Re: Mock Tech Numerical

When project performance shows over budget then a new EAC should be calculated .
At that time TCPI should be

TCPI = BAC-EV/( EAC-AC) but since it is under budget then CPI <1
TCPI = BAC-EV/( BAC-AC) might be used . CPI>1

Hopefully it clarifies!
by nazrulq
Tue Sep 19, 2017 5:12 am
Forum: PMP® Open Forum
Topic: User Story
Replies: 3
Views: 20

User Story

2.The Main Purpose is to write user story is to:

A. To communicate progress of the Project

B. To document features required by stakeholders

C. To perform what if statements

D. To record issues encountered on the project.


Answer: Stakeholders requirement as option B.
by nazrulq
Sun Sep 17, 2017 6:05 pm
Forum: PMP® Open Forum
Topic: Mock Tech Numerical
Replies: 3
Views: 49

Re: Mock Tech Numerical

The question is asking for to find out To Complete Performance Index (TCPI) . If the full solution is required. Complete solution
can be provided!
by nazrulq
Sun Sep 17, 2017 3:45 am
Forum: PMP® Open Forum
Topic: Critical Path
Replies: 9
Views: 134

Re: Critical Path

Thanks Manish by assumption was right. By definition Critical Path have "zero Float". If there is a negative float then it means the activities were fast tracked or crushed .Buffer is removed usually from Critical Path but imposed in Critical Chain as feeding buffer and project buffer! Reg...
by nazrulq
Fri Sep 15, 2017 2:55 am
Forum: PMP® Open Forum
Topic: In Question, which Organization procedure can support in managing feedback's?
Replies: 4
Views: 146

Re: In Question, which Organization procedure can support in managing feedback's?

I think the best option is to look for Risk Control procedures to see how risks have to be managed for the next increment. Hence option D is the best fit!
My justification defect might have identified by stakeholder which can Create Risk to the project!
by nazrulq
Fri Sep 15, 2017 2:40 am
Forum: PMP® Open Forum
Topic: Critical Path
Replies: 9
Views: 134

Re: Critical Path

In Critical Path, there is no Resouce Limitation.Usually, to calculate critical path method there is no resource limitation
considered. I might be wrong !

Any suggestion will be appreciated.

The correct answer was Option 1.

Want to Clarify!
by nazrulq
Fri Sep 15, 2017 12:17 am
Forum: PMP® Open Forum
Topic: Procurement Management Influence
Replies: 1
Views: 36

Procurement Management Influence

Decisions made in developing the procurement management plan may have least influence on ……..

1.Project Schedule

2.Project Budget

3.Project Human Resource Need

4.Risk Management Plan

Correct Answer:3

Explanation given are not much satisfactory can Manish elaborate please!
by nazrulq
Thu Sep 14, 2017 5:43 am
Forum: PMP® Open Forum
Topic: Mock Test
Replies: 4
Views: 80

Re: Mock Test

I think we have to find out who are the stakeholders directly involved in Operation. Call Centre Head - Operational Stakeholder Retail Worker -Operational Stakeworker Plant Operational Chief - Operational Stakeholder Financial Departmental Manager - Dealing with finance. His involvement in this proj...
by nazrulq
Thu Sep 14, 2017 12:07 am
Forum: PMP® Open Forum
Topic: Project Progress Report
Replies: 2
Views: 49

Project Progress Report

When Project Progress to be shown in higher management, milestone chart is the best form while the team or lower a level bar chart i s preferred way. How about if nothing is mentioned in the question or to be presented in townhall meeting where higher management and lower staffs along with project t...
by nazrulq
Thu Sep 14, 2017 12:02 am
Forum: PMP® Open Forum
Topic: Fast Tracking
Replies: 2
Views: 44

Fast Tracking

Q. Project Manager along with team member discuss about the fast tracking of the project schedule. To fast track which of the following statement are true: 1. Project has extra money in contingency reserve. 2. The project has high risk. 3. Activities have preferential dependencies. 4. Add resources ...
by nazrulq
Wed Sep 13, 2017 11:53 pm
Forum: PMP® Open Forum
Topic: Critical Path
Replies: 9
Views: 134

Critical Path

Q. Critical Path Assumes which of the following:

1. There is no resource limitation needed.

2. Resource Optimization has occurred already.

3. Resource Limitation Needed.

4. Start and finish dates of the activities are fixed!
by nazrulq
Wed Sep 13, 2017 11:32 pm
Forum: PMP® Open Forum
Topic: Common vs special causes of variation.
Replies: 4
Views: 83

Re: Common vs special causes of variation.

