Search found 61 matches

by komal
Sun Oct 15, 2017 1:21 am
Forum: iZenBridge PMP Open Questions
Topic: Mock Test CCB
Replies: 1
Views: 24

Mock Test CCB

One of the stakeholders of a project initiated a change request which was then documented in the change control system. In general, who usually would be responsible for approving or rejecting the change request? A. An authority within the project management team or external organization. B. The PMO ...
by komal
Sun Oct 15, 2017 1:18 am
Forum: iZenBridge PMP Open Questions
Topic: Mock Test
Replies: 3
Views: 51

Mock Test

Project management is an integrative undertaking that requires each ______________ and ___________ process to be appropriately aligned and connected with other processes to facilitate coordination. A . Process and knowledge areas B. Project and product C. Product and knowledge areas D. Phases and kn...
by komal
Tue Oct 03, 2017 5:11 pm
Forum: PMP® Open Forum
Topic: Whats the correct answer?
Replies: 7
Views: 173

Re: Whats the correct answer?

1.start planning - Project charter developed and PM authorize now PM can start planning. - Right Answer 2.develop project charter - As we know project charter authrize the project manager, in this case project manager is already assigned and conclusion is project charter is already developed. Not co...
by komal
Tue Oct 03, 2017 4:25 pm
Forum: PMP® Open Forum
Topic: Sponsor : most applicable responsibility
Replies: 7
Views: 121

Re: Sponsor : most applicable responsibility

PM will be giving direction and managing that but Sponsor is leading everything in terms of success.
by komal
Sun Oct 01, 2017 3:44 am
Forum: PMP® Mock Exams Open Questions
Topic: Project Cost Management Mock Test
Replies: 1
Views: 141

Project Cost Management Mock Test

As per the project management plan of Joe’s project, $200,000 has been assigned to it as project cost baseline. The project is planned to finish in one year. At the end of one year, on the planned date of completion, 90% of the work has been accomplished. Calculate schedule performance index for the...
by komal
Sun Oct 01, 2017 3:32 am
Forum: PMP® Mock Exams Open Questions
Topic: Project Cost Management Mock Test
Replies: 0
Views: 42

Project Cost Management Mock Test

Chris is the project manager of a software development project. The project is planned to be end up costing $120,000. Chris can foresee that his project is not going to finish under planned budget. 60% of project work has been completed after spending $80,000. Chris knows that whatever he does, the ...
by komal
Sat Sep 30, 2017 10:48 am
Forum: Oliver 75 PMP Questions
Topic: Oliver 75 - 75th Question
Replies: 7
Views: 2437

Re: Oliver 75 - 75th Question

Still Could not understand why A right option. Please explain
by komal
Sat Sep 30, 2017 8:30 am
Forum: Oliver 75 PMP Questions
Topic: Oliver 75 - 11th Question
Replies: 10
Views: 1948

Re: Oliver 75 - 11th Question

Still could not understand how recently closed-out meant by Cancelled of project.
by komal
Fri Sep 29, 2017 11:17 am
Forum: Questions about Our classes, Online Classes, Webinars, Booking, Payment etc.
Topic: Renew Online course
Replies: 2
Views: 155

Renew Online course

Please suggest how to renew, pmp online course.
by komal
Tue Sep 26, 2017 4:33 pm
Forum: PMP® Open Forum
Topic: Initiating Process group Mock Test
Replies: 1
Views: 98

Initiating Process group Mock Test

Your company has signed a contract with Power Supply Company to erect a 3000 MW power plant and company named you as the project manager for this project. What is the next step you will take? Prepare scope statement Milestone list Identify resources Develop project charter Manish/Saket As Project ch...
by komal
Mon Sep 25, 2017 4:23 pm
Forum: PMP® Open Forum
Topic: What to do when various variance reports showing alarming state?
Replies: 5
Views: 565

Re: What to do when various variance reports showing alarming state?

I am confused between Option A and C.

Both seems correct but i will go for Option A because Sponsor is part of senior management and we should convey him about status of project and how cost , scheduling is having impact rather than going to Stakeholder at initial level of risk.

