Search found 265 matches

by nazrulq
Thu Sep 07, 2017 5:09 am
Forum: PMP® Open Forum
Topic: Change Management procedure
Replies: 9
Views: 1612

Change Management procedure

I am sharing my view points regarding change management procedure as now a days lots of situational questions regarding change management issues are coming in PMP exam. The procedures in order is listed below: 1. Evaluation of Changes a. PM by himself. b. With Project Team 2. Identify Options. a. Pr...
by nazrulq
Thu Sep 07, 2017 4:09 am
Forum: PMP® Open Forum
Topic: Communication Channel
Replies: 4
Views: 1217

Communication Channel

Q: You are managing a team of 10 people . How many Communication Channel you need? Answer : 1. 55 2. 45 3. 35 4.60 Answer should be Option 1 or Option 2 . How to determine if question does n't say about inclusion or exclusion of Project Manager. What Should be by default situation! Can Manish explai...
by nazrulq
Thu Sep 07, 2017 3:45 am
Forum: PMP® Open Forum
Topic: Looking for a Study partner for PMP
Replies: 17
Views: 4079

Re: Looking for a Study partner for PMP

Interested.
by nazrulq
Wed Sep 06, 2017 8:36 pm
Forum: PMP® Open Forum
Topic: Saket Bansal Sir's name in PMBOK 6
Replies: 4
Views: 1036

Re: Saket Bansal Sir's name in PMBOK 6

Congratulations Saket ! Deserved acknowledgment. I do n't know whether they add Risk Management in execution. That should be changed too. The renamed Time Management to Schedule Management and Human Resource Management to Resource Management and add Agile Method. Yes Just check they have 49 processe...
by nazrulq
Wed Sep 06, 2017 8:31 pm
Forum: PMP® Open Forum
Topic: time menagement Q/A
Replies: 2
Views: 748

Re: time menagement Q/A

Q 13. The answer I think, should be lag time. Total Float : The amount of time that a schedule activity can be delayed or extended from its early start without delaying project finish date or violating schedule constraint. Lag : The amount of time whereby successor activity is required to be delayed...
by nazrulq
Mon Aug 28, 2017 4:10 am
Forum: PMP® Open Forum
Topic: Conduct Procurement
Replies: 2
Views: 695

Conduct Procurement

Question :Larry is the project manager and working with procurement department of his organization to do procurement for his project. Procurement department said these are usual commodities and same has been procured many time. Also as this has been procured multiple times, generally they receive re...
by nazrulq
Mon Aug 28, 2017 1:10 am
Forum: PMP® Open Forum
Topic: Communication/ Stakeholder Manaagement
Replies: 1
Views: 635

Communication/ Stakeholder Manaagement

Q.You are working on project which automates the service call handing process of one car servicing company, in the mid of the project, marketing team realized that they are also getting impacted with this automation and provided set of requirements to be included in this project , what is the BEST t...
by nazrulq
Mon Aug 28, 2017 1:06 am
Forum: PMP® Open Forum
Topic: Return of Investment (ROI)
Replies: 2
Views: 879

Re: Return of Investment (ROI)

Rita's book does n't say anything for that but Andy crowe is! Sometimes you need you read more book.
PMP exam is different . I do n't see any thing about ROI usually its a wrong choice in the exam!
ROI should be in % . Is there any range while selecting project!

Thanks Manish!
by nazrulq
Mon Aug 28, 2017 1:01 am
Forum: PMP® Open Forum
Topic: Make or Buy Analysis
Replies: 11
Views: 2239

Re: Make or Buy Analysis

Cleared thanks!
by nazrulq
Mon Aug 28, 2017 1:00 am
Forum: PMP® Open Forum
Topic: Manage Project Team
Replies: 2
Views: 771

Re: Manage Project Team

Thank You! Not cleared when to use Empathy!
by nazrulq
Sat Aug 26, 2017 11:27 pm
Forum: PMP® Open Forum
Topic: Make or Buy Analysis
Replies: 11
Views: 2239

Re: Make or Buy Analysis

Question mentioned $50 per month and expecting 1000 users per month.
My answer after 2.3 month make decision ( My mistake Sorry! ) would be fruitfull.

