Search found 250 matches

by nazrulq
Tue Dec 12, 2017 2:54 am
Forum: PMP® Open Forum
Topic: Conflict Management
Replies: 0
Views: 9

Conflict Management

Question: Your supplier delivered building raw material a week late. To bring some degree of satisfaction, he reduced its cost by 8%. This offer is an example of? A: Compromise B: Collaborate C: Smoothing D: Forcing My Answer: C Correct Answer: B Explanation: Intension is to bring some harmony in re...
by nazrulq
Tue Dec 12, 2017 2:54 am
Forum: PMP® Open Forum
Topic: Conflict Management
Replies: 0
Views: 7

Conflict Management

Question: Your supplier delivered building raw material a week late. To bring some degree of satisfaction, he reduced its cost by 8%. This offer is an example of? A: Compromise B: Collaborate C: Smoothing D: Forcing My Answer: C Correct Answer: B Explanation: Intension is to bring some harmony in re...
by nazrulq
Sat Dec 09, 2017 9:19 pm
Forum: PMP® Open Forum
Topic: Decomposition
Replies: 0
Views: 15

Decomposition

Q. Decomposition is a must to create activity of the project . Which of the following does n't say much about decomposition: 1. Until it can n' t be realistically estimated. 2. Activities can not be decomposed. 3.Until meaningful conclusion. 4. Can not decomposed more that 5 levels. Correct Answer i...
by nazrulq
Sat Dec 09, 2017 3:59 am
Forum: PMP® Open Forum
Topic: Project management Process Group
Replies: 2
Views: 27

Project management Process Group

The key purpose of this process group is to align stakeholder's expectation within the project scope and to give them visibility about the scope and project objectives. Which process group is referred here: 1. Initiating 2.Planning 3.Executing 4. Monitor and controlling 5. Closing. In my opinion I e...
by nazrulq
Sat Dec 09, 2017 3:46 am
Forum: PMP® Open Forum
Topic: HR Management
Replies: 2
Views: 31

Re: HR Management

I think Punishment is not Suggested to solve the issue like this. Discussion or forcing can be done. As both of them are not in the answer option. Better go with elimination. As the question mentioned to use coercive (formal) power his manager can be contacted to force him work! Further clarificatio...
by nazrulq
Sat Dec 09, 2017 3:37 am
Forum: PMP® Open Forum
Topic: Project Charter
Replies: 2
Views: 21

Re: Project Charter

I think option 3 is the right choice. Project Charter has not been approved yet finally. It is in the process of development. Project sponsor should give authority to the Project Manger for using project statement of work to have access to it.
I think option 4 is not the right choice.
by nazrulq
Thu Dec 07, 2017 6:18 am
Forum: iZenBridge PMP Open Questions
Topic: Ethical question
Replies: 8
Views: 227

Re: Ethical question

Same type question in Scordo answered withdrawal or cancellation of the project but as Manish said some middle eastern counties and some countries in Africa have adopted the same rule.
I think if PMI s concern to cancel the project, they should revise their answer and made it as per option 4.
by nazrulq
Wed Dec 06, 2017 4:17 am
Forum: PMP® Open Forum
Topic: Work Performannce
Replies: 2
Views: 65

Work Performannce

Q. You the project manager of a team in where the team is collecting datas and transform them into work performance information for the key stakeholder in biweekly basis. Which of the following does n't provide a sufficient platform to share this information with the stakeholders? A. Project File Up...
by nazrulq
Fri Dec 01, 2017 3:41 am
Forum: PMP® Open Forum
Topic: Project Selection
Replies: 1
Views: 36

Project Selection

Question: John is the Project Manager of Company Z. There are two projects in the market to bid on. Project A has ROI ( Return on Investment) 52% but required high technical skills, Project B has ROI 30%. John's company has lack of technical skill to bid but has the capability to bid on Project B. T...
by nazrulq
Fri Dec 01, 2017 3:20 am
Forum: PMP® Open Forum
Topic: Stakeholder Management
Replies: 0
Views: 30

