A Practical Scenario - Suppose one of the material on the critical path is delayed for 1 month with reference to its schedule (activity will start after 1 month) which was not identified previously so its a unknown unknown risk but . do we still add in the risk register and will analysis as still th...
by sunildubai15
Sun Jan 10, 2016 8:04 am
Forum: PMP® Exam Lessons – Success Stories
Topic: Cleared PMP
Replies: 10
Views: 4168

Re: Cleared PMP

Congrs Arjun

Bravo, Now party time
i knew you will clear it, you desperation showed that
best of luck

Sunil
by sunildubai15
Thu Jan 07, 2016 5:33 am
Forum: PMP® Queries and Tips
Topic: saket urgent attention 1 hour to go
Replies: 4
Views: 1402

Re: saket urgent attention 1 hour to go

Yeah, in the options 1. inform sponsor 2. wait as it is not officially announced last two options i didn't remember may be add to risk another weird question what documents is required before administrative closure meeting (this question came to be 2nd time :oops: ) options including LL, contract ch...
by sunildubai15
Thu Jan 07, 2016 5:17 am
Forum: PMP® Queries and Tips
Topic: saket urgent attention 1 hour to go
Replies: 4
Views: 1402

Re: saket urgent attention 1 hour to go

But Saket in question there was no further information, very difficult to answer such questions.
by sunildubai15
Thu Jan 07, 2016 5:04 am
Forum: PMP® Queries and Tips
Topic: Validate scope
Replies: 2
Views: 1314

Re: Validate scope

what is the purpose of validate scope - to get customer acceptance of verified deliverable (output from CQ)
scope statement and scope baseline is planned deliverable
by sunildubai15
Thu Jan 07, 2016 5:01 am
Forum: PMP® Queries and Tips
Topic: Bell curve
Replies: 2
Views: 1164

Re: Bell curve

http://www.dummies.com/how-to/content/b ... certi.html
also check saket video on i vaguely remember - estimate cost where he explained about 3 point estimation he mentioned about bell curve
by sunildubai15
Wed Jan 06, 2016 1:34 pm
Forum: PMP® Open Forum
Topic: Regarding ethics question
Replies: 2
Views: 1245

Re: Regarding ethics question

Me too didn't get any ethic question.
only one question which was having slight ethic test
by sunildubai15
Wed Jan 06, 2016 7:26 am
Forum: PMP® Exam Lessons – Success Stories
Topic: Passed PMP Exam (Dubai) Today 05-01-2016
Replies: 13
Views: 3600

Re: Passed PMP Exam (Dubai) Today 05-01-2016

My apologize. I thought the same but somehow my intention to help my friends (even i don't know anybody personally) overcome ethics My only intention to disclose few question here to make the other understand the questions coming in the exam are from the live scenario so that they would be better pr...
by sunildubai15
Wed Jan 06, 2016 6:29 am
Forum: PMP® Exam Lessons – Success Stories
Topic: Passed PMP Exam (Dubai) Today 05-01-2016
Replies: 13
Views: 3600

Re: Passed PMP Exam (Dubai) Today 05-01-2016

Hello, Sunil Sharma,PMP, Congratulations my friend. Yes, you really worked hard and now it's party time! Thanks for sharing your LL All the best. Hope to connect with you in Dubai sometimes in March. Best regards, Mahfuz Thanks Mahfuz and you pleasant to have PMP in from of your name. but only litt...
by sunildubai15
Wed Jan 06, 2016 6:27 am
Forum: PMP® Open Forum
Topic: Regarding exam preparation
Replies: 3
Views: 1493

Re: Regarding exam preparation

1) is it ok to have all practice from quampus for exam? Saket : I recommend at least going through 3 exam questions sources , us (quampus) , Rita Book and Cristopher Scordo , each writer has different style and way to take questions just following one source for questions may not expose you for man...
by sunildubai15
Wed Jan 06, 2016 6:21 am
Forum: PMP® Exam Lessons – Success Stories
Topic: Passed PMP Exam (Dubai) Today 05-01-2016
Replies: 13
Views: 3600

Re: Passed PMP Exam (Dubai) Today 05-01-2016

Thanks Sunil. By change control I think you mean by perform ICC process. Do you know the answer of communication channel question? Can I borrow yr brain for 4 hrs this weekend :) better borrow Mahfuz or Ujjal Brain, best is saket :D If you dont mind can you share yr email id. sunilsharma.dubai@gmai...
by sunildubai15
Wed Jan 06, 2016 2:48 am
Forum: PMP® Exam Lessons – Success Stories
Topic: Passed PMP Exam (Jan 03) Edmonton, Canada
Replies: 19
Views: 5847

