS and Decomposition

Postby rathodmk Fri Jun 14, 2019 2:16 pm

In your question "Which of the following represents the technique used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?"


Create WBS

Aggregation

Decomposition

Progressive Elaboration

As per you right answer is "Decomposition".

But as per Rita in page number 204, Trick of the Trade, Decomposition is what we are doing and WBS is means to do it.

Please explain me difference between Decomposition and WBS from PMP exam point of view.
seema.sonkiya
Expert
Expert
Posts: 2315
Joined: Fri Jul 11, 2014 11:57 am

Re: WBS and Decomposition

Postby seema.sonkiya Thu Jun 20, 2019 6:24 am

WBS is the hierarchical structure to show all deliverable and decomposition is the tool to get that structure.

Return to “PMP® Queries and Tips”