Pragmatic Agile Workshop

Search found 48 matches

by komal
Sun Sep 17, 2017 11:11 am
Forum: PMP® Open Forum
Topic: Mock Tech Numerical
Replies: 3
Views: 49

Mock Tech Numerical

Your project has a budget at completion as $80,000. You want to find out that performance of your project is going ok. You know that $50,000 already spent on the work which is 70% done. With the same rate of expenditures, what’s the lowest that you can allow your CPI to go before you’ve exceeded you...
by komal
Wed Sep 13, 2017 3:14 pm
Forum: PMP® Open Forum
Topic: Change Request!
Replies: 4
Views: 72

Re: Change Request!

Manish,

If we consider exception that Sponsor is not part of CCB and after CCB approval changes get rejected by sponsor, in that changes get rejected finally i think. Hence not need to update any doc neither baseline nor other document.

Please correct me if i am wrong.
by komal
Wed Sep 13, 2017 3:13 pm
Forum: PMP® Open Forum
Topic: Change Request!
Replies: 4
Views: 72

Re: Change Request!

Manish,

If we consider exception that Sponsor is not part of CCB and after CCB approval changes get rejected by sponsor, in that changes get rejected finally i think. Hence not need to update any doc neither baseline nor other document.

Please correct me if i am wrong.
by komal
Wed Sep 13, 2017 3:03 pm
Forum: PMP® Open Forum
Topic: Mock Test
Replies: 4
Views: 65

Re: Mock Test

PV(2) is 8. How you have utilized it as 10.
by komal
Wed Sep 13, 2017 2:47 pm
Forum: PMP® Open Forum
Topic: Contingency reserve tricky question.
Replies: 11
Views: 177

Re: Contingency reserve tricky question.

I have not seen any such definition in PMBOK if contingency reserved is not used for risk, eliminate it. Please share screen shot .
by komal
Wed Sep 13, 2017 10:09 am
Forum: PMP® Open Forum
Topic: Mock Test
Replies: 4
Views: 81

Mock Test

To maximize success for your project, you understand that identification of all stakeholders and classifying them in appropriate categories is critical. Along with sponsor you are in process of identifying stakeholders in initial stage of project. Your sponsor tells you that since the project will r...
by komal
Wed Sep 13, 2017 9:57 am
Forum: PMP® Open Forum
Topic: Mock Test
Replies: 2
Views: 57

Mock Test

You are project manager for a large financial organization. Your company has recently entered into new business line of insurance services. You are asked to lead a project for developing insurance products for manufacturing industries. You are in initial stage of the project and your sponsor has ask...
by komal
Wed Sep 13, 2017 9:28 am
Forum: PMP® Open Forum
Topic: Mock Test
Replies: 1
Views: 44

Mock Test

EAC.jpg
EAC.jpg (10.93 KiB) Viewed 44 times


The variances are because of atypical reason, that means that the future work can be accomplished at the planned rate.


Manish/Saket

Could not understand meaning of question and which formula we need to use and WHY ?

Please explain.
by komal
Tue Sep 12, 2017 10:10 am
Forum: PMP® Open Forum
Topic: Mock Test
Replies: 4
Views: 65

Mock Test

Project performance trend is shown below, if BAC is $29 Mn, total duration 12 months, Planned value at end of month 2 was $ 8 Mn and at the end of 4 month was $ 10 Mn. As a project manager what should your focus be ? A. No need to worry project performance is good B. While SPI is improving your CPI ...
by komal
Sun Sep 10, 2017 1:33 pm
Forum: PMP® Open Forum
Topic: Scope Management Mockups
Replies: 3
Views: 73

Scope Management Mockups

The assurance that a product, service, or system meets the needs of the customer and other identified stakeholders which often involves acceptance from external customers is called:

Validation

Verification

Quality Check

Acceptance
by komal
Sun Sep 10, 2017 1:32 pm
Forum: PMP® Open Forum
Topic: Scope Management Mockups
Replies: 1
Views: 48

