Forum: iZenBridge PMP Open Questions
Topic: Situational Question
Replies: 3
Views: 82

Re: Situational Question

But this issue is not impacting project scope,cost and Time.
by komal
Tue Nov 14, 2017 10:59 am
Forum: iZenBridge PMP Open Questions
Topic: Situational Question
Replies: 3
Views: 82

Situational Question

You are project manager for website development company. Testing team finds some issues while testing the accounting module and logs in the bug tracking system. What should be your next action? A) Inform immediately to client B( Implements the change C) Follow change request process D) Do nothing as...
by komal
Thu Nov 09, 2017 6:26 am
Forum: PMP® Open Forum
Topic: Looking for a study partner on an urgent basis.
Replies: 1
Views: 147

Re: Looking for a study partner on an urgent basis.

In which studypal Group are you , will join
by komal
Sat Nov 04, 2017 3:16 am
Forum: PMP® Queries and Tips
Topic: PMP Standard
Replies: 1
Views: 63

PMP Standard

Please suggest, Does PMP exam has same standard of Scordo Book
by komal
Thu Oct 26, 2017 2:03 am
Forum: iZenBridge PMP Open Questions
Topic: Contract Type
Replies: 1
Views: 117

Contract Type

A commercial real-estate developer contracts with a construction firm to build one of the buildings for the actual cost of providing the materials and services plus a fixed fee for profit. What type of contract is this? Time and materials Cost-reimbursable Fixed price Independent vendor According to...
by komal
Thu Oct 26, 2017 1:25 am
Forum: iZenBridge PMP Open Questions
Topic: Project Closure
Replies: 1
Views: 115

Project Closure

Mr Sharma has completed all the deliverables in his project.This was a complex project involving a lot of challenges, but with good management and a motivated team things have been completed successfully.What should he do next as a project manager? Disband the team Validate scope Update lessons lear...
by komal
Wed Oct 25, 2017 6:45 am
Forum: PMP® Open Forum
Topic: Gold Plating
Replies: 1
Views: 94

Gold Plating

The Project Manager determines at the end of the project that five additional functionalities and two areas of performance have been added to the project. The client has expressed satisfaction with the project. What does this mean in the terms of success of the project? The Project was a big success...
by komal
Wed Oct 25, 2017 6:10 am
Forum: PMP® Open Forum
Topic: Stakeholder Role
Replies: 1
Views: 91

Stakeholder Role

The role of each stakeholder is determined by whom? The stakeholder and the sponsor The project manager and the sponsor The team and the project manager The project manager and the stakeholder Stakeholder provide requirement and have positive and negative influence. How to determine role of stakehol...
by komal
Wed Oct 25, 2017 3:17 am
Forum: PMP® Open Forum
Topic: PMP Mock Test
Replies: 1
Views: 65

PMP Mock Test

You are managing a water supply network deployment project. During project planning you are considering two approaches to lay the pipe network. Approach A will most likely cost $50,000 (+/-5%). Approach B will most likely cost $25,000 (+/-40%). Which approach will you select if your project stakehol...
by komal
Wed Oct 25, 2017 3:02 am
Forum: PMP® Open Forum
Topic: PMP Mock Test
Replies: 1
Views: 85

PMP Mock Test

You are currently performing process analysis on your project and following the steps outlined in the process improvement plan to identify needed improvements. You have identified problems that have surfaced, constraints that have been encountered, and non-value-added activities on your project proc...
by komal
Sun Oct 15, 2017 1:21 am
Forum: iZenBridge PMP Open Questions
Topic: Mock Test CCB
Replies: 1
Views: 103

Mock Test CCB

One of the stakeholders of a project initiated a change request which was then documented in the change control system. In general, who usually would be responsible for approving or rejecting the change request? A. An authority within the project management team or external organization. B. The PMO ...
by komal
Sun Oct 15, 2017 1:18 am
Forum: iZenBridge PMP Open Questions
Topic: Mock Test
Replies: 3
Views: 244

Mock Test

Project management is an integrative undertaking that requires each ______________ and ___________ process to be appropriately aligned and connected with other processes to facilitate coordination. A . Process and knowledge areas B. Project and product C. Product and knowledge areas D. Phases and kn...
by komal
Tue Oct 03, 2017 5:11 pm
Forum: PMP® Open Forum
Topic: Whats the correct answer?
Replies: 8
Views: 358

Re: Whats the correct answer?

