Search found 19 matches

by sapmmkamal
Sun Sep 25, 2016 6:59 pm
Forum: PMP® Queries and Tips
Topic: Diff b/w Work Authorization and Work Authorization System
Replies: 1
Views: 1464

Diff b/w Work Authorization and Work Authorization System

Hi Expert
Please elaborate difference between Work Authorization and Work Authorization System, with example
by sapmmkamal
Fri Sep 23, 2016 4:22 pm
Forum: PMP® Queries and Tips
Topic: Question on NPV
Replies: 4
Views: 2029

Question on NPV

Question 4 1.00/0.00 Hi, Please help in understanding the below question from Quampus Project -A Duration-2 Years Interest Rate-5% PV-4.54MN Future Discounted Value-40MN Project-B Duration-3 Years Interest Rate-15% PV-3.63MN Future Discounted Value-45MN Company CEO is using economic model criteria o...
by sapmmkamal
Fri Sep 23, 2016 3:49 pm
Forum: PMP® Queries and Tips
Topic: Question on Budget Estimate
Replies: 1
Views: 1277

Question on Budget Estimate

Hi Can you help how calculation happen for the correct answer Sam is half way through the planning process when his sponsor calls for a meeting to discuss progress of planning phase. Sponsor was worried about the cost estimate at the start of the project when he was provided ROM range of USD 30 Mn t...
by sapmmkamal
Fri Sep 23, 2016 3:05 pm
Forum: PMP® Queries and Tips
Topic: RITA Q in Project Management Framework
Replies: 1
Views: 1171

RITA Q in Project Management Framework

Hi I came through the below question from RITA exercise in Chapter-Project Management Framework A Project manager is trying to complete a Software development project, but cannot get enough attention for the Project. Resources are focused on completing Process related work and Project Manager has Li...
by sapmmkamal
Thu Sep 22, 2016 4:45 pm
Forum: PMP® Queries and Tips
Topic: How to differentiate Threats and Opportunities
Replies: 1
Views: 1165

How to differentiate Threats and Opportunities

Hi Experts, I am struggling to identify the whether it is a Threat or Opportunity in the give situation. Please find the below example for RITA's exercise 1. Remove the Work Package from from Project ........Why it is a Threat, not an Opportunity........ 2. Move a work package to a date when a more ...
by sapmmkamal
Mon Sep 19, 2016 5:44 pm
Forum: PMP® Queries and Tips
Topic: Work Authorization System
Replies: 1
Views: 1030

Re: Work Authorization System

Hi Tushar,
Work Authorization system is When to do the work and in which sequence
by sapmmkamal
Wed Sep 14, 2016 6:57 pm
Forum: PMP® Queries and Tips
Topic: Q19 Integration Management
Replies: 1
Views: 1452

Q19 Integration Management

Hi While going through a quiz, i came through below question, please help in clarifying the same You have been assigned as the Project Manager of a new project. You planned for a session where all stakeholders including customers and development team can be gathered and all critical explicit and imp...
by sapmmkamal
Tue Sep 13, 2016 4:59 pm
Forum: PMP® Queries and Tips
Topic: Q2 Integration Management
Replies: 1
Views: 1067

Q2 Integration Management

Hi, Please clarify the below question- One of the stakeholders of a project initiated a change request which was then documented in the change control system. In general, who usually would be responsible for approving or rejecting the change request? A. An authority within the project management tea...
by sapmmkamal
Tue Sep 13, 2016 3:55 pm
Forum: PMP® Queries and Tips
Topic: Q42 RITA-Integration management
Replies: 1
Views: 1368

Q42 RITA-Integration management

Hi, Please help in clarifying the below question from RITA All Technical work has been completed, which remains to be done- A. Validate Scope B. Plan Risk Response C. Create Staff Management Plan D. Complete Lesson Learned I think answers should be A, since no where in question it is mentioned that ...
by sapmmkamal
Tue Sep 13, 2016 3:49 pm
Forum: PMP® Queries and Tips
Topic: RITA Q17 in Integration Management
Replies: 1
Views: 942

