A task was scheduled to employ two persons, full time, and take two weeks to complete. Instead, the project manager was only able to assign one person to this task. At the end of two weeks, the person assigned to the task was 75% complete. What is the cost performance index? 0.75 1.50 0.25 1.15 Answ...
by catchnithi
Tue Apr 04, 2017 3:30 pm
Forum: PMP® Mock Exams Open Questions
Topic: Question on Change Request
Replies: 1
Views: 829

Question on Change Request

Your team member during execution identify that new task is needed to be added, which was critical for feature delivery related to performance. After analysis with team member you found that no change in deadline of project because of new task. what project manager to do next? a) Update the schedule...
by catchnithi
Tue Apr 04, 2017 3:29 pm
Forum: PMP® Mock Exams Open Questions
Topic: Question on stake Holder
Replies: 1
Views: 894

Question on stake Holder

You have Key stake holder who has High authority and low concern towards your Project, which type of stake holder he is
a) Power/interest,
b) power/influence,
c) salience model,
d) interest/influence
by catchnithi
Tue Apr 04, 2017 3:27 pm
Forum: PMP® Mock Exams Open Questions
Topic: Question on Control Cost
Replies: 2
Views: 1169

Question on Control Cost

BAC for Project is 120000 with total Project duration as 6 months, after 4 months project time budget utilized 55% that is 90,000.
What it is the value of Ev,PV,SV?
by catchnithi
Tue Apr 04, 2017 3:26 pm
Forum: PMP® Mock Exams Open Questions
Topic: Question on Quality
Replies: 3
Views: 1174

Question on Quality

Project is in middle of execution, project manager brought external auditor to ensure all quality methodology is followed in team. Which phase of project now
a) Perform quality assurance,
b) control quality,
c) risk audit
by catchnithi
Tue Apr 04, 2017 3:24 pm
Forum: PMP® Mock Exams Open Questions
Topic: Question on Communication Channel
Replies: 1
Views: 853

Question on Communication Channel

1) Manager form team of 10 member, for new project.how many communication channel wil exist in team now.
a) 45,
b) 55,
c) 35,
d) 50

----
Doubt is need to consider PM also .if so 11 - team size,,, ans wil be 55 , if PM need not to be consider then team size-10 ,asw will be 45.
by catchnithi
Tue Apr 04, 2017 2:53 pm
Forum: PMP® Mock Exams Open Questions
Topic: Sample Questions
Replies: 3
Views: 1045

Re: Sample Questions

I am new to forum !! will post each questions separately.
PMP exam question attached , marked the answers also.. !! need to know whether right..
by catchnithi
Tue Apr 04, 2017 2:51 pm
Forum: Oliver 175 PMP Questions
Topic: Oliver 175 - 77th Question
Replies: 2
Views: 1538

Re: Oliver 175 - 77th Question

Passive risk acceptance !!
Is right ?.
by catchnithi
Tue Apr 04, 2017 2:34 pm
Forum: PMP® Mock Exams Open Questions
Topic: Sample Questions
Replies: 3
Views: 1045

Sample Questions

Hi Forum Leads, Here are few questions, need your suggestion for review.. real PMP questions from my friend. If any wrong answer,, guidance to correct 1) Manager form team of 10 member, for new project.how many communication channel wil exist in team now. a) 45, b) 55, c) 35, d) 50 ANs: 45 2) Projec...