1.start planning - Project charter developed and PM authorize now PM can start planning. - Right Answer 2.develop project charter - As we know project charter authrize the project manager, in this case project manager is already assigned and conclusion is project charter is already developed. Not co...
by komal
Tue Oct 03, 2017 4:25 pm
Forum: PMP® Open Forum
Topic: Sponsor : most applicable responsibility
Replies: 7
Views: 262

Re: Sponsor : most applicable responsibility

PM will be giving direction and managing that but Sponsor is leading everything in terms of success.
by komal
Sun Oct 01, 2017 3:44 am
Forum: PMP® Mock Exams Open Questions
Topic: Project Cost Management Mock Test
Replies: 2
Views: 354

Project Cost Management Mock Test

As per the project management plan of Joe’s project, $200,000 has been assigned to it as project cost baseline. The project is planned to finish in one year. At the end of one year, on the planned date of completion, 90% of the work has been accomplished. Calculate schedule performance index for the...
by komal
Sun Oct 01, 2017 3:32 am
Forum: PMP® Mock Exams Open Questions
Topic: Project Cost Management Mock Test
Replies: 0
Views: 106

Project Cost Management Mock Test

Chris is the project manager of a software development project. The project is planned to be end up costing $120,000. Chris can foresee that his project is not going to finish under planned budget. 60% of project work has been completed after spending $80,000. Chris knows that whatever he does, the ...
by komal
Sat Sep 30, 2017 10:48 am
Forum: Oliver 75 PMP Questions
Topic: Oliver 75 - 75th Question
Replies: 7
Views: 2843

Re: Oliver 75 - 75th Question

Still Could not understand why A right option. Please explain
by komal
Sat Sep 30, 2017 8:30 am
Forum: Oliver 75 PMP Questions
Topic: Oliver 75 - 11th Question
Replies: 10
Views: 2241

Re: Oliver 75 - 11th Question

Still could not understand how recently closed-out meant by Cancelled of project.
by komal
Fri Sep 29, 2017 11:17 am
Forum: Questions about Our classes, Online Classes, Webinars, Booking, Payment etc.
Topic: Renew Online course
Replies: 2
Views: 276

Renew Online course

Please suggest how to renew, pmp online course.
by komal
Tue Sep 26, 2017 4:33 pm
Forum: PMP® Open Forum
Topic: Initiating Process group Mock Test
Replies: 1
Views: 155

Initiating Process group Mock Test

Your company has signed a contract with Power Supply Company to erect a 3000 MW power plant and company named you as the project manager for this project. What is the next step you will take? Prepare scope statement Milestone list Identify resources Develop project charter Manish/Saket As Project ch...
by komal
Mon Sep 25, 2017 4:23 pm
Forum: PMP® Open Forum
Topic: What to do when various variance reports showing alarming state?
Replies: 5
Views: 745

Re: What to do when various variance reports showing alarming state?

I am confused between Option A and C.

Both seems correct but i will go for Option A because Sponsor is part of senior management and we should convey him about status of project and how cost , scheduling is having impact rather than going to Stakeholder at initial level of risk.

Please suggest.
by komal
Fri Sep 22, 2017 1:09 am
Forum: PMP® Open Forum
Topic: PMP Maths
Replies: 2
Views: 153

PMP Maths

You are managing a project which is estimated to cost $ 300,000 with a timeline of 10 months. Due to some reasons schedule was slightly delayed and the net result was that there was some additional cost in the project. At the end of the third month, you review the project and find that the project i...
by komal
Thu Sep 21, 2017 1:09 am
Forum: PMP® Open Forum
Topic: PMP Maths
Replies: 1
Views: 98

PMP Maths

Rick is managing a project which is budgeted for $100,000. The project is expected to last for 10 months with work spread evenly across all the months. At the end of fifth month, he noticed that $50,000 have actually been spent in the project and only 40% of the work has been done. What is the sched...
by komal
Sun Sep 17, 2017 11:11 am
Forum: PMP® Open Forum
Topic: Mock Tech Numerical
Replies: 3
Views: 189

Mock Tech Numerical

Your project has a budget at completion as $80,000. You want to find out that performance of your project is going ok. You know that $50,000 already spent on the work which is 70% done. With the same rate of expenditures, what’s the lowest that you can allow your CPI to go before you’ve exceeded you...
by komal
Wed Sep 13, 2017 3:14 pm
Forum: PMP® Open Forum
Topic: Change Request!
Replies: 5
Views: 315

Re: Change Request!

Manish,

If we consider exception that Sponsor is not part of CCB and after CCB approval changes get rejected by sponsor, in that changes get rejected finally i think. Hence not need to update any doc neither baseline nor other document.

