by signor_rk
Fri Sep 05, 2014 7:24 am
Forum: PMP® Open Forum
Topic: Initiating Phase Question
Replies: 4
Views: 754

Re: Initiating Phase Question

You may refer to Page # 54 , Para 3.3 of PMBOK5 , which states that "Although the project management team may help write the project charter , this standard assumes that business case assessment , approval , and funding are handled externally to the project boundaries (Figure 3-4)." That m...
by signor_rk
Fri Sep 05, 2014 5:16 am
Forum: PMP® Open Forum
Topic: Initiating Phase Question
Replies: 4
Views: 754

Re: Initiating Phase Question

Let us sort out as follows: A. Create the Project Scope Statement => This is done later in the Planning process Group in the Define Scope Process B. Stakeholder analysis => This is used as a Tool & Technique in the Initiating Process Group in the Identify Stakeholder Process C. Product analysis ...
by signor_rk
Wed Sep 03, 2014 2:23 pm
Forum: PMP® Open Forum
Topic: Closing Phase Question
Replies: 3
Views: 728

Re: Closing Phase Question

I choose Option # D.Get formal acceptance, close the contract, write lessons learned, release the team
by signor_rk
Wed Sep 03, 2014 2:19 pm
Forum: PMP® Open Forum
Topic: Just in time(JIT)
Replies: 2
Views: 500

Re: Just in time(JIT)

This is a Japanese inventory control technique. In this technique , to create higher focus on quality on the few items that are in inventory , very low or no excess inventory is maintained. For example , in a construction project , if you need say 150,000 MT of Cement for a particular important stru...
by signor_rk
Tue Sep 02, 2014 4:26 pm
Forum: PMP® Open Forum
Topic: Crashing or Fast tracking
Replies: 2
Views: 635

Re: Crashing or Fast tracking

Since the Company has already invested a lot , so in order to complete the project on time with the EXISTING RESOURCES , Fast Tracking is the best option in this case.
by signor_rk
Tue Sep 02, 2014 4:16 pm
Forum: PMP® Open Forum
Topic: Communication Channel
Replies: 4
Views: 755

Re: Communication Channel

I think the description of the sentence matters most. In this particular question the PM needs to be considered while counting for the number of team members for communication channels.
by signor_rk
Tue Sep 02, 2014 4:08 am
Forum: PMP® Open Forum
Topic: Question of critical path
Replies: 5
Views: 1131

Re: Question of critical path

Thanks Saket for the confirmation. Thanks for such a good question too @nagarwal ... :)
by signor_rk
Mon Sep 01, 2014 5:19 pm
Forum: PMP® Open Forum
Topic: Control Chart Question
Replies: 5
Views: 838

Re: Control Chart Question

Customer's requirement should be given the TOP most priority , what I know so far.
by signor_rk
Mon Sep 01, 2014 5:11 pm
Forum: PMP® Open Forum
Topic: Question of critical path
Replies: 5
Views: 1131

Re: Question of critical path

Can someone please review my calculation as in the attached sketch :
by signor_rk
Sat Aug 30, 2014 8:43 am
Forum: PMP® Open Forum
Topic: Control Chart Question
Replies: 5
Views: 838

Re: Control Chart Question

Option # A. Deliver them to the customer.
Since the upper specification limit provided by the Customer is 15.2 cm , the last aluminium dowels produced with 15.2 cm long have no problem with Customer's specification limit. So it can be delivered without any hesitation.
by signor_rk
Sat Aug 30, 2014 8:28 am
Forum: PMP® Open Forum
Topic: Fixed price Incentive fee
Replies: 1
Views: 466

Re: Fixed price Incentive fee

Option # A is chosen.
Here,
Actual cost incurred =$48,000 which is below the Target cost of $50,000 ; So , there is a saving in cost of $2,000. Target Profit=$5,000;
Final price = $48,000 + $5,000 + $2000*50%
= $54,000.
by signor_rk
Sat Aug 30, 2014 8:03 am
Forum: PMP® Open Forum
Topic: Question on change?
Replies: 6
Views: 1170

Re: Question on change?