If seven readings for example 3.6%,3.8%,3.9%,3.1%,3.2%,3.5%,3.7% below the mean. Then there is a problem in dairy fat analysis system.Should be investigated!
by nazrulq
Tue Sep 12, 2017 8:46 pm
Forum: PMP® Open Forum
Topic: Hi need a good explanation on funding limit reconciliation? please help
Replies: 2
Views: 60

Re: Hi need a good explanation on funding limit reconciliation? please help

Project Funding Limit Reconciliation is to check variance of project funding limit and the planned expenditure at a given point of time. Project Manager has to reconcile (adjustment) the availability of fund for the work. For example, the fund is due after 15 days but PM needs the money now. He has ...
by nazrulq
Tue Sep 12, 2017 8:29 pm
Forum: PMP® Open Forum
Topic: Mock Test
Replies: 4
Views: 64

Re: Mock Test

SPI at the end of 4 month = .9 <1 Still less CPI at the end of 4 month SPI = EV/PV EV(4) = SPI X PV =.9 x 10 = 9M so CPI(4) = EV/AC =9/8 =1.125 CPI at the end of 2 month EV(2) = SPI x PV =.5 x 10 =5 M ; So CPI(2) = EV/AC = 5/2 =2.5 From the example above CPI is detoriating but still > 1 but SPI =.9<...
by nazrulq
Tue Sep 12, 2017 4:40 am
Forum: PMP® Open Forum
Topic: Contingency reserve tricky question.
Replies: 11
Views: 176

Re: Contingency reserve tricky question.

Thanks ! Really interesting question!
by nazrulq
Mon Sep 11, 2017 5:29 pm
Forum: PMP® Open Forum
Topic: Change Request!
Replies: 4
Views: 71

Change Request!

If changes are approved by CCB but rejected by sponsor, in that case baselines is needed to be updated! As there is a rejection. No need for updation. CCB approved does n't mean baselines need to be updates! CCB's approvals for changes are not final! :o I think, Izenbridge Webinar missed that point ...
by nazrulq
Mon Sep 11, 2017 5:01 pm
Forum: PMP® Open Forum
Topic: Closing Process Group
Replies: 0
Views: 34

Closing Process Group

Q1. In this situation when construction support or maintenance is either written or nor written in contract , the project to be closed. I think if it is not written then project considered to be closed! Q2. When project team to be released as it is the last step of the project closure. Of course aft...
by nazrulq
Mon Sep 11, 2017 4:34 pm
Forum: PMP® Exam Lessons – Success Stories
Topic: Passed PMP - First Attempt - Sep 11!
Replies: 4
Views: 192

Re: Passed PMP - First Attempt - Sep 11!

Congratulations! They Changed the Proficiency from Proficient , Moderately Proficient and below proficient to
Above Target ,Target, Below Target! :D
Best of luck!
by nazrulq
Mon Sep 11, 2017 5:56 am
Forum: PMP® Open Forum
Topic: Contingency reserve tricky question.
Replies: 11
Views: 176

Re: Contingency reserve tricky question.

