Search found 8 matches

by sriram manian
Tue Dec 20, 2016 10:09 am
Forum: PMP® Open Forum
Topic: Help to claim PDUs
Replies: 1
Views: 1232

Help to claim PDUs

Dear Ms. Seema, I am Sriram, few days back I had sent you a mail regarding claiming PDUs for PMP. Below noted is my query : I was watching webinars from Izenbridge and tried to claim PDU's in pmi.org. I inputted the date of attending the webinar after my certification date (20th July). Unfortunately...
by sriram manian
Sun Dec 18, 2016 12:50 pm
Forum: PMI-ACP® Open Forum
Topic: Help needed to Claim 30 PDU
Replies: 8
Views: 3756

Re: Help needed to Claim 30 PDU

Dear Ms. Seema, I am Sriram, few days back I had sent you a mail regarding claiming PDUs for PMP. Below noted is my query : I was watching webinars from Izenbridge and tried to claim PDU's in pmi.org. I inputted the date of attending the webinar after my certification date (20th July). Unfortunately...
by sriram manian
Tue Jul 12, 2016 4:27 am
Forum: PMP® Queries and Tips
Topic: quampus question
Replies: 5
Views: 3458

quampus question

kindly explain the attached file and Calculate ES for Activity G in the given network diagram

10

12

7

15
by sriram manian
Tue Jul 12, 2016 4:16 am
Forum: PMP® Queries and Tips
Topic: quampus question
Replies: 2
Views: 1648

quampus question

Hello All, Kindly help to resolve the below question with explanation Question 96 1.00/0.00 Sam is half way through the planning process when his sponsor calls for a meeting to discuss progress of planning phase. Sponsor was worried about the cost estimate at the start of the project when he was pro...
by sriram manian
Sun Jul 10, 2016 7:53 am
Forum: PMP® Queries and Tips
Topic: quampus question 34
Replies: 2
Views: 1866

quampus question 34

In this below noted question, how EV is arrive at $250,000. Please explain Question 34 1.00/0.00 Joe is managing a project having budget of $250,000 and it need to be completed in 10 months. At the time of completion of project, he found that 10% cost of the project is increased because of high mate...
by sriram manian
Sun Jul 10, 2016 7:17 am
Forum: PMP® Queries and Tips
Topic: quampus question 14
Replies: 1
Views: 1496

quampus question 14

Below noted is the question from quampus. Kindly explain how we got 20 while calculating and 15 while calculating AC, if it is half then it should be 10 Question 14 1.00/0.00 In your project, a task was scheduled to use two trained resources for two full weeks to complete. But because of other urgen...
by sriram manian
Sun May 08, 2016 4:01 pm
Forum: PMP® Open Forum
Topic: check your Knowledge - Good one
Replies: 7
Views: 3081

Re: check your Knowledge - Good one

Thank you, which means we are expressing the contingency reserve in positive manner for a negative impact.
by sriram manian
Tue Apr 12, 2016 6:55 am
Forum: PMP® Open Forum
Topic: check your Knowledge - Good one
Replies: 7
Views: 3081

Re: check your Knowledge - Good one

Dear all,

I am new to this group. why the option is not A. when you sum up everything the answer is -11600. Please explain.