Please suggest.
by komal
Fri Sep 22, 2017 1:09 am
Forum: PMP® Open Forum
Topic: PMP Maths
Replies: 2
Views: 80

PMP Maths

You are managing a project which is estimated to cost $ 300,000 with a timeline of 10 months. Due to some reasons schedule was slightly delayed and the net result was that there was some additional cost in the project. At the end of the third month, you review the project and find that the project i...
by komal
Thu Sep 21, 2017 1:09 am
Forum: PMP® Open Forum
Topic: PMP Maths
Replies: 1
Views: 61

PMP Maths

Rick is managing a project which is budgeted for $100,000. The project is expected to last for 10 months with work spread evenly across all the months. At the end of fifth month, he noticed that $50,000 have actually been spent in the project and only 40% of the work has been done. What is the sched...
by komal
Sun Sep 17, 2017 11:11 am
Forum: PMP® Open Forum
Topic: Mock Tech Numerical
Replies: 3
Views: 110

Mock Tech Numerical

Your project has a budget at completion as $80,000. You want to find out that performance of your project is going ok. You know that $50,000 already spent on the work which is 70% done. With the same rate of expenditures, what’s the lowest that you can allow your CPI to go before you’ve exceeded you...
by komal
Wed Sep 13, 2017 3:14 pm
Forum: PMP® Open Forum
Topic: Change Request!
Replies: 5
Views: 192

Re: Change Request!

Manish,

If we consider exception that Sponsor is not part of CCB and after CCB approval changes get rejected by sponsor, in that changes get rejected finally i think. Hence not need to update any doc neither baseline nor other document.

Please correct me if i am wrong.
by komal
Wed Sep 13, 2017 3:13 pm
Forum: PMP® Open Forum
Topic: Change Request!
Replies: 5
Views: 192

Re: Change Request!

Manish,

If we consider exception that Sponsor is not part of CCB and after CCB approval changes get rejected by sponsor, in that changes get rejected finally i think. Hence not need to update any doc neither baseline nor other document.

Please correct me if i am wrong.
by komal
Wed Sep 13, 2017 3:03 pm
Forum: PMP® Open Forum
Topic: Mock Test
Replies: 4
Views: 142

Re: Mock Test

PV(2) is 8. How you have utilized it as 10.
by komal
Wed Sep 13, 2017 2:47 pm
Forum: PMP® Open Forum
Topic: Contingency reserve tricky question.
Replies: 11
Views: 359

Re: Contingency reserve tricky question.

I have not seen any such definition in PMBOK if contingency reserved is not used for risk, eliminate it. Please share screen shot .
by komal
Wed Sep 13, 2017 10:09 am
Forum: PMP® Open Forum
Topic: Mock Test
Replies: 4
Views: 152

Mock Test

To maximize success for your project, you understand that identification of all stakeholders and classifying them in appropriate categories is critical. Along with sponsor you are in process of identifying stakeholders in initial stage of project. Your sponsor tells you that since the project will r...
by komal
Wed Sep 13, 2017 9:57 am
Forum: PMP® Open Forum
Topic: Mock Test
Replies: 2
Views: 119

Mock Test

You are project manager for a large financial organization. Your company has recently entered into new business line of insurance services. You are asked to lead a project for developing insurance products for manufacturing industries. You are in initial stage of the project and your sponsor has ask...
by komal
Wed Sep 13, 2017 9:28 am
Forum: PMP® Open Forum
Topic: Mock Test
Replies: 1
Views: 90

Mock Test

EAC.jpg
EAC.jpg (10.93 KiB) Viewed 90 times


The variances are because of atypical reason, that means that the future work can be accomplished at the planned rate.


Manish/Saket

Could not understand meaning of question and which formula we need to use and WHY ?

Please explain.
by komal
Tue Sep 12, 2017 10:10 am
Forum: PMP® Open Forum
Topic: Mock Test
Replies: 4
Views: 142

Mock Test

Project performance trend is shown below, if BAC is $29 Mn, total duration 12 months, Planned value at end of month 2 was $ 8 Mn and at the end of 4 month was $ 10 Mn. As a project manager what should your focus be ? A. No need to worry project performance is good B. While SPI is improving your CPI ...
by komal
Sun Sep 10, 2017 1:33 pm
Forum: PMP® Open Forum
Topic: Scope Management Mockups
Replies: 3
Views: 119

Scope Management Mockups

The assurance that a product, service, or system meets the needs of the customer and other identified stakeholders which often involves acceptance from external customers is called:

Validation

Verification

Quality Check

Acceptance
by komal
Sun Sep 10, 2017 1:32 pm
Forum: PMP® Open Forum
Topic: Scope Management Mockups
Replies: 1
Views: 91