Let me try to give the answer in elaborate approach. Let's discuss what is a residual risk and secondary risk. Residual Risks are the risks which remain after risk response. Now what is secondary risk! Secondary risk (Unknown is the risk after implementing risk response. These could be new risks. Th...
by nazrulq
Mon Sep 11, 2017 5:24 am
Forum: PMP® Open Forum
Topic: Scope Management Mockups
Replies: 3
Views: 72

Re: Scope Management Mockups

Validation is the right choice as per my point of view.
by nazrulq
Mon Sep 11, 2017 5:06 am
Forum: PMP® Open Forum
Topic: PMP Q&A clarification
Replies: 6
Views: 199

Re: PMP Q&A clarification

In both of the Contracts (CPAF) and CPFF, the buyer has to pay for the cost incurred. But the main difference is in cost plus award fee the buyer is paying an award fee subject to completion of work.In cost plus fixed fee contact, the buyer pays fixed amount of fee upon completion of all work includ...
by nazrulq
Fri Sep 08, 2017 6:09 pm
Forum: PMP® Open Forum
Topic: Plan Risk Mangement Mock Test
Replies: 1
Views: 48

Re: Plan Risk Mangement Mock Test

Option 4.

Risk Register is will be identified and updated all time. Not only in Risk Response Process!
by nazrulq
Fri Sep 08, 2017 3:57 am
Forum: PMP® Open Forum
Topic: How phase to phase relationship can impact the project completion?
Replies: 6
Views: 347

Re: How phase to phase relationship can impact the project completion?

Option C is the right choice I think.It is kind of sequencing all activity which can be done in Project Schedule Management hence is the right choice ,I guess!
by nazrulq
Fri Sep 08, 2017 3:45 am
Forum: PMP® Open Forum
Topic: Change Management procedure
Replies: 9
Views: 157

Re: Change Management procedure

Hello! Not everytime PM is approving (As defined in Project Charter) it requires final approval in terms of cost which also relates to scope, schedule, risk, and resources. Please remember triple constraint is the basic and in addition risk, resources and quality any of those six constraints need th...
by nazrulq
Thu Sep 07, 2017 11:03 pm
Forum: PMP® Open Forum
Topic: Change Management procedure
Replies: 9
Views: 157

Re: Change Management procedure

In addition, Change Request must be approved by CCB and by the sponsor (who provides funding) as it requires additional cost, time and resources.Scope to be changed too!
Once all has been approved it has to be recorded to Change log and Project Management Plan and Project Document to be updated.
by nazrulq
Thu Sep 07, 2017 10:21 pm
Forum: PMP® Open Forum
Topic: Communication Channel
Replies: 4
Views: 93

Re: Communication Channel

That was my answer too. I guess it was n't correct!
by nazrulq
Thu Sep 07, 2017 10:19 pm
Forum: PMP® Open Forum
Topic: Plan Risk Mangement Mock Test
Replies: 4
Views: 99

Re: Plan Risk Mangement Mock Test

How do you know the fallback plan is the right choice usually a backup plan. Specific event triggered if it is known can be managed by Contingency reserve not clearly mentioned.
Risk Mitigation is a general risk response strategies.
Further explanation might clear the situation!
by nazrulq
Thu Sep 07, 2017 5:09 am
Forum: PMP® Open Forum
Topic: Change Management procedure
Replies: 9
Views: 157

Change Management procedure

I am sharing my view points regarding change management procedure as now a days lots of situational questions regarding change management issues are coming in PMP exam. The procedures in order is listed below: 1. Evaluation of Changes a. PM by himself. b. With Project Team 2. Identify Options. a. Pr...
by nazrulq
Thu Sep 07, 2017 4:09 am
Forum: PMP® Open Forum
Topic: Communication Channel
Replies: 4
Views: 93

Communication Channel

Q: You are managing a team of 10 people . How many Communication Channel you need? Answer : 1. 55 2. 45 3. 35 4.60 Answer should be Option 1 or Option 2 . How to determine if question does n't say about inclusion or exclusion of Project Manager. What Should be by default situation! Can Manish explai...
by nazrulq
Thu Sep 07, 2017 3:45 am
Forum: PMP® Open Forum
Topic: Looking for a Study partner for PMP
Replies: 18
Views: 328

Re: Looking for a Study partner for PMP

Interested.
by nazrulq
Wed Sep 06, 2017 8:36 pm
Forum: PMP® Open Forum
Topic: Saket Bansal Sir's name in PMBOK 6
Replies: 4
Views: 93