Stakeholder Management

Correct Answer D. Justification Issue log is an output of Manage Stakeholder Engagement. Since New Stakeholder is added in the Project Stakeholder Management Plan to be updated. List of Stakeholder which is Stakeholder register is needed to be revised with the new addition. New Stakeholder could be ...
by nazrulq
Tue Nov 28, 2017 6:42 am
Forum: PMP® Open Forum
Topic: Passed my PMP Today...1st attempt..."above target" in all 5 domains
Replies: 3
Views: 99

Re: Passed my PMP Today...1st attempt..."above target" in all 5 domains

Congratulations! All the very best to your future endeavour!
by nazrulq
Tue Nov 28, 2017 1:53 am
Forum: PMP® Open Forum
Topic: Projectized / Functional Organization
Replies: 1
Views: 48

Projectized / Functional Organization

You are working in a functional Organization X in North America where the working and other environment is homely in nature . They are really taking care of their own employees . Very recently you got an offer with a salary of 1.5 times from a Projectized organization Y and join there by knowing the...
by nazrulq
Tue Nov 28, 2017 1:14 am
Forum: PMP® Open Forum
Topic: Stakeholder Management ( Real Life Question)
Replies: 0
Views: 40

Stakeholder Management ( Real Life Question)

Question: You are working in a Daycare School, some young children are totally uncontrollable and cause damage to property and subject to very racial misbehaviour to the employees who are the teacher of the daycare. The authority has connected the daycare under video surveillances recently. To keep ...
by nazrulq
Sat Nov 25, 2017 11:08 pm
Forum: PMP® Open Forum
Topic: Contract Type
Replies: 3
Views: 86

Contract Type

Q. Project Manage wanted to award some renovation contract to a preferred source, the contractor said the Total Cost of the contract $ 20000 . Cost of material and others is $16000 and the fees will be $4000. What type of Contract it is? 1. Fixed Price 2. Time and Material Contract 3.Cost plus fixed...
by nazrulq
Sat Nov 25, 2017 5:54 pm
Forum: iZenBridge PMP Open Questions
Topic: izenbridge Free Mock Q 67
Replies: 6
Views: 166

Re: izenbridge Free Mock Q 67

You need to know from Pareto Chart the cause 80/20 and put into the order in histogram to find out whether there is a need to deal with them you categorize the defect.My point of view Pareto Chart would be best option and there is not much use of histogram too. You then need to check out with Contro...
by nazrulq
Sat Nov 25, 2017 8:42 am
Forum: iZenBridge PMP Open Questions
Topic: izenbridge Free Mock Q 67
Replies: 6
Views: 166

Re: izenbridge Free Mock Q 67

Pareto Diagram also called 80/20 Rule. That is 80 percent problem happen from 20 percent cause. It also categorize defect in order from higher to lower!
by nazrulq
Thu Nov 23, 2017 5:17 pm
Forum: PMP® Open Forum
Topic: Cost Plus Contract
Replies: 0
Views: 49

Cost Plus Contract

Question: Which of the following does not encourage the seller to control cost and as a result, places the greatest risk to the buyer! Cost-Exclusive Cost Plus fixed fee Cost plus incentive fee Cost plus percentage of cost I think the right answer should be Cost Contract ( where seller gets no benef...
by nazrulq
Thu Nov 23, 2017 5:59 am
Forum: PMP® Open Forum
Topic: Project Objective
Replies: 1
Views: 59

Project Objective

Q. Who should be defining Project Objective?

Answer:

1. Stakeholders
2.Project Management Team.
3.Project Sponsor.
4.Project Manager.

Correct Answer:

Option 3.