RITA Q17 in Integration Management

Hi, I get stuck on the below question from RITA- You are taking over a project during Project Planning and discovers that 6 individuals have signed the Project Charter, which of the following should most concern you- A. Who will be member of CCB B. Spending more time in Configuration Management C. G...
by sapmmkamal
Tue Sep 13, 2016 2:55 pm
Forum: PMP® Queries and Tips
Topic: EEF and OPA of Performimg Organization
Replies: 5
Views: 1614

Re: EEF and OPA of Performimg Organization

Hi Manish, Thankx, but last query 4. While developing Project Charter, whose EEF and OPAs to be studied? ......TATA or WIPRO......I think EEF of TATA and OPAs of WIPRO Usually performing organizations but in some case you have to study of both the organization depending on how much they will influen...
by sapmmkamal
Tue Sep 13, 2016 1:59 pm
Forum: PMP® Queries and Tips
Topic: Difference between Performing and Requesting Organization
Replies: 1
Views: 1138

Difference between Performing and Requesting Organization

Hi,
While going through PMBOK-Integration management, i cam through 2 terminologies-
Performing organization
Requesting Organization

e.g. TATA Steels choose Infosys as a Vendor to Implement ERP
So in this case who is Performing Organization and who is Requesting Organization
by sapmmkamal
Tue Sep 13, 2016 1:29 pm
Forum: PMP® Queries and Tips
Topic: EEF and OPA of Performimg Organization
Replies: 5
Views: 1614

Re: EEF and OPA of Performimg Organization

Hi Manish Thankx for detailed explanation but i still have some queries considering the same example in mind, i just want to make it clear before i move forward 1. From PMP exam point of view, i should consider myself as a Part of TATA or WIPRO if something specifically is not mentioned.......I thin...
by sapmmkamal
Tue Sep 13, 2016 12:13 pm
Forum: PMP® Queries and Tips
Topic: Who provide Resource for a Project
Replies: 5
Views: 1760

Re: Who provide Resource for a Project

Hi,
Then what is the role of Project manager in resourcing
by sapmmkamal
Tue Sep 13, 2016 9:40 am
Forum: PMP® Queries and Tips
Topic: EEF and OPA of Performimg Organization
Replies: 5
Views: 1614

EEF and OPA of Performimg Organization

Hi Experts, I am confused between some Project Management terminology. e.g Case-1(External Customer)--------TATA selected WIPRO to implement ERP in their organization, so keeping this case in mind, i have below queries 1. From PMP exam point of view, i should condier myself as a Part of TATA or WIPR...
by sapmmkamal
Tue Sep 13, 2016 9:14 am
Forum: PMP® Queries and Tips
Topic: Role of Business Case in Project Charter
Replies: 1
Views: 817

Role of Business Case in Project Charter

Hi,
While going through Saket's video on Develop Project Charter, i understand that Business Case will be used if Project is Internal means no external customer is involved.
Is my opinion is correct?
by sapmmkamal
Tue Sep 13, 2016 9:06 am
Forum: PMP® Queries and Tips
Topic: Who provide Resource for a Project
Replies: 5
Views: 1760

Who provide Resource for a Project

Hi,
I came through below question in a quiz-
Who provides Resources for a Project
A. Project Manager
B. Sponsor
C. Stakeholder
D. Project Team

I my opinion, it should be Project Manager who has authority to provide the resources for a project
by sapmmkamal
Mon Sep 12, 2016 5:39 pm
Forum: PMP® Queries and Tips
Topic: Mixing of Questions in Quiz
Replies: 1
Views: 877

Mixing of Questions in Quiz

Hi, I gone through my first PMP Quiz for Project Management Framework. I found the many of the question were not related to Project management Framework instead they belong to next process group e.g. Cost Benefit Ration, Project selection methods etc. Is this intentionally done or there is some othe...
by sapmmkamal
Mon Sep 12, 2016 5:31 pm
Forum: PMP® Queries and Tips
Topic: Difference Between Phase Gate, Stage Gate, Kill Point
Replies: 1
Views: 2019

Difference Between Phase Gate, Stage Gate, Kill Point

Hi While attempting a quiz for Project management processes, i cam through a following question A commercial aircraft manufacturing organization has embarked upon a project for design of large carrier and project is divided into 7 phases, second phase is complete and Shon the sponsor wants to re-ass...

Go to advanced search