Thank You Manish for catching my mistake.
by nazrulq
Sat Aug 26, 2017 10:53 pm
Forum: PMP® Open Forum
Topic: Return of Investment (ROI)
Replies: 2
Views: 879

Return of Investment (ROI)

For which types of Projects (Is that all Project) ROI is needed. I guess it is not a Project Selection Criteria!

Can Manish Explain Please !
by nazrulq
Sat Aug 26, 2017 10:38 pm
Forum: PMP® Open Forum
Topic: Manage Project Team
Replies: 2
Views: 771

Manage Project Team

Question : Project Manager has problems in managing few team members in his team. Project Manager has problem managing him in desired direction.Based on Daniel Golman's mixed model for emotional intelligence the team members have to work on: 1. Self-awareness 2. Empathy 3.Social Skills 4.Self Regula...
by nazrulq
Sat Aug 26, 2017 4:32 am
Forum: PMP® Open Forum
Topic: How to process changes during an initial stage of the project?
Replies: 13
Views: 4275

Re: How to process changes during an initial stage of the project?

I think Option C is the current choice. First PM has to analyze the situation about change management .
by nazrulq
Fri Aug 25, 2017 6:53 pm
Forum: PMP® Open Forum
Topic: Make or Buy Analysis
Replies: 11
Views: 2239

Re: Make or Buy Analysis

Let me explain if I have understood the question clearly Option 1 (To Make) To make in house , cost of making the module is =$ 50000 Cost of Maintainance is 30000/Month Option2 (To Buy) $50/Month , No of people expected =1500/Month Maintainance =1500/Month let the number of months = M When make and ...
by nazrulq
Tue Aug 22, 2017 5:43 am
Forum: PMP® Open Forum
Topic: Calculation of Standard Deviation from various Data
Replies: 0
Views: 927

Calculation of Standard Deviation from various Data

Following data points are used 5, 6, 7,8,9, 10. from that point calculate STD ( Standard Deviation)

Mean = 5 + 6 + 7+8 +9 + 10 = 45/ 6 =7.5

Variance = (7.5-5) ² + ( 7.5-6)² +(7.5-7)²+ (7.5-8)²+ (7.5-9)²+(7.5-10)² = 17.5

Std = Sqrt (Var)= Sqrt (Variances) = 4.18
by nazrulq
Tue Aug 22, 2017 5:28 am
Forum: PMP® Open Forum
Topic: Communication Channels!
Replies: 1
Views: 737

Communication Channels!

Please advise in calculating communication channel n. Sometimes exam does n't give clue whether PM is included or not!

Thanks.
by nazrulq
Tue Aug 22, 2017 5:15 am
Forum: PMP® Open Forum
Topic: Key Perfomance Indicator (KPI), Exam Content Outline (June 2015)
Replies: 2
Views: 980

Key Perfomance Indicator (KPI), Exam Content Outline (June 2015)

What is KPI? Is KPI lagging factor or leading factor! KPI - Is the key performance indicator or the organization showing organizations performance. KPI use to be lagging factor not leading factor. Generally, SMART techniques applied to KPI - S pecific, M easurable, A ttainable, R ealistic and T ime-...
by nazrulq
Tue Aug 22, 2017 4:51 am
Forum: PMP® Open Forum
Topic: Change Log, Issue log & Change Request
Replies: 10
Views: 6132

Re: Change Log, Issue log & Change Request

Option D is the correct answer, I guess! Approved Change request which is approved by change control board (CCB) to be incorporated in the change log. If stakeholder asked for the information, they can be referred to Change log where approved change request is noted. stakeholders concerns are record...
by nazrulq
Sat Aug 19, 2017 3:36 am
Forum: PMP® Open Forum
Topic: Scope Management Mockups
Replies: 3
Views: 1137