Can somebody give the reference where to find in PMBOK?
Aillen Ellis book said that Project Manager. Page-35
by nazrulq
Mon Nov 20, 2017 4:14 am
Forum: iZenBridge PMP Open Questions
Topic: Situational Question
Replies: 5
Views: 228

Re: Situational Question

At first, PM has to analyze the impact of the change either alone or with the team before taking the further option.
Implementation of change only done after approval of CCB.But he has to log the change request either approved or rejected!
by nazrulq
Mon Nov 20, 2017 4:09 am
Forum: iZenBridge PMP Open Questions
Topic: Project Closure
Replies: 7
Views: 288

Re: Project Closure

Partial Release and PMP updates and Projects Documents updates can be done parallelly. Sometimes questions can be confusing!

Thanks
by nazrulq
Tue Oct 24, 2017 4:13 pm
Forum: PMP® Open Forum
Topic: Change Control
Replies: 8
Views: 465

Re: Change Control

The answer option should be preventive action and defect repair. That would be the best answer. Unfortunately, those questions make people fail in the exam! As mostly fail for 10 to 20 questions . That does n't mean your knowledge is limited. I think PMI should take out confused questions from their...
by nazrulq
Mon Oct 23, 2017 9:05 pm
Forum: PMP® Open Forum
Topic: Change Control
Replies: 8
Views: 465

Re: Change Control

Those are really confused questions! I hope in real PMP question will be straight forward!
Thanks for the participation!
by nazrulq
Thu Oct 19, 2017 4:02 am
Forum: PMP® Open Forum
Topic: Change Control
Replies: 8
Views: 465

Change Control

A regularly scheduled inspection of the manufacturing line is completed and has noted that a key piece of machinery is showing signs of wear and damage much earlier than expected. A change request has been submitted to be reviewed by the Change Control Board to interrupt product manufacturing in ord...
by nazrulq
Thu Oct 19, 2017 3:58 am
Forum: PMP® Open Forum
Topic: Perform integrated Change Control
Replies: 2
Views: 215

Re: Perform integrated Change Control

Thanks Saket. Project Manager is Responsible for All processes (47) from inception to completion, Ref : PMBOK 5 Page -96 ; Ist Paragraph. Change Management such as change request either to be approved or rejected is Project Manager or Project sponsor is ultimately responsible. PMBOK -5 ,page -96 3rd...
by nazrulq
Wed Oct 18, 2017 6:23 am
Forum: PMP® Open Forum
Topic: Project Closure Documents
Replies: 3
Views: 269

Re: Project Closure Documents

Thank You Manish. That was my guess too. When Buyer and Seller relationship happens always contract is a mutual agreement .Sometimes we verify with Project management Plan as it is a input of close Project/ phase process!
by nazrulq
Wed Oct 18, 2017 6:19 am
Forum: PMP® Open Forum
Topic: Perform integrated Change Control
Replies: 2
Views: 215

Perform integrated Change Control

Q. Perform Integrated Change Control Process is conducted from project inception through completion and is ultimately the responsibility of the: Answer: 1. Project Sponsor 2. Project manager 3. Project Stakeholders 4. None of the above. Q. Who is Responsible for Change Management 1. Project Manager ...
by nazrulq
Mon Oct 16, 2017 6:16 am
Forum: PMP® Open Forum
Topic: Project Closure Documents
Replies: 3
Views: 269

Project Closure Documents

Q. Project is near to completion, Project charter is the document which authorized the project in the beginning. The contractor has his own Project Charter to implement the project. Now customer needs to verify the project deliverables as mentioned in the project charter. To which document PM to ref...
by nazrulq
Tue Oct 10, 2017 8:22 pm
Forum: PMP® Open Forum
Topic: Standard Deviation
Replies: 2
Views: 273

Re: Standard Deviation

2 of course. Option 2 is 2.

Thanks!

Regards,
by nazrulq
Fri Oct 06, 2017 5:39 pm
Forum: PMP® Open Forum
Topic: Change Request!
Replies: 5
Views: 433

Re: Change Request!