The best possible Option is the Option # 1 1. The lack of clear instructions from project sponsor. The other options follow thereafter.
 
by signor_rk
Sat Aug 30, 2014 6:06 am
Forum: PMP® Open Forum
Topic: Question
Replies: 2
Views: 615

Re: Question

What I have observed in a solution for this question is that this is actually OUT OF PMBOK5 !!!
There , the chosen Option is Option # 1. project team members' professional responsibility.
by signor_rk
Sat Aug 30, 2014 5:23 am
Forum: PMP® Open Forum
Topic: Question on EVM
Replies: 3
Views: 700

Re: Question on EVM

But one solution says that we need to choose the Option # 1. The project has a cost overrun of $500,000. The explanation is something like this: Since the project is 60% completed, so with the original budget, the earned value for the work that has been done should be 60% *$5,000,000 = $3,000,000. T...
by signor_rk
Thu Aug 28, 2014 5:20 pm
Forum: PMP® Open Forum
Topic: Thanks a Million, I cleared PMP Certification Examination
Replies: 9
Views: 1965

Re: Thanks a Million, I cleared PMP Certification Examinatio

Thanks Sudhansu for sharing your LL .... it really matters for PMP aspirant like me. Good Luck for your future endeavors.
by signor_rk
Thu Aug 28, 2014 5:09 pm
Forum: PMP® Open Forum
Topic: Cost
Replies: 3
Views: 805

Re: Cost

Option # B. When the product is being designed
by signor_rk
Wed Aug 27, 2014 6:24 pm
Forum: PMP® Open Forum
Topic: Scope Management
Replies: 3
Views: 791

Re: Scope Management

Possible Option is Option # D Template , but since Template is not a tool , rather it is an OPA , then the next possible Option is # A Decomposition.
by signor_rk
Tue Aug 26, 2014 5:53 am
Forum: PMP® Open Forum
Topic: Project Management Process
Replies: 2
Views: 552

Re: Project Management Process

What I understand so far is :
In Develop Project Team process , assessment for performance is done for the overall project team , whereas , in the Close Project or Phase process , it is done for individual Project Team members.
by signor_rk
Mon Aug 25, 2014 2:14 pm
Forum: PMP® Open Forum
Topic: Question on Tools & Techniques of Risk Control :
Replies: 3
Views: 581

Re: Question on Tools & Techniques of Risk Control :

Tools & Techniques for Control Risk process are :
1. Risk reassessment
2. Risk audit
3. Variance and trend Analysis
4. Technical performance measurement
5. Reserve analysis
6. Meetings
So , option # C , Sensitivity analysis is NOT the Tools & Technique of this process.
by signor_rk
Sun Aug 24, 2014 4:57 am
Forum: PMP® Open Forum
Topic: Estimate Cost Tool
Replies: 5
Views: 722

Re: Estimate Cost Tool

That means the referred book is giving more emphasis on his earlier expertise of similar work executed and the method of quick estimating which leads to an Analogous Estimating.
by signor_rk
Sun Aug 24, 2014 2:12 am
Forum: PMP® Open Forum
Topic: Estimate Cost Tool
Replies: 5
Views: 722

Re: Estimate Cost Tool

Expert Judgement as he is basically looking at the equipment and specs , budget , which means he is applying this tool for ESTIMATE ACTIVITY RESOURCES.
by signor_rk
Sat Aug 23, 2014 11:42 am
Forum: PMP® Open Forum
Topic: Question on Crashing:
Replies: 4
Views: 748

Re: Question on Crashing:

Option # A Reallocation of existing resources or assigning additional resources to the project.
by signor_rk
Fri Aug 22, 2014 3:10 pm
Forum: PMP® Open Forum
Topic: Risk Management
Replies: 2
Views: 607

Re: Risk Management

Nice explanation. Thanks Namita.
by signor_rk
Fri Aug 22, 2014 5:15 am
Forum: PMP® Open Forum
Topic: Risk Management
Replies: 3
Views: 767

Re: Risk Management

I do agree with Umesh. Nice explanation.
by signor_rk
Thu Aug 21, 2014 8:19 am
Forum: PMP® Open Forum
Topic: Analytical Techniques
Replies: 2
Views: 914