Scope Management Mockups

You are working on a software development project. The sponsor wants to make a change to the Scope after it has been baseline. You want to know the procedure that how to manage these changes. What is the BEST place to look for this information? WBS Scope management plan Change request template Busin...
by komal
Fri Sep 08, 2017 3:23 pm
Forum: PMP® Open Forum
Topic: Plan Risk Mangement Mock Test
Replies: 1
Views: 49

Plan Risk Mangement Mock Test

Q. What is not true about risk register ? Risk register usually gets update throughout the duration of project Risk register is input to plan quality management plan and may be updated as part of estimate costs Risk register will be part of project file as an output to close phase Risk register will...
by komal
Wed Sep 06, 2017 2:23 pm
Forum: PMP® Open Forum
Topic: Plan Risk Mangement Mock Test
Replies: 4
Views: 100

Plan Risk Mangement Mock Test

Which of the following describes responses provided which may be used in the event that a specific trigger occurs?

Contingent Response Strategies

Fallback Plan

Risk Mitigation

Residual Risk
by komal
Wed Sep 06, 2017 8:59 am
Forum: PMP® Open Forum
Topic: Looking for a Study partner for PMP
Replies: 18
Views: 329

Re: Looking for a Study partner for PMP

I am also interested to connect , planning to give exam in December 2017.

My Mail id : komal.mutreja07@gmail.com

Please suggest how to proceed.
by komal
Wed Sep 06, 2017 8:56 am
Forum: PMP® Open Forum
Topic: Plan Risk Mangement Mock Test
Replies: 2
Views: 55

Re: Plan Risk Mangement Mock Test

Answer is B

Manish/Saket

Please elaborate question, what exactly is asked and why to choose option B.
by komal
Wed Sep 06, 2017 1:42 am
Forum: PMP® Open Forum
Topic: Plan Risk Mangement Mock Test
Replies: 2
Views: 55

Plan Risk Mangement Mock Test

Risk identification checklists are usually developed based on historical information and knowledge accumulated from previous similar projects. Which of the following statements about risk identification checklists is wrong? It is impossible to build an exhaustive checklist The lowest level of the Ri...
by komal
Wed Sep 06, 2017 1:04 am
Forum: PMP® Open Forum
Topic: Plan Risk Mangement
Replies: 0
Views: 35

Plan Risk Mangement

How to calculate Contingency reserve?
by komal
Sun Sep 03, 2017 1:30 pm
Forum: PMP® Open Forum
Topic: Quantitative Risk Analysis
Replies: 1
Views: 77

Quantitative Risk Analysis

Could you please explain EMV and Monte Carlo analysis technique in details with example. Also decision diagram mentioned under EMV in PMBOK5.
by komal
Mon Aug 28, 2017 4:28 am
Forum: PMP® Open Forum
Topic: Plan Risk Mangement: Tool and Techniques
Replies: 1
Views: 64

Plan Risk Mangement: Tool and Techniques

Can you please explain Analytical Technique in risk management, i could not understand its concept. Please explain with example if possible.
by komal
Fri Aug 25, 2017 7:30 am
Forum: PMP® Mock Exams Open Questions
Topic: Stakeholder Mgmt Strategy sample question
Replies: 10
Views: 946

Re: Stakeholder Mgmt Strategy sample question

According to me it is avoiding risk.

Manish, can you please clarify if i am wrong .
by komal
Fri Aug 25, 2017 6:41 am
Forum: PMP® Mock Exams Open Questions
Topic: PMP Practice Questions
Replies: 5
Views: 382

Re: PMP Practice Questions

Manish,

I could not get what izenbridge has explain in description, please explain more .
by komal
Thu Aug 24, 2017 4:42 pm
Forum: PMP® Open Forum
Topic: Make or Buy Analysis
Replies: 11
Views: 253

Re: Make or Buy Analysis

Buy>Make then to be cost effective we should go make make in house.