Thanks Manish for clarity!
by nazrulq
Fri Oct 06, 2017 5:21 pm
Forum: PMP® Open Forum
Topic: Standard Deviation
Replies: 2
Views: 273

Standard Deviation

Q:A project manager made 3-point estimates on a critical path and found the following results: Need help is calculating the below problem Optimistic Most Likely Pessimistic PERT Weighted Avg Act. A 12 15 24 16 Act B 8 9 14 9.7 Act. C 15 19 27 19.7 Act. D 10 14 28 15.7 Act. E 17 20 35 22 Estimate for...
by nazrulq
Fri Oct 06, 2017 5:14 pm
Forum: PMP® Exam Lessons – Success Stories
Topic: Passed PMP with above rating
Replies: 4
Views: 622

Re: Passed PMP with above rating

Congratulations!
by nazrulq
Thu Oct 05, 2017 5:36 pm
Forum: PMP® Open Forum
Topic: Workaround
Replies: 3
Views: 345

Re: Workaround

As there is no execution phase for the Risk Management in PMBOK5 it should be in Monitor and control. But According to PMBOK6 it would be in execution phase! We are safe till March 26,2018! :D :D
by nazrulq
Thu Oct 05, 2017 5:32 pm
Forum: PMP® Open Forum
Topic: SPI=.8 CPI= 1 , Deliverables Status!
Replies: 2
Views: 247

SPI=.8 CPI= 1 , Deliverables Status!

If SPI = .8 , CPI=1 and project is closed out in my understanding; all deliverables are not given but the project is on budget. The Project might be cancelled. But Schedule was it was behind; as it is behind the schedule, not all activities fully performed and all deliverables were not given to the ...
by nazrulq
Thu Oct 05, 2017 3:56 am
Forum: iZenBridge PMP Open Questions
Topic: residual risk and secondary risk difference
Replies: 2
Views: 345

Re: residual risk and secondary risk difference

I do n't think residual risks are low priority risks could be the moderately priority too. Those risks remain after mitigation plan.Only low priority can be placed in Watchlist.

I think Manish Can clarify more!
by nazrulq
Thu Oct 05, 2017 2:32 am
Forum: PMP® Open Forum
Topic: Whats the correct answer?
Replies: 8
Views: 592

Re: Whats the correct answer?

I think Project Charter has already developed.High-level information is listed in Project Charter! According to my opinion, it is early to develop planning. Stakeholders Identification in detail level is required. Bit Confused, this identification of stakeholder in detail and develop project managem...
by nazrulq
Tue Oct 03, 2017 2:23 am
Forum: PMP® Open Forum
Topic: Stakeholder Analysis query.
Replies: 2
Views: 190

Re: Stakeholder Analysis query.

Whatever his role is in different stages of the project, he is the ultimate approver of project funding. He has to be managed by PM very closely.

Option B is the right choice in my opinion!
by nazrulq
Tue Oct 03, 2017 2:15 am
Forum: PMP® Open Forum
Topic: Sponsor : most applicable responsibility
Replies: 7
Views: 377

Re: Sponsor : most applicable responsibility

Sponsor is the person or group who provides resources and support for the project and is accountable for enabling of project success.

PMBOK Section 2.2.1 Page- 32
by nazrulq
Tue Oct 03, 2017 2:08 am
Forum: PMP® Open Forum
Topic: Communications query.
Replies: 2
Views: 190

Re: Communications query.

To include Communication Management Plan , Stakeholder Register or Stakeholder Traceability Matix to be updated.To updated.In this regard, it is necessary to generate a change request .Hence, in my opinion, is the right answer!
by nazrulq
Mon Sep 25, 2017 3:12 am
Forum: PMP® Open Forum
Topic: scordo Cost management
Replies: 5
Views: 337

Re: scordo Cost management

Thanks Manish ! Yes it is understandable but the question does not clearly mention if the estimate is not valid or the performance will be done in as per planned way or nothing changed.

If the question does n't mention anything then ETC = BAC/CPI is that right!

