Search found 4 matches

by gauto988
Tue Aug 18, 2015 4:58 pm
Forum: Oliver 75 PMP Questions
Topic: Oliver 75 - 23rd Question
Replies: 9
Views: 7345

Re: Contract related Question

The contractor‘s indirect costs will increase and the customer‘s payment for them will increase.
by gauto988
Tue Aug 18, 2015 7:27 am
Forum: PMP® Open Forum
Topic: Critical Path Question by nazish
Replies: 4
Views: 1754

Re: Critical Path Question by nazish

1. You have to draw PERT chart base on question chart table. 2. You have to calculate ES, LS, EF, LF of every activity on chart 3. There are 3 types of Float: Total Float : time of an activity can be delay without delaying the project. It's can be called "Float" Total Float = LS - ES = LF ...
by gauto988
Tue Aug 18, 2015 7:10 am
Forum: PMP® Open Forum
Topic: please help.....Network Diagram questions,
Replies: 2
Views: 1544

Re: please help.....Network Diagram questions,

Because activity D is not in Critical Path and has smallest duration
by gauto988
Mon Aug 17, 2015 7:42 am
Forum: PMP® Open Forum
Topic: PERT
Replies: 8
Views: 3507

Re: PERT

I my opinion: I think the PERT distribution is used when the Most Likely estimation is provided by the person who is responsible for that activity in the future. Since that person knows exactly how can he complete that activity in the future, his estimation will be weighted. ex: The worker estimates...