Correct me if i am wrong.
by komal
Thu Aug 24, 2017 1:00 am
Forum: PMP® Open Forum
Topic: PMP Practice Questions
Replies: 5
Views: 176

Re: PMP Practice Questions

Even i couldn't understand calculation here,please explain.
by komal
Wed Aug 23, 2017 9:09 am
Forum: PMP® Open Forum
Topic: PMP Practice Questions
Replies: 1
Views: 84

PMP Practice Questions

A prime contractor in a customer project under CPFF contract has run into unexpected technical problems. Fixing them will require a lot of additional work to be done. The company made a decision to book more staff and equipment from their subcontractors in order to adhere to the agreed timeline. The...
by komal
Wed Aug 23, 2017 1:34 am
Forum: PMP® Open Forum
Topic: PMP Practice Questions
Replies: 1
Views: 74

PMP Practice Questions

In a traditionally drawn decision tree, a circle represents ___________. 1. a chance to which no expected monetary value can be assigned so that a likely pay-off can not be shown. 2. a decision to which no expected monetary value can be assigned so that a likely pay-off can not be shown. 3. a chance...
by komal
Wed Aug 23, 2017 1:23 am
Forum: PMP® Open Forum
Topic: PMP Practice Questions
Replies: 2
Views: 79

PMP Practice Questions

In order to speed up a project, you made a decision to fast-track a phase currently performed with five team members, and another one which was planned to begin in four weeks time with another five team members. Which of the following activities should you do first? 1. Make sure that all exit criter...
by komal
Wed Aug 23, 2017 1:14 am
Forum: PMP® Open Forum
Topic: PMP Practice Questions
Replies: 5
Views: 176

PMP Practice Questions

A production process has been defined as part of an industrial equipment manufacturing project. The process is intended to produce steel bolts with a length of 20 cm. The control limits are 19.955cm and 20.045cm. The measurements made at the end of the process yielded the following results: 20.033cm...
by komal
Wed Aug 23, 2017 1:06 am
Forum: PMP® Open Forum
Topic: PMP Practice Questions
Replies: 1
Views: 78

PMP Practice Questions

A company has to make a choice between two projects, because the available resources in money and kind are not sufficient to run both at the same time. Each project would take 9 months and would cost $250,000. The first project is a process optimization which would result in a cost reduction of $120...
by komal
Wed Aug 16, 2017 4:04 pm
Forum: PMP® Open Forum
Topic: Project Time Management
Replies: 7
Views: 217

Project Time Management

How to justify Schedule Management plan is major input to project management plan process ?
by komal
Wed Aug 16, 2017 1:23 am
Forum: PMP® Open Forum
Topic: Scope Management Mockups
Replies: 3
Views: 132

Scope Management Mockups

Jay and his team have just begun planning phase for their project which has duration of 3 years. Team has gone through project charter and is now developing scope management plan. One of the team members comes to Jay and mentions that project Management plan does not have quality management plan and...
by komal
Wed Aug 16, 2017 1:19 am
Forum: PMP® Open Forum
Topic: Scope Management Mockups
Replies: 1
Views: 86

Scope Management Mockups

What would be termed as conditions or capabilities that are to be met by project or present in the product or service, or result to satisfy an agreement or other formally imposed specification ? Acceptance criteria Contractual need Business case Requirements Please explain, my answer is Acceptance C...
by komal
Mon Aug 14, 2017 5:26 pm
Forum: PMP® Open Forum
Topic: Collect Requirements in Project Scope Management
Replies: 2
Views: 108

Collect Requirements in Project Scope Management

What is difference between focus group and facilitated Workshops? Please explain with an example.
by komal
Tue Aug 08, 2017 3:05 am
Forum: PMP® Open Forum
Topic: integration management Q&A
Replies: 6
Views: 239

Re: integration management Q&A

According me Option is D is correct, Cost management plan is part of Planning process group and budget can't be measured at each and every phase review, Hence Option D Correct.

