Forum: PMP® Open Forum
Topic: What activity will be involved to obtain management reserve?
Replies: 23
Views: 7448

Re: What activity will be involved to obtain management reserve?

I found this question online where answer is. A. Cost baseline B. Cost management plan C. Contingency reserves D. Managament reserves Online answer is D. Management reserves...but i think it should be C. Contingency reserves as in question it says that bugdet is set aside which should be contingency...
by jasmeenu
Mon Apr 24, 2017 5:47 pm
Forum: PMP® Open Forum
Topic: Project integration management
Replies: 6
Views: 2959

Re: Project integration management

For this question...scordo book says answer is " get single sponsor" Rita book say answer is " spending more time on configuration management. And a website tutorialspoint say answer is " determining reporting structure" Now its confusing as 3 sources give 3 different answer...