Re: Scope Management Mockups

Quality Management Plan is not required at the level of creation of Scope Management Plan. May be high level quality management plan is needed to be required but detail level quality requirement is not necessary as progressive elaboration might required later! Hopefully it justifies! Manish can expl...
by nazrulq
Sat Aug 19, 2017 3:09 am
Forum: PMP® Open Forum
Topic: Project Time Management
Replies: 7
Views: 1667

Re: Project Time Management

Schedule Management Plan is a subsidiary plan of Project Management Plan. Schedule Management Plan is not a input rather Project Management Plan is a input of Plan Schedule Management. Output of that is Schedule Management Plan. In fact Project Management plan is the input of all 8 Management Plan e...
by nazrulq
Thu Aug 17, 2017 6:01 am
Forum: PMP® Open Forum
Topic: Project Time Management
Replies: 7
Views: 1667

Re: Project Time Management

There are other Plans to which feed into Project Management Plan
1. Stakeholder Management Plan
2. Integration management Plan.
3. Process Improvement Plan. (Subsidiary Plan of Quality Management Plan)
4. Requirement Management Plan ( Subsidiary Plan of Scope Management Plan)
by nazrulq
Tue Aug 15, 2017 5:53 pm
Forum: PMP® Open Forum
Topic: Requirement documentation VS traceabilty matrix
Replies: 4
Views: 1244

Re: Requirement documentation VS traceabilty matrix

So far my understanding requirement documentations are all of the documents needed for the project and Requirement Traceability Matrix is a grid or table where all of the requirements are listed from the beginning of the project till the deliverable of the product in Matrix or Tabulated format could...
by nazrulq
Tue Aug 15, 2017 6:15 am
Forum: PMP® Open Forum
Topic: Collect Requirements in Project Scope Management
Replies: 2
Views: 883

Re: Collect Requirements in Project Scope Management

Focus Group : An Elicitation techniques that brings pre qualified stakeholder and SME to learn about their expectations and attitude about the proposed product , service or result. Focus group is a tools and techniques of collecting stakeholders requirement. Facilitation Techniques / Workshop: This ...
by nazrulq
Sat Aug 12, 2017 6:00 am
Forum: PMP® Open Forum
Topic: Assumptions and Constraints
Replies: 1
Views: 756

Assumptions and Constraints

In PMBOK page -124 described about Project Charter and Project Scope Statement, Assumption and Constraint is not the part of Project Charter but in PMBOK page no: 72 described project charter documents assumptions and constrain. there could be a question whether those are part of Project Charter in ...
by nazrulq
Fri Aug 11, 2017 10:44 pm
Forum: PMP® Open Forum
Topic: Project Staatus
Replies: 16
Views: 2968

Re: Project Staatus

Sure. We can discuss!
by nazrulq
Wed Aug 09, 2017 4:54 am
Forum: PMP® Open Forum
Topic: integration management Q&A
Replies: 6
Views: 1421

Re: integration management Q&A

Justification is understandable but question has asked for least likely option. Phase end review rarely cancelled the project. Try to mitigate or change anything in terms of budget , scope or schedule etc.
by nazrulq
Tue Aug 08, 2017 5:19 am
Forum: PMP® Exam Lessons – Success Stories
Topic: Passed PMP like Achieved a Milestone
Replies: 3
Views: 1861

Re: Passed PMP like Achieved a Milestone

Congratulations ! Great Success!
by nazrulq
Mon Aug 07, 2017 10:16 pm
Forum: PMP® Open Forum
Topic: integration management Q&A
Replies: 6
Views: 1421

Re: integration management Q&A

I think cancel the project is the least likely to have but at the phase end review, it happens.
by nazrulq
Mon Aug 07, 2017 10:13 pm
Forum: PMP® Open Forum
Topic: Project Staatus
Replies: 16
Views: 2968

Re: Project Staatus

To pass PMP is difficult as the answers are debatable! I do n't know how the match with PMI-isms.