Manish, Correct if i am wrong.
by komal
Sun Aug 06, 2017 7:45 am
Forum: PMP® Open Forum
Topic: Practice Question
Replies: 2
Views: 124

Practice Question

A project manager needs to develop a web site that allows users to submit expenses. There are two vendors competing for the project. Vendor A proposes an upfront fee of $20,000 and a maintenance fee of $4,000 per month. Vendor B proposes an upfront fee of $10,000 and a maintenance fee of $5,000 per ...
by komal
Sat Aug 05, 2017 3:18 pm
Forum: PMP® Open Forum
Topic: Project Staatus
Replies: 16
Views: 488

Re: Project Staatus

I could not get clarification, can you please put shadow again "How to justify project is completed" ?
by komal
Sat Aug 05, 2017 7:54 am
Forum: PMP® Open Forum
Topic: Project Staatus
Replies: 16
Views: 488

Re: Project Staatus

Then how cam i find project is completed or not , if i am not wrong from SPI =0.9 as shows project is behind schedule? Please share your views and clarify.
by komal
Fri Aug 04, 2017 5:24 pm
Forum: PMP® Open Forum
Topic: Project Staatus
Replies: 16
Views: 488

Re: Project Staatus

Don't we get an idea from Question statement During the completion of project that project is completed. Please clarify
by komal
Thu Aug 03, 2017 2:23 pm
Forum: PMP® Mock Exams Open Questions
Topic: PMP Practice Questions
Replies: 5
Views: 382

PMP Practice Questions

To maximize success for your project, you understand that identification of all stakeholders and classifying them in appropriate categories is critical. Along with sponsor you are in process of identifying stakeholders in initial stage of project. Your sponsor tells you that since the project will r...
by komal
Fri Jul 28, 2017 1:06 am
Forum: PMP® Open Forum
Topic: Cost Management Practice
Replies: 3
Views: 154

Cost Management Practice

Could not figure difference between options C and D. Please clarify as i could understand both options meaning is same.
by komal
Thu Jul 27, 2017 5:48 pm
Forum: PMP® Open Forum
Topic: Earned Value Management
Replies: 2
Views: 144

Earned Value Management

Could not get difference between Actual Cost and Earned Value?
by komal
Sun Jul 23, 2017 10:56 am
Forum: PMP® Open Forum
Topic: Time Management Practice
Replies: 5
Views: 213

Re: Time Management Practice

In Rita Mulkai Book, Answer is Activity C
by komal
Sun Jul 23, 2017 10:24 am
Forum: PMP® Open Forum
Topic: Time Management Practice
Replies: 5
Views: 213

Re: Time Management Practice

Please explain more how to solve this ?
by komal
Sat Jul 22, 2017 2:03 am
Forum: PMP® Open Forum
Topic: Time Management Practice
Replies: 5
Views: 213

Time Management Practice

Please explain how to solve this question

TimeManagement1.png
TimeManagement1.png (36.35 KiB) Viewed 213 times
by komal
Thu Jul 20, 2017 2:53 pm
Forum: PMP® Open Forum
Topic: Time Estimation
Replies: 1
Views: 82

Time Estimation

Time Estimation of activity/project is group of all estimation techniques or we can use either of one?
by komal
Thu Jul 20, 2017 2:39 pm
Forum: PMP® Open Forum
Topic: Estimation Techniques
Replies: 1
Views: 86

Estimation Techniques

How we can decide estimation techniques based on project execution in specific industry? Means how to decide technique for software project or construction ?
by komal
Sat Jun 17, 2017 1:18 am
Forum: PMP® Open Forum
Topic: Could not understand Schedule method, schedule model in Time Management
Replies: 1
Views: 201

Could not understand Schedule method, schedule model in Time Management

Please clarify with some live examples. In Video Saket is saying for some tools. If i am not wrong, does he says about third party tools or something else.
by komal
Thu Jun 15, 2017 1:04 am
Forum: PMP® Open Forum
Topic: Validate Scope in Project scope management
Replies: 1
Views: 190

Validate Scope in Project scope management

Please put more shadow with examples on validate scope as could not understand from video.
by komal
Tue Jun 13, 2017 5:02 am
Forum: PMP® Queries and Tips
Topic: Monitoring and Control Process in Project Integration management
Replies: 1
Views: 285

Monitoring and Control Process in Project Integration management

Please give some best scenario to understand Monitoring and Control Process in Project Integration management as i could not understand this topic

Go to advanced search