Jonathan has recently been hired in a company as a business improvement manager. Jonathan has been asked to reorganize the company's meetings and reporting structure. Jonathan is currently identifying all key project stakeholders. Which of the following enterprise environmental factors is least likely to be used as an input to this process?
A. Organizational culture and structure
B. Existing human resources
C. Project management information system
D. Industry standards

Re: EEF Question

Posted: Fri Sep 19, 2014 4:16 am
by Parul
Hi Umesh,

Project Management Information System is not required when we are trying to identify Stakeholders.

Once they are Identified while planing the communication process and reporting system we will consider Project Management Information System.

Hence C

Re: EEF Question

Posted: Fri Sep 19, 2014 3:14 pm
by umeshbww
Thanks Parul.

Re: EEF Question

Posted: Thu Dec 04, 2014 8:26 pm
by bs_pani
I agree with Parul that we do not use PMIS for Identifying Stakeholder. But do we really use Existing human resources for Identifying Stakeholder? I do not see that as well in PMBOK Page 395.

For me both B and C is correct answer. Any though on this?

Re: EEF Question

Posted: Fri Dec 05, 2014 7:23 am
by pank_pmp
Existing Human Resources may include team lead, expert, Middle Management, Sr. Management, Sponsors, SME and moreover their hierarchy is also important. I think this understanding is important in identifying stakeholders.

Re: EEF Question

Posted: Fri Dec 05, 2014 5:07 pm
by bs_pani
Pankaj,

I understand you point. But if a pre existing resource is so important to project then he will be pre assigned to the project. If you take the existing human resource then everyone in the company will be stake holder to the project which does not look correct to me.