Search found 282 matches

by coolpmp69
Fri May 08, 2015 2:28 pm
Forum: PMP® Open Forum
Topic: Webinar on Change Management : Poll 1
Replies: 3
Views: 1618

Re: Webinar on Change Management : Poll 1

You need to have a formal CR to modify any proj.docs. so the answer is yes
by coolpmp69
Fri May 08, 2015 2:27 pm
Forum: PMP® Open Forum
Topic: work performance data/information
Replies: 4
Views: 2519

Re: work performance data/information

Also, stakeholders normally don't understand what do you mean by CPI/TCPI >1 or <1 or new estimate to complete unless it is explicitly reported in the format that is understood. So these are all raw data, so the correct answer should be WPD.
by coolpmp69
Fri May 08, 2015 2:24 pm
Forum: PMP® Open Forum
Topic: WPD & WPD
Replies: 3
Views: 2378

Re: WPD & WPD

The correct answer is work performance data. WPD is the raw/primary observation/data gathered during project execution. These data will be the lowest level and need to further analyzed/formatted. In the given question, team is collecting number and the nature of defects which is raw data again so th...
by coolpmp69
Thu May 07, 2015 2:59 pm
Forum: PMP® Open Forum
Topic: Webinar on Change Management : Poll 3
Replies: 11
Views: 3766

Re: Webinar on Change Management : Poll 3

True
by coolpmp69
Wed May 06, 2015 1:30 pm
Forum: PMP® Open Forum
Topic: ITTO's
Replies: 4
Views: 2097

Re: ITTO's

@Nidhi: When you revise PMBOK, go through the diagrams of ITTO for each process in each KA. Try to question yourself and understand why as to the listed one is an input/output. This way to can get a bigger picture and also helps you remember. Again, for tools and technique, you need to understand as...
by coolpmp69
Thu Apr 30, 2015 3:01 pm
Forum: PMP® Open Forum
Topic: another qts to think
Replies: 2
Views: 1657

Re: another qts to think

In my opinion, the correct answer is a. The team will implement immediate corrective action to bring the budget back in line Because if the project continues at the same rate, the project will complete earlier but will be over budget. So corrective action is necessary to bring the project cost back ...
by coolpmp69
Thu Apr 30, 2015 2:55 pm
Forum: PMP® Open Forum
Topic: EMV qts
Replies: 5
Views: 2468

Re: EMV qts

correct answer is b. Build with a partner with a $4.25 billion in potential return
by coolpmp69
Thu Apr 30, 2015 2:51 pm
Forum: PMP® Open Forum
Topic: change request
Replies: 6
Views: 2377

Re: change request

Whenever any stakeholder request for a change either verbally(telephonic conversation/meeting/casual conversation etc.)/in writing, PM should first document the requested change and raise a CR. This is the 1st steps in the perform integrated change control process.
by coolpmp69
Thu Apr 30, 2015 2:46 pm
Forum: PMP® Open Forum
Topic: scope validation
Replies: 4
Views: 2816

Re: scope validation

Customer is correct as PM works with customer for scope validation
by coolpmp69
Wed Apr 29, 2015 6:13 pm
Forum: PMP® Open Forum
Topic: Initiating
Replies: 6
Views: 3385

Re: Initiating

Agreed. For the given question I would choose option b. Initiating can kick off the project or a phase of the project
by coolpmp69
Wed Apr 29, 2015 4:04 pm
Forum: PMP® Open Forum
Topic: Initiating
Replies: 6
Views: 3385

Re: Initiating

@AM1969: As given in Rita's book - kick off meeting is held at the end of the planning phase (after PM plan approval) to keep all the stakeholders on the same page and formally start working/execution on the project. There is no kick off meeting in initiating phase. Normally project charter is creat...
by coolpmp69
Wed Apr 29, 2015 1:00 pm
Forum: PMP® Open Forum
Topic: direct vs fixed
Replies: 1
Views: 1228

Re: direct vs fixed

Normally lease amount is fixed for a particular duration (like 3 years, 5 years etc.) and does not change until the lease term is over. As all the employees are occupying the leased space, it cannot be directly billed to the project. So the correct answer would be fixed cost.
by coolpmp69
Mon Apr 27, 2015 12:59 pm
Forum: PMP® Open Forum
Topic: risk response
Replies: 9
Views: 4316

Re: risk response

Sharing risk response strategy will benefit both the parties. In this question, the company will benefit by increasing their business by involving community and community will get new commercial building. So the option should be 'share'
by coolpmp69
Fri Apr 24, 2015 12:58 pm
Forum: PMP® Open Forum
Topic: PMI member free resources
Replies: 1
Views: 1078