Re: Saket Bansal Sir's name in PMBOK 6

Congratulations Saket ! Deserved acknowledgment. I do n't know whether they add Risk Management in execution. That should be changed too. The renamed Time Management to Schedule Management and Human Resource Management to Resource Management and add Agile Method. Yes Just check they have 49 processe...
by nazrulq
Wed Sep 06, 2017 8:31 pm
Forum: PMP® Open Forum
Topic: time menagement Q/A
Replies: 2
Views: 53

Re: time menagement Q/A

Q 13. The answer I think, should be lag time. Total Float : The amount of time that a schedule activity can be delayed or extended from its early start without delaying project finish date or violating schedule constraint. Lag : The amount of time whereby successor activity is required to be delayed...
by nazrulq
Mon Aug 28, 2017 4:10 am
Forum: PMP® Open Forum
Topic: Conduct Procurement
Replies: 1
Views: 73

Conduct Procurement

Question :Larry is the project manager and working with procurement department of his organization to do procurement for his project. Procurement department said these are usual commodities and same has been procured many time. Also as this has been procured multiple times, generally they receive re...
by nazrulq
Mon Aug 28, 2017 1:10 am
Forum: PMP® Open Forum
Topic: Communication/ Stakeholder Manaagement
Replies: 1
Views: 73

Communication/ Stakeholder Manaagement

Q.You are working on project which automates the service call handing process of one car servicing company, in the mid of the project, marketing team realized that they are also getting impacted with this automation and provided set of requirements to be included in this project , what is the BEST t...
by nazrulq
Mon Aug 28, 2017 1:06 am
Forum: PMP® Open Forum
Topic: Return of Investment (ROI)
Replies: 2
Views: 95

Re: Return of Investment (ROI)

Rita's book does n't say anything for that but Andy crowe is! Sometimes you need you read more book.
PMP exam is different . I do n't see any thing about ROI usually its a wrong choice in the exam!
ROI should be in % . Is there any range while selecting project!

Thanks Manish!
by nazrulq
Mon Aug 28, 2017 1:01 am
Forum: PMP® Open Forum
Topic: Make or Buy Analysis
Replies: 11
Views: 253

Re: Make or Buy Analysis

Cleared thanks!
by nazrulq
Mon Aug 28, 2017 1:00 am
Forum: PMP® Open Forum
Topic: Manage Project Team
Replies: 2
Views: 93

Re: Manage Project Team

Thank You! Not cleared when to use Empathy!
by nazrulq
Sat Aug 26, 2017 11:27 pm
Forum: PMP® Open Forum
Topic: Make or Buy Analysis
Replies: 11
Views: 253

Re: Make or Buy Analysis

Question mentioned $50 per month and expecting 1000 users per month.
My answer after 2.3 month make decision ( My mistake Sorry! ) would be fruitfull.

Thank You Manish for catching my mistake.
by nazrulq
Sat Aug 26, 2017 10:53 pm
Forum: PMP® Open Forum
Topic: Return of Investment (ROI)
Replies: 2
Views: 95

Return of Investment (ROI)

For which types of Projects (Is that all Project) ROI is needed. I guess it is not a Project Selection Criteria!

Can Manish Explain Please !
by nazrulq
Sat Aug 26, 2017 10:38 pm
Forum: PMP® Open Forum
Topic: Manage Project Team
Replies: 2
Views: 93

Manage Project Team

Question : Project Manager has problems in managing few team members in his team. Project Manager has problem managing him in desired direction.Based on Daniel Golman's mixed model for emotional intelligence the team members have to work on: 1. Self-awareness 2. Empathy 3.Social Skills 4.Self Regula...
by nazrulq
Sat Aug 26, 2017 4:38 am
Forum: PMP® Mock Exams Open Questions
Topic: Stakeholder Mgmt Strategy sample question
Replies: 10
Views: 946

Re: Stakeholder Mgmt Strategy sample question

Answer: Facilitated Workshop is the correct answer, I guess!
by nazrulq
Sat Aug 26, 2017 4:32 am
Forum: PMP® Open Forum
Topic: How to process changes during an initial stage of the project?
Replies: 13
Views: 774

Re: How to process changes during an initial stage of the project?