Re: Passed PMP Exam (Jan 03) Edmonton, Canada

Congratulation and great effort
I can understand when you are attempting 2nd attempt (kind of pressure on you)
Now its party time

Best Regards
Sunil
by sunildubai15
Wed Jan 06, 2016 2:42 am
Forum: PMP® Exam Lessons – Success Stories
Topic: Passed PMP Exam (Dubai) Today 05-01-2016
Replies: 13
Views: 3600

Re: Passed PMP Exam (Dubai) Today 05-01-2016

First of all Thanks you all for your kind wishes Now on Arjun Query There were around 7-8 question came on HR but not so difficult communication channel question now a days coming quite tricky 4 member including PM, out of which one member said will do part-time and another member also joined part-t...
by sunildubai15
Tue Jan 05, 2016 3:36 pm
Forum: PMP® Exam Lessons – Success Stories
Topic: Passed PMP Exam (Dubai) Today 05-01-2016
Replies: 13
Views: 3600

Passed PMP Exam (Dubai) Today 05-01-2016

At last I have passed pmp in 2nd attempt but on border line :D . My Journey was being quite long, started in May 2014 with attending a training course for 35 PDU and had my first attempt in Sep, 2014 but couldn't cleared and left with little margin. my actual journey started after coming across Sake...
by sunildubai15
Tue Jan 05, 2016 7:02 am
Forum: PMP® Queries and Tips
Topic: saket urgent attention 1 hour to go
Replies: 4
Views: 1402

saket urgent attention 1 hour to go

if client has published in blog or media that they are going to close the project, what should PM do
shall he update sponser or customer
or wait as it is not officially announced
by sunildubai15
Mon Jan 04, 2016 3:05 pm
Forum: PMP® Queries and Tips
Topic: Question appear in exam - urgent anser
Replies: 1
Views: 1237

Question appear in exam - urgent anser

IF change get approved, what it update first
Project Management plan or schedule baseline
by sunildubai15
Mon Jan 04, 2016 7:34 am
Forum: PMP® Queries and Tips
Topic: Q-simplilearn
Replies: 5
Views: 2256

Re: Q-simplilearn

Thanks Saket
this rule of elimination is very useful and helpful
by sunildubai15
Mon Jan 04, 2016 7:30 am
Forum: PMP® Open Forum
Topic: doubt regarding EVM
Replies: 4
Views: 1982

Re: doubt regarding EVM

Ans 1
behind and ahead is term for schedule
kindly post the complete question for question 2
by sunildubai15
Mon Jan 04, 2016 7:29 am
Forum: PMP® Open Forum
Topic: Help testing in 10 hrs
Replies: 3
Views: 1689

Re: Help testing in 10 hrs

when in the question they have mentioned that variation was recovered and rest of the project will go as per budget, s it is a typical case however as Mahfuz mentioned in the question mentioned about schedule and cost variation.
by sunildubai15
Sun Jan 03, 2016 6:25 pm
Forum: PMP® Queries and Tips
Topic: Q-Simplilearn
Replies: 6
Views: 2611

Re: Q-Simplilearn

Thanks a lot Saket
by sunildubai15
Sun Jan 03, 2016 5:20 pm
Forum: PMP® Open Forum
Topic: Calculate communication channel
Replies: 10
Views: 4182

Re: Calculate communication channel

I got confused with the statement 3 different location with lead. I thought communication will be between PM and lead
by sunildubai15
Sun Jan 03, 2016 12:51 pm
Forum: PMP® Queries and Tips
Topic: Q-Simplilearn wrong answer
Replies: 3
Views: 1208

Re: Q-Simplilearn wrong answer

So in this question there are 2 answers swot and monte carlo isn't?
by sunildubai15
Sun Jan 03, 2016 8:29 am
Forum: PMP® Queries and Tips
Topic: Q-Simplilearn wrong answer
Replies: 3
Views: 1208

Q-Simplilearn wrong answer

Which of the following is NOT a tool used in the perform qualitative risk analysis process?