Re: PMI member free resources

You need to be a PMI member to access those resources. On PMI website, check under eReads & Reference section.
by coolpmp69
Fri Apr 24, 2015 12:56 pm
Forum: PMP® Open Forum
Topic: Procurement Mgmt
Replies: 2
Views: 1511

Re: Procurement Mgmt

I don't remember the page number but Rita talks about procurement contract type and SOW in the introduction of the Procurement KA chapter. Please refer to that section for details.
by coolpmp69
Wed Apr 22, 2015 4:35 pm
Forum: PMP® Open Forum
Topic: question
Replies: 4
Views: 2076

Re: question

Considering the ROM of -25% to 25% , first calculate the budgetary value. Let's say budgetary value = X Therefore (-25% of X) + (+25% of X) = 50% of the range. i.e. 4 million dollars Then apply next ROM of -10% to +10% to this value (-10% of 4 million) + (+10% of 4 million) =3.6 and 4.4 million doll...
by coolpmp69
Wed Apr 22, 2015 1:07 pm
Forum: PMP® Open Forum
Topic: Assumption to be made in Real Exam
Replies: 1
Views: 1325

Re: Assumption to be made in Real Exam

Assume Matrix Org if it is not stated in the question and sub-type of matrix org depends upon the given question. So understand all types of orgs.

For other questions, I would be not assume anything unless it is stated in the questions.
by coolpmp69
Wed Apr 22, 2015 1:04 pm
Forum: PMP® Open Forum
Topic: Expected question in Real Exam
Replies: 2
Views: 1683

Re: Expected question in Real Exam

PMP question database is very vast so it is difficult to predict the number of questions on formula based math or ITTO. Advice you to prepare well on these areas.
by coolpmp69
Wed Apr 22, 2015 1:02 pm
Forum: PMP® Open Forum
Topic: question
Replies: 4
Views: 2076

Re: question

Answer - Between 3.6 and 4.4 million dollars
by coolpmp69
Wed Apr 22, 2015 12:57 pm
Forum: PMP® Open Forum
Topic: question :2
Replies: 6
Views: 2678

Re: question :2

Also as per PMBOK 5 "Control Costs is the process of monitoring the status of the project to update the project costs and managing changes to the cost baseline."
Here PM is trying to analyze the impact of the change and update the baseline if needed. So it is control cost process.
by coolpmp69
Tue Apr 21, 2015 4:39 pm
Forum: PMP® Open Forum
Topic: question :2
Replies: 6
Views: 2678

Re: question :2

Answer - Control Costs
by coolpmp69
Tue Apr 21, 2015 4:33 pm
Forum: PMP® Open Forum
Topic: qts submitted
Replies: 6
Views: 2848

Re: qts submitted

Where did you get this question from? Corrective action aligns the changes as per PM plan where as preventive action reduces the probability and impact. So as per the given info - At least half of those requests were made to bring the quality of the micro texture of the road aligned with the quality...
by coolpmp69
Tue Apr 21, 2015 3:21 pm
Forum: PMP® Open Forum
Topic: qts submitted
Replies: 6
Views: 2848

Re: qts submitted

As per PMBOK5, here are the definitions of " Corrective Action- An intentional activity that realigns the performance of the project work with the project management plan. Defect Repair- An intentional activity to modify a nonconforming product or product component Preventive Action- An intenti...
by coolpmp69
Tue Apr 21, 2015 1:11 pm
Forum: PMP® Open Forum
Topic: Another pmp question
Replies: 12
Views: 6099

Re: Another pmp question

@Celine: Please see the attached image for the question reference. As Jyoti mentioned you have swapped the values of M and P. Hope the table clarifies your doubt. If you are still confused then let me know and I'll try to explain differently. The link provides the source of the question - http://www...
by coolpmp69
Mon Apr 20, 2015 1:02 pm
Forum: PMP® Open Forum
Topic: Active Listening vs Effective Listening
Replies: 2
Views: 5261

Re: Active Listening vs Effective Listening

"Active listening occurs when the listener attempts to understand as clearly as possible what the speaker says. Effective listening is attempting to understand the perspective of the speaker and empathize, not sympathize, with him or her. " This link explains active and effective listening...
by coolpmp69
Mon Apr 20, 2015 12:57 pm
Forum: PMP® Open Forum
Topic: Another pmp question
Replies: 12
Views: 6099