Thanks!
by nazrulq
Sun Sep 24, 2017 8:30 pm
Forum: PMP® Open Forum
Topic: scordo Cost management
Replies: 5
Views: 337

Re: scordo Cost management

EAC = ETC (bottom up) +AC is the best way so that ; ETC = EAC -AC, in my opinion, should be best answer! W

Which is option A!
by nazrulq
Sun Sep 24, 2017 4:25 am
Forum: PMP® Open Forum
Topic: Question regarding EV
Replies: 4
Views: 280

Re: Question regarding EV

That is totally correct! Straight forward.
by nazrulq
Sun Sep 24, 2017 4:19 am
Forum: PMP® Open Forum
Topic: PMP Exam Changes from March 26,2018
Replies: 0
Views: 174

PMP Exam Changes from March 26,2018

Hello PMP Aspirants! Just to let all of you know the PMP Exam based on PMBOK 5 will be Changed from March 26, 2018. From that day all the questions will be based on PMBOK 6. So get the test done before that day and pass! Please see below the Link: https://www.pmi.org/certifications/types/project-man...
by nazrulq
Sat Sep 23, 2017 10:21 pm
Forum: PMP® Open Forum
Topic: Workaround
Replies: 3
Views: 345

Workaround

Workaround is the negative risk for which the project is not planned for. It is managed by contingency reserve. My question all risks are in response to plan risk response ( Fallback plan, residual risk, secondary risk) but why workaround is done in control risk process why not planning as risk resp...
by nazrulq
Fri Sep 22, 2017 5:09 am
Forum: PMP® Open Forum
Topic: Getting Resource commitments.
Replies: 4
Views: 288

Re: Getting Resource commitments.

Planning Process Group in Plan HR Management.
by nazrulq
Thu Sep 21, 2017 4:20 am
Forum: PMP® Open Forum
Topic: NPV Q/A
Replies: 2
Views: 224

Re: NPV Q/A

This type of question does n't come in the real exam which require iterations. We have limited time. Should avoid that type of question. Honest Opinion!
by nazrulq
Thu Sep 21, 2017 3:55 am
Forum: PMP® Open Forum
Topic: Getting Resource commitments.
Replies: 4
Views: 288

Re: Getting Resource commitments.

In my point of view PMBOK 5 , Section 9.1.3.1 says , HR management Plan creates 1. Roles and Responsibilities 2.Project Organization Chart 3.Staffing Management Plan - Which is a component of Human Resource Management Plan describe when and how the project team will acquired and how long they will b...
by nazrulq
Thu Sep 21, 2017 3:44 am
Forum: PMP® Open Forum
Topic: PMP Maths
Replies: 1
Views: 133

Re: PMP Maths

Let me answer this question.

BAC = $100000
AC= $50000
EV = 40% of BAC= .40 x 100000 =$40000
PV = 50% of BAC = .5 x 100000 =$50000 (Actually Planned For)
Should have been done = $50000
SV= 40000/50000 =.8 < 1 Behind Schedule

Hopefully, it answers the requirement.
by nazrulq
Tue Sep 19, 2017 5:17 am
Forum: PMP® Open Forum
Topic: Mock Tech Numerical
Replies: 3
Views: 251

Re: Mock Tech Numerical

When project performance shows over budget then a new EAC should be calculated .
At that time TCPI should be

TCPI = BAC-EV/( EAC-AC) but since it is under budget then CPI <1
TCPI = BAC-EV/( BAC-AC) might be used . CPI>1

Hopefully it clarifies!
by nazrulq
Tue Sep 19, 2017 5:12 am
Forum: PMP® Open Forum
Topic: User Story
Replies: 3
Views: 224

User Story

2.The Main Purpose is to write user story is to:

A. To communicate progress of the Project

B. To document features required by stakeholders

C. To perform what if statements

D. To record issues encountered on the project.


Answer: Stakeholders requirement as option B.
by nazrulq
Sun Sep 17, 2017 6:05 pm
Forum: PMP® Open Forum
Topic: Mock Tech Numerical
Replies: 3
Views: 251

Re: Mock Tech Numerical

The question is asking for to find out To Complete Performance Index (TCPI) . If the full solution is required. Complete solution
can be provided!