Which of the following is not accurate about the initial phase of a project?
A. The highest uncertainty is at this stage of the project
B. The cost associated at the beginning of the project is highest
C. Stakeholders have maximum influence during this phase
D. Staffing levels are the highest at this stage
GOAL : PMP Certified by 24th Sept 2014 -- ACCOMPLISHED
seema.sonkiya
Expert
Expert
Posts: 1772
Joined: Fri Jul 11, 2014 11:57 am

Re: Initial Phase : Cost & Staffing Level

Postby seema.sonkiya Sun Sep 21, 2014 4:49 am

are you sure only one option is incorrect?

Cost and staffing levels - both are low at initial stage of project.
umeshbww
Contributor
Contributor
Posts: 168
Joined: Fri Aug 15, 2014 3:02 pm

Re: Initial Phase : Cost & Staffing Level

Postby umeshbww Sun Sep 21, 2014 4:10 pm

Seema - I agree with you. This question is from Scordo; and I don't agree with answer/explanation.

Answer/Explanation : option B - At the initial stage of a project, the cost is typically not at its highest. [PMBOK 5th edition, Page 40]
GOAL : PMP Certified by 24th Sept 2014 -- ACCOMPLISHED
seema.sonkiya
Expert
Expert
Posts: 1772
Joined: Fri Jul 11, 2014 11:57 am

Re: Initial Phase : Cost & Staffing Level

Postby seema.sonkiya Mon Sep 22, 2014 6:59 am

I checked the PMBOK, page no. 40: it is clearly written there: cost and staffing are low at start.
So B&D are incorrect.

Option A is correct as ideally at the start of project, risk levels are high and as we move towards execution, risk levels get reduced.

Option C - “Influence” means involvement, it is right that Key stakeholders have maximum involvement at the initial stage, but other team members at execution. Apart from it, if we consider where phase to phase relationship is iterative in that case, all the team members get involved all the time – here in question no differentiation of stakeholders, what kind of stakeholders – question is talking about? Stakeholder influence is also depend on Power/Interest grid :-)
So we can say the option C is also incorrect.
User avatar
saket
Site Admin
Site Admin
Posts: 3125
Joined: Sat Dec 07, 2013 10:37 pm

Re: Initial Phase : Cost & Staffing Level

Postby saket Mon Sep 22, 2014 11:07 am

we had this question discussed in some previous threads ...
viewtopic.php?f=11&t=247&p=762
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image

Return to “PMP® Queries and Tips”

Who is online

Users browsing this forum: No registered users and 1 guest