Re: Project Closure

Contract closure is done in Close Procurement process where as the project closure is done in Close Project/Phase process.
However, contract closure after accepting deliverables from the vendor need to be done prior to the project closure.
by d.ranatunga
Mon Nov 20, 2017 5:24 pm
Forum: PMP® Open Forum
Topic: Close Project
Replies: 4
Views: 1168

Re: Close Project

1. Product/Service transition to production ( support, SLA)
2. Measure Success/failure
3. Updates- OPA -Lessons learned, PMP
4. Administrative project closure
5. Release Team

Accepted Deliverables is an INPUT to this process.