Please correct me if i am wrong.
by komal
Wed Sep 13, 2017 3:13 pm
Forum: PMP® Open Forum
Topic: Change Request!
Replies: 5
Views: 315

Re: Change Request!

Manish,

If we consider exception that Sponsor is not part of CCB and after CCB approval changes get rejected by sponsor, in that changes get rejected finally i think. Hence not need to update any doc neither baseline nor other document.

Please correct me if i am wrong.
by komal
Wed Sep 13, 2017 3:03 pm
Forum: PMP® Open Forum
Topic: Mock Test
Replies: 4
Views: 248

Re: Mock Test

PV(2) is 8. How you have utilized it as 10.
by komal
Wed Sep 13, 2017 2:47 pm
Forum: PMP® Open Forum
Topic: Contingency reserve tricky question.
Replies: 11
Views: 659

Re: Contingency reserve tricky question.

I have not seen any such definition in PMBOK if contingency reserved is not used for risk, eliminate it. Please share screen shot .
by komal
Wed Sep 13, 2017 10:09 am
Forum: PMP® Open Forum
Topic: Mock Test
Replies: 4
Views: 258

Mock Test

To maximize success for your project, you understand that identification of all stakeholders and classifying them in appropriate categories is critical. Along with sponsor you are in process of identifying stakeholders in initial stage of project. Your sponsor tells you that since the project will r...
by komal
Wed Sep 13, 2017 9:57 am
Forum: PMP® Open Forum
Topic: Mock Test
Replies: 2
Views: 196

Mock Test

You are project manager for a large financial organization. Your company has recently entered into new business line of insurance services. You are asked to lead a project for developing insurance products for manufacturing industries. You are in initial stage of the project and your sponsor has ask...
by komal
Wed Sep 13, 2017 9:28 am
Forum: PMP® Open Forum
Topic: Mock Test
Replies: 1
Views: 147

Mock Test

EAC.jpg
EAC.jpg (10.93 KiB) Viewed 147 times


The variances are because of atypical reason, that means that the future work can be accomplished at the planned rate.


Manish/Saket

Could not understand meaning of question and which formula we need to use and WHY ?

Please explain.
by komal
Tue Sep 12, 2017 10:10 am
Forum: PMP® Open Forum
Topic: Mock Test
Replies: 4
Views: 248

Mock Test

Project performance trend is shown below, if BAC is $29 Mn, total duration 12 months, Planned value at end of month 2 was $ 8 Mn and at the end of 4 month was $ 10 Mn. As a project manager what should your focus be ? A. No need to worry project performance is good B. While SPI is improving your CPI ...
by komal
Sun Sep 10, 2017 1:33 pm
Forum: PMP® Open Forum
Topic: Scope Management Mockups
Replies: 3
Views: 210

Scope Management Mockups

The assurance that a product, service, or system meets the needs of the customer and other identified stakeholders which often involves acceptance from external customers is called:

Validation

Verification

Quality Check

Acceptance
by komal
Sun Sep 10, 2017 1:32 pm
Forum: PMP® Open Forum
Topic: Scope Management Mockups
Replies: 1
Views: 137

Scope Management Mockups

You are working on a software development project. The sponsor wants to make a change to the Scope after it has been baseline. You want to know the procedure that how to manage these changes. What is the BEST place to look for this information? WBS Scope management plan Change request template Busin...
by komal
Fri Sep 08, 2017 3:23 pm
Forum: PMP® Open Forum
Topic: Plan Risk Mangement Mock Test
Replies: 1
Views: 136

Plan Risk Mangement Mock Test

Q. What is not true about risk register ? Risk register usually gets update throughout the duration of project Risk register is input to plan quality management plan and may be updated as part of estimate costs Risk register will be part of project file as an output to close phase Risk register will...
by komal
Wed Sep 06, 2017 2:23 pm
Forum: PMP® Open Forum
Topic: Plan Risk Mangement Mock Test
Replies: 4
Views: 246

Plan Risk Mangement Mock Test

Which of the following describes responses provided which may be used in the event that a specific trigger occurs?

Contingent Response Strategies

Fallback Plan

Risk Mitigation

Residual Risk
by komal
Wed Sep 06, 2017 8:59 am
Forum: PMP® Open Forum
Topic: Looking for a Study partner for PMP
Replies: 18
Views: 1029

Re: Looking for a Study partner for PMP

I am also interested to connect , planning to give exam in December 2017.

