Re: Passed PMP with above rating

Mighty Congrats :D
by Prembalaji
Tue Aug 29, 2017 10:04 am
Forum: PMP® Mock Exams Open Questions
Topic: Stakeholder Mgmt Strategy sample question
Replies: 10
Views: 1586

Re: Stakeholder Mgmt Strategy sample question

why cant the answer be " Stake holder management strategy " PMBOK says "Plan Stakeholder Management is the process of developing appropriate management strategies to effectively engage stakeholders throughout the lifecycle of the project, based on the analysis of their needs, interest...
by Prembalaji
Wed Aug 23, 2017 5:37 am
Forum: Oliver 175 PMP Questions
Topic: Oliver 175 - 53rd Question
Replies: 4
Views: 1089

Re: Oliver 175 - 53rd Question

Hi Jyoti , following to the PMBOK definition it also denotes "Quality audits are independent reviews performed by trained auditors or third-party reviewers"

so why cant the answer be "B. They must be third-party staff. "

can you please throw some light , Thanks
by Prembalaji
Wed Aug 23, 2017 4:57 am
Forum: PMP® Open Forum
Topic: PMP Practice Questions
Replies: 5
Views: 463

Re: PMP Practice Questions

I guess , since all the Values are within the control limits specified .
the answer should be "The process is under control. It should not be adjusted."
by Prembalaji
Mon Aug 14, 2017 6:14 am
Forum: PMP® Open Forum
Topic: PMP Q&A clarification
Replies: 6
Views: 492

PMP Q&A clarification

Q: The deliverable as well as the schedule baselines of your project have been changed three times. Which of the following is MOST LIKELY the cause of the changes? 1. The lack of clear instructions from project sponsor 2. Incomplete project management plans 3. The lack of a signed-off project charte...
by Prembalaji
Tue Aug 01, 2017 2:43 am
Forum: PMP® Open Forum
Topic: Project Staatus
Replies: 16
Views: 1141

Re: Project Staatus

The Answer should be - The project is completed and on Budget and behind the schedule.

CPI=1 is "on" budget (not over or under)
SPI=0.9 is behind schedule

Can someone correct me if im wrong
by Prembalaji
Mon Jul 17, 2017 8:21 am
Forum: PMP® Open Forum
Topic: Procurement Management Plan
Replies: 5
Views: 663

Re: Procurement Management Plan

Option 1 , cannot be the correct answer as procurement management plan deals about How to handle the procurement for the Project rather than , what is being handled in the Procurement .
by Prembalaji
Mon Jul 17, 2017 8:10 am
Forum: PMP® Open Forum
Topic: Analogous Estimates
Replies: 3
Views: 465

Re: Analogous Estimates

Parametric Estimating = ( Analogous Estimate + certain formula ) , the formula may be an explanation on the Scale at which the previous Projects is bigger or smaller to that of the current project , Since there is no such explanation about the scale or magnitude at the difference between the Current...
by Prembalaji
Mon Jun 19, 2017 6:48 am
Forum: PMP® Open Forum
Topic: Stakeholder Management
Replies: 6
Views: 570

Re: Stakeholder Management

I would pick: 1.Take into account risk tolerance (choosing the ans by elimination method) And to my understanding , working on Risk Tolerance would be PM and PM Teams responsibility rather than Sponsor/Customer , although Sponsor/Customer would contribute initially in giving their inputs for Risks ....