Scope Management Mockups

You are working on a software development project. The sponsor wants to make a change to the Scope after it has been baseline. You want to know the procedure that how to manage these changes. What is the BEST place to look for this information? WBS Scope management plan Change request template Busin...
by komal
Fri Sep 08, 2017 3:23 pm
Forum: PMP® Open Forum
Topic: Plan Risk Mangement Mock Test
Replies: 1
Views: 83

Plan Risk Mangement Mock Test

Q. What is not true about risk register ? Risk register usually gets update throughout the duration of project Risk register is input to plan quality management plan and may be updated as part of estimate costs Risk register will be part of project file as an output to close phase Risk register will...
by komal
Wed Sep 06, 2017 2:23 pm
Forum: PMP® Open Forum
Topic: Plan Risk Mangement Mock Test
Replies: 4
Views: 156

Plan Risk Mangement Mock Test

Which of the following describes responses provided which may be used in the event that a specific trigger occurs?

Contingent Response Strategies

Fallback Plan

Risk Mitigation

Residual Risk
by komal
Wed Sep 06, 2017 8:59 am
Forum: PMP® Open Forum
Topic: Looking for a Study partner for PMP
Replies: 18
Views: 578

Re: Looking for a Study partner for PMP

I am also interested to connect , planning to give exam in December 2017.

My Mail id : komal.mutreja07@gmail.com

Please suggest how to proceed.
by komal
Wed Sep 06, 2017 8:56 am
Forum: PMP® Open Forum
Topic: Plan Risk Mangement Mock Test
Replies: 2
Views: 91

Re: Plan Risk Mangement Mock Test

Answer is B

Manish/Saket

Please elaborate question, what exactly is asked and why to choose option B.
by komal
Wed Sep 06, 2017 1:42 am
Forum: PMP® Open Forum
Topic: Plan Risk Mangement Mock Test
Replies: 2
Views: 91

Plan Risk Mangement Mock Test

Risk identification checklists are usually developed based on historical information and knowledge accumulated from previous similar projects. Which of the following statements about risk identification checklists is wrong? It is impossible to build an exhaustive checklist The lowest level of the Ri...
by komal
Wed Sep 06, 2017 1:04 am
Forum: PMP® Open Forum
Topic: Plan Risk Mangement
Replies: 0
Views: 73

Plan Risk Mangement

How to calculate Contingency reserve?
by komal
Sun Sep 03, 2017 1:30 pm
Forum: PMP® Open Forum
Topic: Quantitative Risk Analysis
Replies: 1
Views: 133

Quantitative Risk Analysis

Could you please explain EMV and Monte Carlo analysis technique in details with example. Also decision diagram mentioned under EMV in PMBOK5.
by komal
Mon Aug 28, 2017 4:28 am
Forum: PMP® Open Forum
Topic: Plan Risk Mangement: Tool and Techniques
Replies: 1
Views: 100

Plan Risk Mangement: Tool and Techniques

Can you please explain Analytical Technique in risk management, i could not understand its concept. Please explain with example if possible.
by komal
Fri Aug 25, 2017 7:30 am
Forum: PMP® Mock Exams Open Questions
Topic: Stakeholder Mgmt Strategy sample question
Replies: 10
Views: 1197

Re: Stakeholder Mgmt Strategy sample question

According to me it is avoiding risk.

Manish, can you please clarify if i am wrong .
by komal
Fri Aug 25, 2017 6:41 am
Forum: PMP® Mock Exams Open Questions
Topic: PMP Practice Questions
Replies: 5
Views: 562

Re: PMP Practice Questions

Manish,

I could not get what izenbridge has explain in description, please explain more .
by komal
Thu Aug 24, 2017 4:42 pm
Forum: PMP® Open Forum
Topic: Make or Buy Analysis
Replies: 11
Views: 384

Re: Make or Buy Analysis

Buy>Make then to be cost effective we should go make make in house.

Correct me if i am wrong.
by komal
Thu Aug 24, 2017 1:00 am
Forum: PMP® Open Forum
Topic: PMP Practice Questions
Replies: 5
Views: 270

Re: PMP Practice Questions

Even i couldn't understand calculation here,please explain.
by komal
Wed Aug 23, 2017 9:09 am
Forum: PMP® Open Forum
Topic: PMP Practice Questions
Replies: 1
Views: 131

PMP Practice Questions

A prime contractor in a customer project under CPFF contract has run into unexpected technical problems. Fixing them will require a lot of additional work to be done. The company made a decision to book more staff and equipment from their subcontractors in order to adhere to the agreed timeline. The...
by komal
Wed Aug 23, 2017 1:34 am
Forum: PMP® Open Forum
Topic: PMP Practice Questions
Replies: 1
Views: 130