My Mail id : komal.mutreja07@gmail.com

Please suggest how to proceed.
by komal
Wed Sep 06, 2017 8:56 am
Forum: PMP® Open Forum
Topic: Plan Risk Mangement Mock Test
Replies: 2
Views: 150

Re: Plan Risk Mangement Mock Test

Answer is B

Manish/Saket

Please elaborate question, what exactly is asked and why to choose option B.
by komal
Wed Sep 06, 2017 1:42 am
Forum: PMP® Open Forum
Topic: Plan Risk Mangement Mock Test
Replies: 2
Views: 150

Plan Risk Mangement Mock Test

Risk identification checklists are usually developed based on historical information and knowledge accumulated from previous similar projects. Which of the following statements about risk identification checklists is wrong? It is impossible to build an exhaustive checklist The lowest level of the Ri...
by komal
Wed Sep 06, 2017 1:04 am
Forum: PMP® Open Forum
Topic: Plan Risk Mangement
Replies: 0
Views: 129

Plan Risk Mangement

How to calculate Contingency reserve?
by komal
Sun Sep 03, 2017 1:30 pm
Forum: PMP® Open Forum
Topic: Quantitative Risk Analysis
Replies: 1
Views: 222

Quantitative Risk Analysis

Could you please explain EMV and Monte Carlo analysis technique in details with example. Also decision diagram mentioned under EMV in PMBOK5.
by komal
Mon Aug 28, 2017 4:28 am
Forum: PMP® Open Forum
Topic: Plan Risk Mangement: Tool and Techniques
Replies: 1
Views: 156

Plan Risk Mangement: Tool and Techniques

Can you please explain Analytical Technique in risk management, i could not understand its concept. Please explain with example if possible.
by komal
Fri Aug 25, 2017 7:30 am
Forum: PMP® Mock Exams Open Questions
Topic: Stakeholder Mgmt Strategy sample question
Replies: 10
Views: 1523

Re: Stakeholder Mgmt Strategy sample question

According to me it is avoiding risk.

Manish, can you please clarify if i am wrong .
by komal
Fri Aug 25, 2017 6:41 am
Forum: PMP® Mock Exams Open Questions
Topic: PMP Practice Questions
Replies: 5
Views: 748

Re: PMP Practice Questions

Manish,

I could not get what izenbridge has explain in description, please explain more .
by komal
Thu Aug 24, 2017 4:42 pm
Forum: PMP® Open Forum
Topic: Make or Buy Analysis
Replies: 11
Views: 587

Re: Make or Buy Analysis

Buy>Make then to be cost effective we should go make make in house.

Correct me if i am wrong.
by komal
Thu Aug 24, 2017 1:00 am
Forum: PMP® Open Forum
Topic: PMP Practice Questions
Replies: 5
Views: 431

Re: PMP Practice Questions

Even i couldn't understand calculation here,please explain.
by komal
Wed Aug 23, 2017 9:09 am
Forum: PMP® Open Forum
Topic: PMP Practice Questions
Replies: 1
Views: 198

PMP Practice Questions

A prime contractor in a customer project under CPFF contract has run into unexpected technical problems. Fixing them will require a lot of additional work to be done. The company made a decision to book more staff and equipment from their subcontractors in order to adhere to the agreed timeline. The...
by komal
Wed Aug 23, 2017 1:34 am
Forum: PMP® Open Forum
Topic: PMP Practice Questions
Replies: 1
Views: 206

PMP Practice Questions

In a traditionally drawn decision tree, a circle represents ___________. 1. a chance to which no expected monetary value can be assigned so that a likely pay-off can not be shown. 2. a decision to which no expected monetary value can be assigned so that a likely pay-off can not be shown. 3. a chance...
by komal
Wed Aug 23, 2017 1:23 am
Forum: PMP® Open Forum
Topic: PMP Practice Questions
Replies: 2
Views: 221

PMP Practice Questions

In order to speed up a project, you made a decision to fast-track a phase currently performed with five team members, and another one which was planned to begin in four weeks time with another five team members. Which of the following activities should you do first? 1. Make sure that all exit criter...
by komal
Wed Aug 23, 2017 1:14 am
Forum: PMP® Open Forum
Topic: PMP Practice Questions
Replies: 5
Views: 431

PMP Practice Questions

A production process has been defined as part of an industrial equipment manufacturing project. The process is intended to produce steel bolts with a length of 20 cm. The control limits are 19.955cm and 20.045cm. The measurements made at the end of the process yielded the following results: 20.033cm...

Go to advanced search