Probability and Impact Matrix
SWOT (Strength, Weakness, Opportunities and Threat)
Monte Carlo Simulation
Root cause identification
by sunildubai15
Sun Jan 03, 2016 7:45 am
Forum: PMP® Queries and Tips
Topic: Q- Simplilearn
Replies: 4
Views: 2035

Q- Simplilearn

Your project is in the final stages of testing and the team is interacting with the customer on daily basis to update him with the project status and incorporate his feedback. Which of the following would be the most critical process to be followed in this scenario? Control Quality Control Scope Man...
by sunildubai15
Sun Jan 03, 2016 7:39 am
Forum: PMP® Queries and Tips
Topic: Q- Close group
Replies: 2
Views: 1757

Q- Close group

project manager is in the final closure phase of the project . Which of the following should he do FIRST as part of the project closure activity? Get formal sign off from the customer to confirm customer acceptance of final deliverable Measure customer satisfaction as a key performance indicator of ...
by sunildubai15
Sun Jan 03, 2016 7:12 am
Forum: PMP® Queries and Tips
Topic: Q-simplilearn
Replies: 5
Views: 2256

Q-simplilearn

Harry has been assigned the flyover construction project and he is in the process of initiating the project. In order to meet the customer's project expectations, based on the business and compliance requirements, which of the following should Harry define FIRST? High level scope of the project Proj...
by sunildubai15
Sun Jan 03, 2016 7:06 am
Forum: PMP® Open Forum
Topic: Calculate communication channel
Replies: 10
Views: 4182

Calculate communication channel

You are managing a project with project teams in different geographical locations. There are approximately 25 team members in 3 different locations each being lead by a team lead. Additionally, there are 3 members from a supporting group that are working part- time on the project. How many communica...
by sunildubai15
Sun Jan 03, 2016 7:04 am
Forum: PMP® Queries and Tips
Topic: Q-Simplilearn
Replies: 6
Views: 2611

Q-Simplilearn

Which one of the following is the last step of project closing? Archive Project Documents Measure customer satisfaction at the end of the project Client appreciates your product Lessons learnt are documented I answerd A but answer is saying B why? please explain he right answer is B. All of the stat...
by sunildubai15
Sat Jan 02, 2016 10:08 am
Forum: PMP® Open Forum
Topic: Free Float on Converging activities
Replies: 8
Views: 3002

Re: Free Float on Converging activities

cos the ES of B>E
by sunildubai15
Sat Jan 02, 2016 5:46 am
Forum: PMP® Open Forum
Topic: Q - Scordo
Replies: 10
Views: 3685

Re: Q - Scordo

Are you talking about free exam PMstudy and simpli learn
by sunildubai15
Sat Jan 02, 2016 5:43 am
Forum: PMP® Open Forum
Topic: Free Float on Converging activities
Replies: 8
Views: 3002

Re: Free Float on Converging activities

a=0
d=5
g=2
free float=ES of successor-ES of Predecessor-Duration
by sunildubai15
Fri Jan 01, 2016 1:26 pm
Forum: PMP® Open Forum
Topic: Q - Scordo
Replies: 10
Views: 3685

Re: Q - Scordo

Thanks Mahfuz. My exam is on Jan 5th.
tell me I am scoring above 80% in all izen test. am I able to clear pmp
by sunildubai15
Fri Jan 01, 2016 1:23 pm
Forum: PMP® Queries and Tips
Topic: sample test questions
Replies: 1
Views: 971

Re: sample test questions

Goto assessment tab, u will get ample questions
by sunildubai15
Fri Jan 01, 2016 5:17 am
Forum: PMP® Open Forum
Topic: Activity Duration Question
Replies: 2
Views: 1105

Re: Activity Duration Question

Sometime back saket explained this LS : Late Start Date LF : Late Finish Date= LS + duration -1 (start one) ES : Early Start Date EF : Early Finish Date : ES+Duration -1 (start one) Slack / float= LF-EF or LS - ES Duration = LF-LS +1 or EF-ES+1 (i am taking start with one calculation , not zero star...
by sunildubai15
Thu Dec 31, 2015 4:10 am
Forum: PMP® Open Forum
Topic: 2 Answers in Quampus Question
Replies: 3
Views: 1046

Re: 2 Answers in Quampus Question

Correct also not every change request goes to CCB - that is also not true. some changes could be manage on PM level
by sunildubai15
Wed Dec 30, 2015 8:45 am
Forum: PMP® Open Forum
Topic: 2 Answers in Quampus Question
Replies: 3
Views: 1046

2 Answers in Quampus Question

Which of the following is NOT true regarding change requests? Change requests should be managed in controlled fashion For every change request, follow change control system define for your project - is it correct answer? Change requests are sign of bad project planning Change requests can lead to sc...
by sunildubai15
Wed Dec 30, 2015 6:45 am
Forum: PMP® Open Forum
Topic: Q - Scordo
Replies: 10
Views: 3685

