Re: Project Charter Creation

hello,

I feel, The project manager has to inform to the sponsor.

As sponsor or customer, will come with unrealistic schedule and constraints.
The responsibility of project manager should show it in realistic form that cannot be achieved in given period of time.

Regards
Manhantesh
by mahanteshbhuyar
Thu Feb 09, 2017 1:41 pm
Forum: PMP® Open Forum
Topic: Question on EVM
Replies: 2
Views: 1346

Re: Question on EVM

Thank you riyadh.

Yes it's Planned value. Typo in question
by mahanteshbhuyar
Wed Feb 08, 2017 5:58 pm
Forum: PMP® Open Forum
Topic: Question on EVM
Replies: 2
Views: 1346

Question on EVM

Please find attached question.

In this, Can you please answer how the Present value (PV) calculated.

I wanted to know the number 0.375 in the answer column is calculated.