Re: Analytical Techniques

Option # B , i.e., Regression and Trend Analysis
by signor_rk
Thu Aug 21, 2014 5:59 am
Forum: PMP® Open Forum
Topic: Control schedule
Replies: 5
Views: 1103

Re: Control schedule

I also downloaded the ITTO excel file. This is quite handy indeed. Thanks Saket for that.
by signor_rk
Wed Aug 20, 2014 10:54 am
Forum: PMP® Open Forum
Topic: Control schedule
Replies: 5
Views: 1103

Re: Control schedule

On the other hand , the new terms as per PMBOK5 for the following processes are :
Perform Quality Control (OLD) ...... Control Quality (NEW)
Monitor and Control Risks (OLD) ..... Control Risk (NEW)
This should be okey ...
by signor_rk
Tue Aug 19, 2014 2:12 pm
Forum: PMP® Open Forum
Topic: Thanks a Million, I cleared PMP Certification Examination
Replies: 9
Views: 1965

Re: Thanks a Million, I cleared PMP Certification Examinatio

wow !!! That's great !!! Congrats to you on achieving PMP !!!
by signor_rk
Tue Aug 19, 2014 12:43 pm
Forum: PMP® Open Forum
Topic: Question on Earned Value
Replies: 3
Views: 671

Re: Question on Earned Value

hi ,

As the ETC is calculated based on bottom up summation , so we need to apply the following formula for EAC:
EAC = AC + ETC Bottom up
= $ 25 , 000 + $ 75 , 000
= $ 100 , 000
So , Option # B , i.e., $ 100 , 000
by signor_rk
Tue Aug 19, 2014 8:01 am
Forum: PMP® Open Forum
Topic: Question....
Replies: 3
Views: 580

Re: Question....

It might be the Functional Manager who is instructing the 1st Team member to pull the 2nd Team member out off the Project to perform another work. So Option # D , i.e., Functional Manager ... :)
by signor_rk
Mon Aug 18, 2014 7:20 am
Forum: PMP® Open Forum
Topic: Calculate VAC
Replies: 5
Views: 831

Re: Calculate VAC

Here , EAC = AC + BAC - EV
= 275 + 500 - 250
= 525
So , VAC = BAC - EAC
= 500 -525
= - 25
Option # A , i.e, -25
by signor_rk
Mon Aug 18, 2014 5:55 am
Forum: PMP® Open Forum
Topic: Organization form
Replies: 4
Views: 839

Re: Organization form

hi ,

If you refer to Table 2-1 , Page # 22 , PMBOK5 , you will notice that in a FUNCTIONAL Organization the PM has LITTLE or NO authority at all.
by signor_rk
Sat Aug 16, 2014 3:25 pm
Forum: PMP® Open Forum
Topic: Risk Response Strategy
Replies: 2
Views: 611

Re: Risk Response Strategy

In my opinion , Option # C , i.e., Risk Acceptance . Since the PM is not taking any proactive action and just waiting the Risk .i.e., STRIKE to happen. In the meantime , he might be documenting the Strategy to tackle the Risk , if it occurs on the holiday season based on the prior information and th...
by signor_rk
Sat Aug 16, 2014 2:56 pm
Forum: PMP® Open Forum
Topic: Organization form
Replies: 4
Views: 839

Re: Organization form

Option # A i.e., Functional since the PM has LITTLE authority to assign the resources and they are already occupied in PROCESS related (not Project related) work.
Thanks
by signor_rk
Sat Aug 16, 2014 4:24 am
Forum: PMP® Exam Lessons – Success Stories
Topic: Yesterday. I cleared my PMP.
Replies: 9
Views: 1908

Re: Yesterday. I cleared my PMP.