Re: Another pmp question

@ Celina : M vales are used to calculate the range of estimate by plugging in the formula (P+4M+O)/6 or (P+M+O)/3. The question has provided the estimate range and thus no need to calculate the same. So M value was not used. We only need to calculate SD for the path so (P-O)/6 was the correct formul...
by coolpmp69
Fri Apr 17, 2015 4:59 pm
Forum: PMP® Open Forum
Topic: question PMP
Replies: 9
Views: 3758

Re: question PMP

After re-read the question, I realized that I missed reading it and concentrated only rescheduling of the tasks. Actually there are 2 important points given in the question: 1. The VP Operations challenged that some of the critical path activities cannot be executed as scheduled as they will disturb...
by coolpmp69
Fri Apr 17, 2015 3:02 pm
Forum: PMP® Open Forum
Topic: dependency ?
Replies: 1
Views: 998

Re: dependency ?

Discretionary Project Dependencies are defined by the project team based on best practices or lessons learned from their prior experiences. Normally Discretionary Dependencies act as opportunities and are exploited for schedule compression. But sometimes wrong choice of discretionary dependencies as...
by coolpmp69
Fri Apr 17, 2015 2:50 pm
Forum: PMP® Open Forum
Topic: question PMP
Replies: 9
Views: 3758

Re: question PMP

Let's look at each option A. Analyze the impact of change - it is one of the steps but before this PM has to create CR. There is no point in evaluating the impact of the change without having CR. B. Record the issue in the issue log - True for issues but not for changes requested. So this option is ...
by coolpmp69
Thu Apr 16, 2015 7:06 pm
Forum: PMP® Open Forum
Topic: Another pmp question
Replies: 12
Views: 6099

Re: Another pmp question

Standard Deviation measures the amount of Variation from Average or Mean. Standard deviation can be zero or positive. Let's say your project involves five activities, calculating the standard deviation for each activity tells you the most likely time for its completion. So to find SD for a series of...
by coolpmp69
Thu Apr 16, 2015 5:45 pm
Forum: PMP® Open Forum
Topic: Another pmp question
Replies: 12
Views: 6099

Re: Another pmp question

To calculate the standard deviation of critical path, below are the steps 1) calculate the standard deviation of each activity, 2) take a square of standard deviation of these activities to get variance, 3) Add variance of each activity to get total variance of the path, 4) calculate the square root...
by coolpmp69
Wed Apr 15, 2015 12:49 pm
Forum: PMP® Open Forum
Topic: Influence diagram
Replies: 2
Views: 1833

Re: Influence diagram

This blog may help you to understand influence diagram
http://getpmpcertified.blogspot.com/201 ... grams.html
by coolpmp69
Tue Apr 14, 2015 12:54 pm
Forum: PMP® Open Forum
Topic: Pure risk vs business risk
Replies: 1
Views: 1768

Re: Pure risk vs business risk

Pure Risk – risk with potential loss only
ex. Fire, natural disaster

Business Risk – risk with potential loss or gain
ex. A highly skilled developer is able to work on your project enhancing your project deliverable quality and reducing your project schedule timeline
by coolpmp69
Mon Apr 13, 2015 1:14 pm
Forum: PMP® Open Forum
Topic: BCR and Time value of money
Replies: 1
Views: 1226

Re: BCR and Time value of money

The "time value of money" is a notion that a dollar today is worth more than the same dollar 5 years from now. This is nothing but Present Value (PV) So time value of money=Present Value (PV)= FV /(1+r)^n BCR = value of Benefit (revenue)/ cost This can also be expressed in terms of "t...
by coolpmp69
Fri Apr 10, 2015 12:58 pm
Forum: PMP® Open Forum
Topic: Processes - Inputs. Tools and Outputs
Replies: 3
Views: 1883

Re: Processes - Inputs. Tools and Outputs

Try to understand and ask yourself as to why items of a particular process is an input /output. This way you don't need to memorize them. In exam, you will get the mixed list of input/output for different process as options (to just to confuse the applicant) and in such scenarios your understanding ...
by coolpmp69
Thu Apr 09, 2015 7:11 pm
Forum: PMP® Open Forum
Topic: ANOTHER APPLICATION related qts
Replies: 2
Views: 1373

Re: ANOTHER APPLICATION related qts

It depends upon your preparation and confidence level as you know how best you are/have prepared. You can always submit your application and choose a exam date later.
by coolpmp69
Thu Apr 09, 2015 7:09 pm
Forum: PMP® Open Forum
Topic: Not a stk and why?
Replies: 2
Views: 1284

Re: Not a stk and why?