Re: Q - Scordo

Congrs
kindly reply on my risk queries, still waiting for answer
by sunildubai15
Wed Dec 30, 2015 4:54 am
Forum: PMP® Queries and Tips
Topic: Clarification On Direct and Manage Project work process
Replies: 6
Views: 4011

Re: Clarification On Direct and Manage Project work process

sunildubai15 wrote:No, i am telling you on the behalf of few question i attempted

competitors are consider as stakeholder
by sunildubai15
Wed Dec 30, 2015 4:47 am
Forum: PMP® Exam Lessons – Success Stories
Topic: Cleared PMP on Dec 28,2015 in Edmonton,AB Canada
Replies: 19
Views: 6193

Re: Cleared PMP on Dec 28,2015 in Edmonton,AB Canada

Tons of Congrs Mahfuz and thanks for sharing your knowledge in the forum and helping others last 10 days i have only practiced on izen question bank (30 and 50 questions) and manage to score 80+ and since last 3 days attempting scordo starting from 14 so 14 - 38/50 15 - 44/50 16 - 43/50 i want to un...
by sunildubai15
Tue Dec 29, 2015 4:24 pm
Forum: PMP® Open Forum
Topic: Q - Scordo
Replies: 10
Views: 3685

Re: Q - Scordo

Hi Shalini
My exam is next week. can you give me ideas how many questions you got on risk, quality, evm, procurement and hr
by sunildubai15
Tue Dec 29, 2015 4:18 am
Forum: PMP® Queries and Tips
Topic: Clarification On Direct and Manage Project work process
Replies: 6
Views: 4011

Re: Clarification On Direct and Manage Project work process

No, i am telling you on the behalf of few question i attempted
by sunildubai15
Mon Dec 28, 2015 5:52 pm
Forum: PMP® Open Forum
Topic: Risk Queries
Replies: 9
Views: 3112

Re: Risk Queries - urgent attention

Dear Manish I have two main queries based on scenario 1. Say risk occur however the impact is more/ less than anticipated then what we will do (execution perspective) 2. while doing risk response if we realize that the impact is more or less then what we do (planning perspective) 3. Can secondary ri...
by sunildubai15
Mon Dec 28, 2015 1:19 pm
Forum: PMP® Open Forum
Topic: Q - Scordo
Replies: 10
Views: 3685

Q - Scordo

You are managing a project with a large multi-national staff. One of the engineers was originally tasked to deliver her part of the work on Oct 19, but due to the change in the critical path, her deliverable will be needed 2 days sooner. However, as the new deadline is still 2 weeks away and she is ...
by sunildubai15
Mon Dec 28, 2015 9:21 am
Forum: PMP® Open Forum
Topic: Preventive Vs Corrective.
Replies: 11
Views: 4415

Re: Preventive Vs Corrective.

PMBOK Page NO 413 having different defination for corrective action

"Recommended action include changes that bring the future performance of the project in line with the project management plan
by sunildubai15
Mon Dec 28, 2015 6:17 am
Forum: PMP® Queries and Tips
Topic: Clarification On Direct and Manage Project work process
Replies: 6
Views: 4011

Re: Clarification On Direct and Manage Project work process

i would recommend watch saket video on control risk. he has cleared the complete process. manage risk in D&MPW means to implement what so ever risk response stretagy you have choosed for the identified high priority risk. another view point is when you in execution, new risk could appear. what a...
by sunildubai15
Mon Dec 28, 2015 5:34 am
Forum: PMP® Open Forum
Topic: Doubt regarding "ADJOURNING"
Replies: 2
Views: 1443

Re: Doubt regarding "ADJOURNING"

Not necessary.sometime if there is urgent requirement, an architect could join the project from HO and finish his requirement and could released. or say for example if one site staff is going for vacation for 1 month and will be replaced by another one.
by sunildubai15
Sun Dec 27, 2015 12:33 pm
Forum: PMP® Open Forum
Topic: Risk Queries
Replies: 9
Views: 3112

Re: Risk Queries

can you send me some reference link from forum, if possible
by sunildubai15
Sun Dec 27, 2015 12:32 pm
Forum: PMP® Open Forum
Topic: procurement management
Replies: 7
Views: 2406

Re: procurement management

the main keyword is "make use of " it means weighting criteria are mentioned in proposal evaluation technique but it could be used with source selection criteria