Search found 49 matches

by SRIMENON9
Thu Jul 09, 2015 6:30 am
Forum: PMP® Open Forum
Topic: CCR queries
Replies: 1
Views: 949

CCR queries

Hi, Below are a few queries i have wrt maintaining PDU's. Kindly help. I have already watched Saket's Video on youtube How many PDU's can one earn by reading a single book or a single video ( Category C under Self Directed). I know we can earn upto 30 PDUs here Also, i hear there is going to be a ch...
by SRIMENON9
Thu Jul 09, 2015 6:20 am
Forum: PMP® Exam Lessons – Success Stories
Topic: Phew - Thanks
Replies: 7
Views: 3719

Re: Phew - Thanks

Thanks Celina and Abhimanyu All, Below is my post on Linkedin which includes lessons learnt. Apologies for the long explanation! Hi All, Glad to inform you that I passed the PMP exam on 2nd JuIy. I take this opportunity to thank all those who have helped and/or motivated me. Oliver – Thank you for t...
by SRIMENON9
Thu Jul 02, 2015 11:56 am
Forum: PMP® Exam Lessons – Success Stories
Topic: Phew - Thanks
Replies: 7
Views: 3719

Re: Phew - Thanks

Will Do
by SRIMENON9
Thu Jul 02, 2015 10:22 am
Forum: PMP® Exam Lessons – Success Stories
Topic: Phew - Thanks
Replies: 7
Views: 3719

Phew - Thanks

Hi All,

I cleared by exam today and am now a certified PMP :)

Saket,

Thank you for letting me into this forum and my regards to the rest for assisting me as and when. To name a few, Manish, Pankaj, CoolPMP, AM1969 etc

I will provide a detailed review on Linkedin

SriMenon
by SRIMENON9
Sun Jun 28, 2015 11:52 am
Forum: PMP® Open Forum
Topic: Reducing cost
Replies: 3
Views: 1687

Re: Reducing cost

I thought so too but Rita believes otherwise. What could be the reason?

She says- Direct costs are directly attributable to the project and variable costs are costs that vary with amount of work accomplished. it is best to look at decreasing these costs!!!
by SRIMENON9
Sun Jun 28, 2015 11:49 am
Forum: PMP® Open Forum
Topic: EVM question
Replies: 4
Views: 1910

Re: EVM question

Thanks Manish. How did you arrive at that?

I got confused and thought " Planning control" as we use EVM whilst controlling scope and schedule

What did i do wrong?
by SRIMENON9
Sun Jun 28, 2015 9:03 am
Forum: PMP® Open Forum
Topic: Reducing cost
Replies: 3
Views: 1687

Reducing cost

A PM needs to analyze cost to find ways to decrease it. It would be best if PM looks at

Variable and fixed costs
fixed and indirect costs
Direct and variable costs
Indirect and direct costs
by SRIMENON9
Sun Jun 28, 2015 9:01 am
Forum: PMP® Open Forum
Topic: EVM question
Replies: 4
Views: 1910

EVM question

Earned Value Measurement is an example of

Performance reporting
planning control
Ishikawa diagrams
Integrating project components into whole?
by SRIMENON9
Sun Jun 28, 2015 5:19 am
Forum: PMP® Open Forum
Topic: Another query
Replies: 10
Views: 4335

Re: Another query

My sentiments precisely. Thanks again
by SRIMENON9
Sat Jun 27, 2015 5:04 pm
Forum: PMP® Open Forum
Topic: Another query
Replies: 10
Views: 4335

Re: Another query

Thanks Manish

In real life though, if i spoke to my team, i would perhaps get some pointers and be prepared before i speak to client. Having said that i understand your answer. Thanks
by SRIMENON9
Sat Jun 27, 2015 9:47 am
Forum: PMP® Open Forum
Topic: Another query
Replies: 10
Views: 4335

Re: Another query

Again , i answered like you but Rita says otherwise!!

First find out why the customer is not happy and then meet with team and determine options
by SRIMENON9
Sat Jun 27, 2015 9:44 am
Forum: PMP® Open Forum
Topic: query
Replies: 3
Views: 1368

Re: query

I answered the same but below is the answer from Rita M!!!! Answer D Did you pick validate scope?Then you may have forgotten that validate scope process is done during Monitoring and controlling, not project closing.planning risk responses and creating staff management plan are done earlier in the p...
by SRIMENON9
Fri Jun 26, 2015 3:25 pm
Forum: PMP® Open Forum
Topic: Another query
Replies: 10
Views: 4335

Another query

You are assigned as the PM in the middle of a project.The project is within baselines but the customer is not happy with the performance of the project. What is the first thing you should do?

Discuss it with Project team
Recalculate baselines
Renegotiate contract
Meet with customer

Pls help answer
by SRIMENON9
Fri Jun 26, 2015 3:23 pm
Forum: PMP® Open Forum
Topic: query
Replies: 3
Views: 1368

query

All technical work is completed on the project. which of the following remains to be done?