Congrats Lax on achieving your PMP!!! :)
by signor_rk
Thu Aug 14, 2014 5:14 am
Forum: PMP® Open Forum
Topic: Ishikawa
Replies: 2
Views: 606

Re: Ishikawa

"what could cause potential risks on his project" , that means Mike is still in Planning and in the IDENTIFY RISK Process. But if the sentence started like this " what could have caused / what could have been the potential risks on his project" , then it will direct to Control Qu...
by signor_rk
Thu Aug 14, 2014 4:38 am
Forum: PMP® Open Forum
Topic: Decomposition
Replies: 2
Views: 685

Re: Decomposition

In WBS by decomposition deliverables are broken down into smaller Work packages , whereas in Define Activities deliverables/workpackages are further broken down into manageble work activities. I hope my explanation should be OK. So option #(B) is correct. You may refer Page#151 , Para.6.2.2.1 of PMB...
by signor_rk
Thu Aug 14, 2014 4:07 am
Forum: PMP® Open Forum
Topic: FF-2 Duration
Replies: 3
Views: 581

Re: FF-2 Duration

Is it 7 Days ?
by signor_rk
Tue Aug 12, 2014 12:45 pm
Forum: PMP® Open Forum
Topic: Question on Stakeholder conflict
Replies: 10
Views: 1360

Re: Question on Stakeholder conflict

I got it from PMBOK5. Thanks Namita. Earlier quote" Schedule, Priorities, Resources, Technical Beliefs, Admin Policies and Procedures, Project Costs and Personality" might be from an Older Version of PMBOK.
by signor_rk
Tue Aug 12, 2014 12:17 pm
Forum: PMP® Exam Lessons – Success Stories
Topic: I have cleared PMP exam
Replies: 13
Views: 2333

Re: I have cleared PMP exam

Congrats !!!
by signor_rk
Tue Aug 12, 2014 1:55 am
Forum: PMP® Open Forum
Topic: Question on Stakeholder conflict
Replies: 10
Views: 1360

Re: Question on Stakeholder conflict

I could not find the line from page # 282 of PMBOK5 as mentioned by @nagarwal. Thanks Saket for the timely input.
by signor_rk
Sun Jul 27, 2014 11:19 am
Forum: PMP® Open Forum
Topic: Initiation
Replies: 6
Views: 768

Re: Initiation

Option # (C) Identify Stakeholders is the right choice as the Project/Project Manager has been authorized i.e., Develop Project Charter Process is completed.
by signor_rk
Sun Jul 27, 2014 11:06 am
Forum: PMP® Open Forum
Topic: Stakeholder management Q3
Replies: 3
Views: 563

Re: Stakeholder management Q3

Option # (C) Stakeholder satisfaction is the right choice. (PMBOK5 Page#391)
by signor_rk
Sat Jul 26, 2014 3:46 pm
Forum: PMP® Open Forum
Topic: Biometric enabled Check-in for Test
Replies: 3
Views: 996

Re: Biometric enabled Check-in for Test

That's fine. I think Namita is right.For locating my Test Center , I will be visiting the Prometric Test Center one day before the test. I may discuss there on that day if required. Anyway thanks Mandarapu , thanks Namita for your comments & suggestions.
by signor_rk
Thu Jul 24, 2014 11:18 am
Forum: PMP® Open Forum
Topic: Biometric enabled Check-in for Test
Replies: 3
Views: 996

Biometric enabled Check-in for Test

Today I completed my consent for the "Biometric Enabled Check-in" for the PMP Exam online. (By mistake I took this option :) ). Anyway , should I have to provide any additional info or my Photograph prior to taking the test to PMI/Prometric ? So far I know , photograph and finger print wil...
by signor_rk
Mon Jul 21, 2014 11:21 am
Forum: PMP® Open Forum
Topic: Q1 on Closing....
Replies: 3
Views: 575

Re: Q1 on Closing....

Though I am do not have Rita's book for reference , as per PMBOK5 , I think it should be the Option # 1 , Close Project or Phase (Ref Page# 28).
by signor_rk
Mon Jul 21, 2014 4:06 am
Forum: PMP® Open Forum
Topic: Quality control activities
Replies: 4
Views: 731

Re: Quality control activities

Option# (D) Focus Groups is the odd one , which is related to Collect Requirement Process group.
by signor_rk
Mon Jul 21, 2014 3:39 am
Forum: PMP® Open Forum
Topic: Question for Discussion-Plan Scope Management
Replies: 4
Views: 645

Re: Question for Discussion-Plan Scope Management

Let us remove the odd ones first: Options # B & C are EEFs , so removed. Though Options #(A) & (D) are OPAs , still Option #(A) Issue and defect identification procedure will not appear in this Planning stage of Project Scope Management. Rather it will appear in the Manage Stakeholder Engage...