I think Option C is the current choice. First PM has to analyze the situation about change management .
by nazrulq
Fri Aug 25, 2017 6:53 pm
Forum: PMP® Open Forum
Topic: Make or Buy Analysis
Replies: 11
Views: 253

Re: Make or Buy Analysis

Let me explain if I have understood the question clearly Option 1 (To Make) To make in house , cost of making the module is =$ 50000 Cost of Maintainance is 30000/Month Option2 (To Buy) $50/Month , No of people expected =1500/Month Maintainance =1500/Month let the number of months = M When make and ...
by nazrulq
Tue Aug 22, 2017 5:43 am
Forum: PMP® Open Forum
Topic: Calculation of Standard Deviation from various Data
Replies: 0
Views: 62

Calculation of Standard Deviation from various Data

Following data points are used 5, 6, 7,8,9, 10. from that point calculate STD ( Standard Deviation)

Mean = 5 + 6 + 7+8 +9 + 10 = 45/ 6 =7.5

Variance = (7.5-5) ² + ( 7.5-6)² +(7.5-7)²+ (7.5-8)²+ (7.5-9)²+(7.5-10)² = 17.5

Std = Sqrt (Var)= Sqrt (Variances) = 4.18
by nazrulq
Tue Aug 22, 2017 5:28 am
Forum: PMP® Open Forum
Topic: Communication Channels!
Replies: 1
Views: 55

Communication Channels!

Please advise in calculating communication channel n. Sometimes exam does n't give clue whether PM is included or not!

Thanks.
by nazrulq
Tue Aug 22, 2017 5:15 am
Forum: PMP® Open Forum
Topic: Key Perfomance Indicator (KPI), Exam Content Outline (June 2015)
Replies: 2
Views: 85

Key Perfomance Indicator (KPI), Exam Content Outline (June 2015)

What is KPI? Is KPI lagging factor or leading factor! KPI - Is the key performance indicator or the organization showing organizations performance. KPI use to be lagging factor not leading factor. Generally, SMART techniques applied to KPI - S pecific, M easurable, A ttainable, R ealistic and T ime-...
by nazrulq
Tue Aug 22, 2017 4:51 am
Forum: PMP® Open Forum
Topic: Change Log, Issue log & Change Request
Replies: 10
Views: 2308

Re: Change Log, Issue log & Change Request

Option D is the correct answer, I guess! Approved Change request which is approved by change control board (CCB) to be incorporated in the change log. If stakeholder asked for the information, they can be referred to Change log where approved change request is noted. stakeholders concerns are record...
by nazrulq
Sat Aug 19, 2017 3:36 am
Forum: PMP® Open Forum
Topic: Scope Management Mockups
Replies: 3
Views: 132

Re: Scope Management Mockups

Quality Management Plan is not required at the level of creation of Scope Management Plan. May be high level quality management plan is needed to be required but detail level quality requirement is not necessary as progressive elaboration might required later! Hopefully it justifies! Manish can expl...
by nazrulq
Sat Aug 19, 2017 3:09 am
Forum: PMP® Open Forum
Topic: Project Time Management
Replies: 7
Views: 217

Re: Project Time Management

Schedule Management Plan is a subsidiary plan of Project Management Plan. Schedule Management Plan is not a input rather Project Management Plan is a input of Plan Schedule Management. Output of that is Schedule Management Plan. In fact Project Management plan is the input of all 8 Management Plan e...
by nazrulq
Thu Aug 17, 2017 6:01 am
Forum: PMP® Open Forum
Topic: Project Time Management
Replies: 7
Views: 217

Re: Project Time Management

There are other Plans to which feed into Project Management Plan
1. Stakeholder Management Plan
2. Integration management Plan.
3. Process Improvement Plan. (Subsidiary Plan of Quality Management Plan)
4. Requirement Management Plan ( Subsidiary Plan of Scope Management Plan)