Validate Scope
Plan risk responses
Create Staffing management plan
Complete lessons learnt

Pls help answer this
by SRIMENON9
Mon Jun 22, 2015 11:52 am
Forum: PMP® Open Forum
Topic: Question - Tool and Technique
Replies: 9
Views: 3073

Re: Question - Tool and Technique

It does now, thank you
by SRIMENON9
Sun Jun 21, 2015 7:50 pm
Forum: PMP® Open Forum
Topic: Question - Tool and Technique
Replies: 9
Views: 3073

Re: Question - Tool and Technique

Thanks AM1969 but i disagree with this. Would have been great to talk but since this forum does not allow that, i will let this rest
by SRIMENON9
Sun Jun 21, 2015 5:11 pm
Forum: PMP® Open Forum
Topic: ETC query
Replies: 2
Views: 1447

Re: ETC query

Thank You. This clarifies
by SRIMENON9
Sun Jun 21, 2015 2:53 pm
Forum: PMP® Open Forum
Topic: Question - Tool and Technique
Replies: 9
Views: 3073

Re: Question - Tool and Technique

Request a re-assessment of your answer Take another example on Scordo You are presented with a situation in a project where you need to measure the performance of the project. Which of these techniques would suit your requirement? Learned Value Technique Earned Value Technique Analogous Estimating E...
by SRIMENON9
Sun Jun 21, 2015 2:46 pm
Forum: PMP® Open Forum
Topic: Ethics query
Replies: 7
Views: 3080

Re: Ethics query

Follow up question by comparing another ethics query You are managing a medium sized construction project, and are reviewing some invoices from the electrical contractor. You see that materials not required for your project have been included on the invoice. After making a few phone calls it becomes...
by SRIMENON9
Sun Jun 21, 2015 2:34 pm
Forum: PMP® Open Forum
Topic: ETC query
Replies: 2
Views: 1447

ETC query

A project was estimated to cost $ 200,000 with a timeline of 10 months. Due to a shipment delay, the schedule was slightly delayed. This was however made up by receiving the first batch of materials for the project by air. The net result was that there was some additional cost in the project. At the...
by SRIMENON9
Sun Jun 21, 2015 1:34 pm
Forum: PMP® Open Forum
Topic: Int Change Control
Replies: 4
Views: 1678

Re: Int Change Control

Thanks
by SRIMENON9
Sat Jun 20, 2015 5:38 pm
Forum: PMP® Open Forum
Topic: Int Change Control
Replies: 4
Views: 1678

Int Change Control

You are beginning a new project. When should you use the Perform Integrated Change Control process? I believe the answer should be D but Scordo says A? Where is the question of Change control until scope is defined?? Throughout the entire project Only when closing out the project Only after the proj...
by SRIMENON9
Wed Jun 17, 2015 9:40 am
Forum: PMP® Open Forum
Topic: Ethics query
Replies: 7
Views: 3080

Re: Ethics query

More than helpful . Thanks :)
by SRIMENON9
Wed Jun 17, 2015 4:57 am
Forum: PMP® Open Forum
Topic: Ethics query
Replies: 7
Views: 3080

Re: Ethics query

Sure thanks
by SRIMENON9
Tue Jun 16, 2015 7:06 pm
Forum: PMP® Open Forum
Topic: Ethics query
Replies: 7
Views: 3080

Ethics query

1.) You are managing a multi-million dollar project, and discover several critical pieces of data in the project information repository have been modified without authorization. What should you do? Determine the extent of the data breach, and implement security procedures to prevent a recurrence. De...
by SRIMENON9
Tue Jun 16, 2015 4:46 pm
Forum: PMP® Open Forum
Topic: Question
Replies: 3
Views: 1509

Re: Question

Thanks. No further questions on this one
by SRIMENON9
Tue Jun 16, 2015 4:32 pm
Forum: PMP® Open Forum
Topic: Question - Tool and Technique
Replies: 9
Views: 3073

Re: Question - Tool and Technique

Thanks Both. Your Answer is correct as per Scordo. My question is this. Analytical techniques is a tool and technique under "Monitor and Control Project Work" and under this, we have forecasting, EVM etc.... Hence can i not chose " Earned Value technique"? or is this wrong becaus...
by SRIMENON9
Tue Jun 16, 2015 2:07 pm
Forum: PMP® Open Forum
Topic: Question
Replies: 3
Views: 1509

Question

Another one that i need help on. I will put forth my query once i get an answer. Mary is currently focusing on controlling the key stakeholder engagement on her project. The project management plan is an essential input to this process. Which of the following components of the project management pla...
by SRIMENON9
Tue Jun 16, 2015 2:04 pm
Forum: PMP® Open Forum
Topic: Question - Tool and Technique
Replies: 9
Views: 3073

Question - Tool and Technique

Can someone answer this for me pls?