PMP Practice Questions

In a traditionally drawn decision tree, a circle represents ___________. 1. a chance to which no expected monetary value can be assigned so that a likely pay-off can not be shown. 2. a decision to which no expected monetary value can be assigned so that a likely pay-off can not be shown. 3. a chance...
by komal
Wed Aug 23, 2017 1:23 am
Forum: PMP® Open Forum
Topic: PMP Practice Questions
Replies: 2
Views: 141

PMP Practice Questions

In order to speed up a project, you made a decision to fast-track a phase currently performed with five team members, and another one which was planned to begin in four weeks time with another five team members. Which of the following activities should you do first? 1. Make sure that all exit criter...
by komal
Wed Aug 23, 2017 1:14 am
Forum: PMP® Open Forum
Topic: PMP Practice Questions
Replies: 5
Views: 270

PMP Practice Questions

A production process has been defined as part of an industrial equipment manufacturing project. The process is intended to produce steel bolts with a length of 20 cm. The control limits are 19.955cm and 20.045cm. The measurements made at the end of the process yielded the following results: 20.033cm...
by komal
Wed Aug 23, 2017 1:06 am
Forum: PMP® Open Forum
Topic: PMP Practice Questions
Replies: 1
Views: 138

PMP Practice Questions

A company has to make a choice between two projects, because the available resources in money and kind are not sufficient to run both at the same time. Each project would take 9 months and would cost $250,000. The first project is a process optimization which would result in a cost reduction of $120...
by komal
Wed Aug 16, 2017 4:04 pm
Forum: PMP® Open Forum
Topic: Project Time Management
Replies: 7
Views: 342

Project Time Management

How to justify Schedule Management plan is major input to project management plan process ?
by komal
Wed Aug 16, 2017 1:23 am
Forum: PMP® Open Forum
Topic: Scope Management Mockups
Replies: 3
Views: 197

Scope Management Mockups

Jay and his team have just begun planning phase for their project which has duration of 3 years. Team has gone through project charter and is now developing scope management plan. One of the team members comes to Jay and mentions that project Management plan does not have quality management plan and...
by komal
Wed Aug 16, 2017 1:19 am
Forum: PMP® Open Forum
Topic: Scope Management Mockups
Replies: 1
Views: 115

Scope Management Mockups

What would be termed as conditions or capabilities that are to be met by project or present in the product or service, or result to satisfy an agreement or other formally imposed specification ? Acceptance criteria Contractual need Business case Requirements Please explain, my answer is Acceptance C...
by komal
Mon Aug 14, 2017 5:26 pm
Forum: PMP® Open Forum
Topic: Collect Requirements in Project Scope Management
Replies: 2
Views: 162

Collect Requirements in Project Scope Management

What is difference between focus group and facilitated Workshops? Please explain with an example.
by komal
Tue Aug 08, 2017 3:05 am
Forum: PMP® Open Forum
Topic: integration management Q&A
Replies: 6
Views: 312

Re: integration management Q&A

According me Option is D is correct, Cost management plan is part of Planning process group and budget can't be measured at each and every phase review, Hence Option D Correct.

Manish, Correct if i am wrong.
by komal
Sun Aug 06, 2017 7:45 am
Forum: PMP® Open Forum
Topic: Practice Question
Replies: 2
Views: 175

Practice Question

A project manager needs to develop a web site that allows users to submit expenses. There are two vendors competing for the project. Vendor A proposes an upfront fee of $20,000 and a maintenance fee of $4,000 per month. Vendor B proposes an upfront fee of $10,000 and a maintenance fee of $5,000 per ...
by komal
Sat Aug 05, 2017 3:18 pm
Forum: PMP® Open Forum
Topic: Project Staatus
Replies: 16
Views: 674

Re: Project Staatus

I could not get clarification, can you please put shadow again "How to justify project is completed" ?
by komal
Sat Aug 05, 2017 7:54 am
Forum: PMP® Open Forum
Topic: Project Staatus
Replies: 16
Views: 674

Re: Project Staatus

Then how cam i find project is completed or not , if i am not wrong from SPI =0.9 as shows project is behind schedule? Please share your views and clarify.
by komal
Fri Aug 04, 2017 5:24 pm
Forum: PMP® Open Forum
Topic: Project Staatus
Replies: 16
Views: 674

Re: Project Staatus

Don't we get an idea from Question statement During the completion of project that project is completed. Please clarify