Thanks.
by nazrulq
Mon Aug 07, 2017 5:09 am
Forum: PMP® Open Forum
Topic: Project Staatus
Replies: 16
Views: 2968

Re: Project Staatus

Please provide book reference!
by nazrulq
Mon Aug 07, 2017 5:04 am
Forum: PMP® Open Forum
Topic: Practice Question
Replies: 2
Views: 861

Re: Practice Question

First it is to find when the time will be equal , Let the number of months are D.

Vendor A

20000 + 4000D

Vendor B

10000+ 5000D

20000 +4000D = 10000+5000D

1000D = 10000
D=10 Months

After 10 months using vendor, A will be profitable for maintenance!
by nazrulq
Mon Aug 07, 2017 4:29 am
Forum: PMP® Open Forum
Topic: PMBOK new edition
Replies: 1
Views: 802

Re: PMBOK new edition

Till the end of this year PMBOK 5th Edition should be good! If you can clear it by this year 5th edition is good enough.
by nazrulq
Sat Aug 05, 2017 6:00 am
Forum: PMP® Open Forum
Topic: PMP Math / Change Management/ Monitor and Control Webinars
Replies: 1
Views: 681

PMP Math / Change Management/ Monitor and Control Webinars

Now a days maximum 8 to 10 question about PMP math. Those are EVM , Schedule, and ETC or EAC pretty straight forward. THose does n't play role passing the exam. Brief knowledge of change management and monitor and control is giving guarantee to pass. If webinar on change management and monitor and c...
by nazrulq
Sat Aug 05, 2017 5:51 am
Forum: PMP® Open Forum
Topic: Project Staatus
Replies: 16
Views: 2968

Re: Project Status

The Question is given SPI = 0.9 , CPI =1.0 and the closing process group but SPI=.9, the project is delayed not as per closing date. Project Manager is giving earn value management status to the sponsor near to closing. It is not wise to call Project is completed as SPI< 1 but on budget. Manish ther...
by nazrulq
Wed Aug 02, 2017 6:52 am
Forum: PMP® Open Forum
Topic: Monitor and Control
Replies: 1
Views: 603

Closing

Can Manish explain in order the approaches in solving problem those often comes in the exam nowadays rather that direct input, ITTO and output and as well as process groups! kind of what to do next or what PM should do?

Thanks
by nazrulq
Wed Aug 02, 2017 6:51 am
Forum: PMP® Open Forum
Topic: Monitor and Control
Replies: 1
Views: 603

Monitor and Control

Can Manish explain in order the approaches in solving problem those often comes in the exam now a days rather that direct input, ITTO and output and as well as process groups! kind of what to do next or what PM should do?

Thanks
by nazrulq
Wed Aug 02, 2017 6:51 am
Forum: PMP® Open Forum
Topic: Execution
Replies: 0
Views: 755

Execution

Can Manish explain in order the approaches in solving problem those often comes in the exam nowadays rather that direct input, ITTO and output and as well as process groups! kind of what to do next or what PM should do?

Thanks
by nazrulq
Wed Aug 02, 2017 6:50 am
Forum: PMP® Open Forum
Topic: Planning
Replies: 1
Views: 576

Planning

Can Manish explain in order the approaches in solving problem those often comes in the exam nowadays rather that direct input, ITTO and output and as well as process groups! kind of what to do next or what PM should do? As you know questions are not straight forward like Rita, Izenbridge or Scristop...
by nazrulq
Wed Aug 02, 2017 6:48 am
Forum: PMP® Open Forum
Topic: Initiation
Replies: 1
Views: 650

Initiation

Can Manish explain in order the approaches in solving problem those often comes in the exam nowadays rather that direct input, ITTO and output and as well as process groups! kind of what to do next or what PM should do?