B. An attorney from your company’s competitor

Because a competitor cannot be your stakeholder. All other options are stakeholders
by coolpmp69
Thu Apr 09, 2015 1:33 pm
Forum: PMP® Open Forum
Topic: pota: CONTRACT
Replies: 3
Views: 1478

Re: pota: CONTRACT

Stick to the abbreviations used in PMBOK for communication otherwise it can cause confusion among readers

Regarding PTA refer to this link
http://www.izenbridge.com/blog/pmp-exam ... ssumption/
by coolpmp69
Thu Apr 09, 2015 1:08 pm
Forum: PMP® Open Forum
Topic: pota: CONTRACT
Replies: 3
Views: 1478

Re: pota: CONTRACT

what is POTA?
by coolpmp69
Thu Apr 09, 2015 1:06 pm
Forum: PMP® Open Forum
Topic: single vs sole
Replies: 2
Views: 1775

Re: single vs sole

Single source : Selecting a seller without competition. Preferred seller

Sole source : Selecting a seller because it is the only provider of the needed product or service that you are looking for
by coolpmp69
Mon Apr 06, 2015 1:02 pm
Forum: PMP® Open Forum
Topic: risk mgmt qts need to clarify
Replies: 4
Views: 1731

Re: risk mgmt qts need to clarify

Can you give an example
by coolpmp69
Fri Apr 03, 2015 6:52 pm
Forum: PMP® Open Forum
Topic: risk mgmt qts need to clarify
Replies: 4
Views: 1731

Re: risk mgmt qts need to clarify

Q: difference between risk tolerance and threshold A: This post should help you to understand the difference http://www.izenbridge.com/blog/what-is-the-difference-between-risk-appetite-risk-tolerance-and-risk-threshold/ Q: If risk exposure is calculated in perf qual analysis or perform Quant analysi...
by coolpmp69
Fri Apr 03, 2015 1:14 pm
Forum: PMP® Open Forum
Topic: contradictory statements in Rita and PMBOK---
Replies: 4
Views: 2326

Re: contradictory statements in Rita and PMBOK---

I agree with manishpn's viewpoint. Regarding issue log : Normally issues do occur when you are in execution phase when there are disputes/lack of commonality between stakeholders. If you see in PMBOk, issue log arises due to managing project team and stakeholders which falls under execution process ...
by coolpmp69
Fri Apr 03, 2015 1:01 pm
Forum: PMP® Open Forum
Topic: contradictory statements in Rita and PMBOK---
Replies: 4
Views: 2326

Re: contradictory statements in Rita and PMBOK---

@AM1969 : Regarding project resource release You can refer to the same discussion in another thread here : http://forum.izenbridge.com/viewtopic.php?f=3&t=1712 As I mentioned in the another thread Project resources can be released anytime in the project- after their work in completed, accepted b...
by coolpmp69
Thu Apr 02, 2015 12:51 pm
Forum: PMP® Open Forum
Topic: PMP form Rita Mulchay
Replies: 5
Views: 2584

Re: PMP form Rita Mulchay

@Dipti...It doesn't matter as to how many mock tests you are giving and also there is no rulebook for taking X number of exams. What matters is - are you able to apply your knowledge in the mock exam and are you consistently getting over 75-80%. In case that you are well prepared for the exams. Mock...
by coolpmp69
Tue Mar 31, 2015 1:11 pm
Forum: PMP® Open Forum
Topic: PMP application : Queries
Replies: 4
Views: 1949

Re: PMP application : Queries

@dipti 1>To show 4500 hours of experience will it be okay if I consider 2 years 10 mnths from current company and then another 4 years from my 1st company as the 2nd company I had worked with was very less time ..and I do not have the contacts from this company nor the manager. So in case my applica...
by coolpmp69
Tue Mar 31, 2015 12:56 pm
Forum: PMP® Open Forum
Topic: Diagramming method and FS and few other qts
Replies: 4
Views: 2025

Re: Diagramming method and FS and few other qts

Try to understand the concepts and what happens in each stage. This way you cannot miss anything in each process groups. In simple words/layman language: initiating - preparing and starting the project planning - plan how you are going to work on your project all the resources within given timeline ...
by coolpmp69
Mon Mar 30, 2015 6:28 pm
Forum: PMP® Open Forum
Topic: question on cost mgmt plan
Replies: 2
Views: 1069

Re: question on cost mgmt plan

The WBS level at which earned value will be calculated

The WBS component used for the project cost accounting is called the control account. Each of these control accounts are summed up to arrive to the cost baseline.