Risk identified in between of Project

Postby kshitij_y Tue Jan 28, 2014 4:56 pm

If new risk is identified in between of project and it has cost impact, Then client will be impacted on same ? How this situation get managed commerically with the client.

Regards
Kshitij Yelkar
namita
Super Member
Super Member
Posts: 502
Joined: Wed Dec 11, 2013 10:25 am

Re: Risk identified in between of Project

Postby namita Wed Jan 29, 2014 11:18 am

Kshitij,

We have something called management reserves defined in project budget for unknown unknowns. That is nothing but reserved for unforeseen work that is within scope of the project.. If there is newly identified risk which impact cost means it is something which was unknown at the time of project initiation, planning and now some new work is to be done. We can make use of management reserves and take approval to update the cost baseline.

Answering your question - if there is something which is beyond the allocated management reserves, we may need to really look in details that new risk is really within scope of this project or the work this risk is triggering can be taken separately. Ideally management reserves are devised taking into consideration of size of project and probability of unknown unknowns can be reported for it and should be sufficient to address it
kshitij_y
PMP
Posts: 229
Joined: Wed Dec 11, 2013 9:39 am

Re: Risk identified in between of Project

Postby kshitij_y Wed Jan 29, 2014 3:51 pm

Is defined management reserved get discussed with the client?
Assuming we mentioned 5% management cost reserved in pm plan and if that is not used till the end of the project , will it get benifited to client at the time of billing?
User avatar
saket
Site Admin
Site Admin
Posts: 3113
Joined: Sat Dec 07, 2013 10:37 pm

Re: Risk identified in between of Project

Postby saket Thu Jan 30, 2014 3:59 am

A lot depend on type of Procurement Contract Between these two parties.
a. Fixed Price, client has nothing to do with this, its a vendor responsibility to manage it , while vendor create budget for project ,he should take care of such risks
b. On time and Material or Cost Reimbursement, vendor has to make detail report on this issue and customer is the one who is going to pay the additional cost.
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image
kshitij_y
PMP
Posts: 229
Joined: Wed Dec 11, 2013 9:39 am

Re: Risk identified in between of Project

Postby kshitij_y Thu Jan 30, 2014 7:27 am

Thanks saket... :)