Re: Confidence Level

Thanks - So answer will be .68? Since SD of the project is 2.7?

a).68
b).997
c).95
d).88
by vaishnavi
Mon Apr 24, 2017 2:33 pm
Forum: PMP® Open Forum
Topic: Confidence Level
Replies: 4
Views: 598

Confidence Level

Hi, Critical path of the project has 3 activities in sequence . Activity A has optimistic estimate as 8,pessimistic as 16 and most likely as 12.Activity B has optimistic estimate as5,Pessimistic estimates as15 and most likely estimate as 0.Activity C has optimistic estimate as 10,pessismistic estima...
by vaishnavi
Thu Apr 06, 2017 2:13 pm
Forum: PMP® Open Forum
Topic: Question on Over budget
Replies: 1
Views: 226

Question on Over budget

Your project is running slightly over budget. You mention this to another project manager, who suggests you shift some of your expenses to indirect costs that are not charged to your project budget. What do you do? A)Crash the project. b)Use your contingency reserves. C)According to the other projec...
by vaishnavi
Wed Mar 22, 2017 3:04 pm
Forum: Oliver 175 PMP Questions
Topic: Oliver 175 - 173rd QUESTION
Replies: 4
Views: 1079

Re: Oliver 175 - 173rd QUESTION

Thanks for Clarifying - I missed to understand question correctly
by vaishnavi
Mon Mar 20, 2017 2:51 pm
Forum: Oliver 175 PMP Questions
Topic: Oliver 175 - 173rd QUESTION
Replies: 4
Views: 1079

Oliver 175 - 173rd QUESTION

Hi ,

Can some one please explain me with below question?

What is wrong in this diagram? 173



o The data date must be accurately between weeks.
o AC cannot be higher than PV when EV is lower.
o EV cannot be assessed beyond the data date.
o PV cannot be assessed beyond the data date.
Image.png
Image.png (15.56 KiB) Viewed 1079 times