Q from Rita-If you need to shorten the duration of project, which activity would you try to shorten (see attachment)?

Critical path is C, E,H,End

Options:
Activity B
Activity D
Activity H
Activity C

Ans- If you have choice choose, all the things being equal, choose the earlier option, Therefore, Activity C is the best option.

Can you please explain what is the logic behind shortening the ‘earlier’ activity in this case.. Why not Activity ‘H’ or we just need to remember this as mentioned in exam.

Thanks!
Attachments
Q6.png
Q6.png (162.5 KiB) Viewed 90 times
manishpn
Expert
Expert
Posts: 2392
Joined: Sat Jan 04, 2014 3:55 pm

Re: Schedule Mgmt

Postby manishpn Sat May 12, 2018 4:55 pm

not sure what is the question , post entire questions or refer to which section in rita is the question coming from
if you want to shorten the duration of the project, you should try to shorten the activities on CP.
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
KaurP
Posts: 17
Joined: Wed Apr 04, 2018 4:08 am

Re: Schedule Mgmt

Postby KaurP Sat May 19, 2018 11:19 am

Q 23 Rita Ed-8 Schedule Mgmt.

Question:

In the attached network diagram Critical path is C, E,H,End. If you need to shorten the duration of project, which activity would you try to shorten?

Options:
Activity B
Activity D
Activity H
Activity C

Answer description- In this case activity C and H both are on critical path. If you have choice choose, all the things being equal, choose the earlier option, Therefore, Activity C is the best option.

My question is why can't we select or shorten activity ‘H’ in this case as it is also on CP or what is the logic behind selecting the activity which appears first on critical path in such a case, as stated in answer description above.
KaurP
Posts: 17
Joined: Wed Apr 04, 2018 4:08 am

Re: Schedule Mgmt

Postby KaurP Tue May 22, 2018 4:23 am

Q 23 Rita Ed-8 Schedule Mgmt. P-243

Awaiting your response.