Thanks
by nazrulq
Tue Aug 01, 2017 2:52 am
Forum: PMP® Open Forum
Topic: Project Staatus
Replies: 16
Views: 2968

Re: Project Staatus

Just want to know where I can get evidence the project is completed!
by nazrulq
Tue Aug 01, 2017 1:48 am
Forum: PMP® Open Forum
Topic: Project Staatus
Replies: 16
Views: 2968

Project Staatus

Question : During the completion of project, sponsor asked you the send project updates as record. CPI= 1 and SPI =.9 which one under following you will give the sponsor as updates of the project. Answer: 1. The project is completed and on Budget and behind the schedule. 1. The project is not comple...
by nazrulq
Mon Jul 31, 2017 12:42 am
Forum: PMP® Open Forum
Topic: Kanban System!
Replies: 1
Views: 809

Re: Kanban System!

Can some body differentiate Lean , Kanban, Six Sigma, Agile , kaizen and Water fall in Quality Management ! As per my understanding Waterfall - Plan Driven, Sequential. Kanban -Pulling System. Six Sigma- Remove Variability. Agile - Iteration. Lean - Remove waste Kaizen - Continuous improvement Can ...
by nazrulq
Mon Jul 31, 2017 12:32 am
Forum: PMP® Open Forum
Topic: Analogous Estimate
Replies: 2
Views: 843

Re: Analogous Estimate

I think exam will not be confusing.

Option 3 is the best choice.

Thank you.
by nazrulq
Sun Jul 30, 2017 5:02 am
Forum: PMP® Open Forum
Topic: Kanban System!
Replies: 1
Views: 809

Kanban System!

Can some body differentiate Lean , Kanban, Six Sigma, Agile , kaizen and Water fall in Quality Management ! As per my understanding Waterfall - Plan Driven, Sequential. Kanban -Pulling System. Six Sigma- Remove Variability. Agile - Iteration. Lean - Remove waste Kaizen - Continuous improvement Can M...
by nazrulq
Sat Jul 29, 2017 8:10 pm
Forum: PMP® Open Forum
Topic: Analogous Estimate
Replies: 2
Views: 843

Analogous Estimate

This is to let you know and confirm the right choice. That topic has been discussed earlier.Just to clarify from Manish or Saket! :D Here is the question: Question :Which one of the following would be best described as Analogous Estimates : a. Pert Estimate. b. Three Point Estimate with Simple Avera...
by nazrulq
Fri Jul 28, 2017 3:48 pm
Forum: PMP® Open Forum
Topic: Cost Management Practice
Replies: 3
Views: 1164

Re: Cost Management Practice

I think C is the correct answer. It is described as Estimate at completion.

Thanks.
by nazrulq
Thu Jul 27, 2017 11:24 pm
Forum: PMP® Open Forum
Topic: Process Group wise
Replies: 5
Views: 1234

Re: Process Group wise

I do n't think over 85% will give you guarantee to PASS. I saw people failed getting over 90% and passed barely got 70%. Depends on your concentration on exam day and how well you understand the concept also well you interpret the questions and eliminate the wrong choice.
by nazrulq
Thu Jul 27, 2017 11:18 pm
Forum: PMP® Open Forum
Topic: Earned Value Management
Replies: 2
Views: 990

Re: Earned Value Management

Actual cost is the money you have spend or cost incurred during the certain time of the project . Denotes as AC CV =EV-AC ;CV= Cost Variance Earn Value is the work done till the certain time of project in terms of $ amount. Sum of the planned value of completed work usually denotes as EV SV= EV-PV; ...
by nazrulq
Thu Jul 27, 2017 4:30 pm
Forum: PMP® Open Forum
Topic: Parametric Estimates
Replies: 2
Views: 1166

Re: Parametric Estimates

According to Saket's Video Both Parametric and Analogous Estimates are Top Down Estimates. Analogus Estimates base on previous similar project while Parametric Estimates based on historical report or rate/sq.ft or linear feet. I have seen anything in PMBOK refers Analogous Estimating is only Top Dow...

Go to advanced search