Which of the following is a tool or technique used in the Monitor and Control Project Work process?

Expert judgment

Rejected change requests

Earned value technique

Change control tools
by SRIMENON9
Sat Jun 13, 2015 11:29 am
Forum: PMP® Exam Lessons – Success Stories
Topic: Shukriya :)
Replies: 11
Views: 4497

Re: Shukriya :)

Congrats
by SRIMENON9
Wed Jun 10, 2015 3:24 am
Forum: PMP® Open Forum
Topic: Quampus Q - Beta distribution
Replies: 5
Views: 1787

Re: Quampus Q - Beta distribution

Thanks
by SRIMENON9
Tue Jun 09, 2015 6:38 pm
Forum: PMP® Open Forum
Topic: Rita M - Procurement Mgmt - EMV
Replies: 4
Views: 2030

Re: Rita M - Procurement Mgmt - EMV

Perfect.Thanks
by SRIMENON9
Tue Jun 09, 2015 3:02 pm
Forum: PMP® Open Forum
Topic: Quampus Q - Beta distribution
Replies: 5
Views: 1787

Re: Quampus Q - Beta distribution

I know but where is the budget estimate numbers given in PMBOK 5. As mentioned earlier, i picked it up from CF's blog. Thanks
by SRIMENON9
Tue Jun 09, 2015 2:59 pm
Forum: PMP® Open Forum
Topic: Quampus Q
Replies: 3
Views: 1753

Re: Quampus Q

Got it, thanks
by SRIMENON9
Tue Jun 09, 2015 2:53 pm
Forum: PMP® Open Forum
Topic: Rita M - Procurement Mgmt - EMV
Replies: 4
Views: 2030

Re: Rita M - Procurement Mgmt - EMV

Celina - Can you share the question as well pls for my understanding. I cant see it
by SRIMENON9
Sun Jun 07, 2015 8:36 am
Forum: PMP® Open Forum
Topic: Quampus Q
Replies: 3
Views: 1753

Re: Quampus Q

Agree with you on this one Celina. No clue
by SRIMENON9
Sun Jun 07, 2015 8:29 am
Forum: PMP® Open Forum
Topic: Quampus Q - Beta distribution
Replies: 5
Views: 1787

Re: Quampus Q - Beta distribution

Hi Celina, I think the question is trying to trick us. It only says " in most probability you will be using the services of Vendor A" but does not indicate that this is the most likely cost. ( Might be when we look at one of the cheaper options as the best) Getting back to the calculation ...
by SRIMENON9
Fri Jun 05, 2015 4:14 am
Forum: PMP® Open Forum
Topic: scope management
Replies: 2
Views: 1075

Re: scope management

There is no right order to this and you will not be asked in the exam on what comes first. Ideally , you will control scope and then validate scope, but there can also be times when you are Verifying/validating scope and you have to control it. Works both ways.
by SRIMENON9
Wed Jun 03, 2015 1:32 pm
Forum: PMP® Open Forum
Topic: Quality Management
Replies: 1
Views: 863

Quality Management

Hi Folks, Need some help in understanding " Project Quality Management" This is the process of identifying quality requirements and standards of the project and its deliverables....how project will demonstrate compliance etc...Basically, how quality will be managed and controlled. Other pr...
by SRIMENON9
Mon Jun 01, 2015 7:50 am
Forum: PMP® Open Forum
Topic: Andy Crowe's Q
Replies: 1
Views: 1559

Re: Andy Crowe's Q

Hi Celina, This is quite a confusing one. Here's my take on it A & B is not a definition of free float and total float as per me Lets take an example. The latest the activity can finish without delaying the project. IN this case, the latest an activity can finish would be on a particular day ( s...
by SRIMENON9
Sun May 31, 2015 1:33 am
Forum: PMP® Open Forum
Topic: Communication Mgmt - Q
Replies: 9
Views: 2758

Re: Communication Mgmt - Q

Like Jyothi mentioned, pls factorize number. 6 *5 = 30 and is the only multiples that can give you -n
-6n+5n= -n

The other options don't help. For example; 2*15... 3*10......
by SRIMENON9
Thu May 28, 2015 6:40 am
Forum: PMP® Open Forum
Topic: Difference between Composite and Matrix Organization
Replies: 6
Views: 3350

Re: Difference between Composite and Matrix Organization

Dear Raji, in this case, answer is straight forward and a clear description of a composite organization. Question clearly states that this is fundamentally a functional organization and a special project team has been created...... Bottom line, this Project team has set up in a "functional"...
by SRIMENON9
Thu May 28, 2015 5:49 am
Forum: PMP® Open Forum
Topic: Communication Mgmt - Q
Replies: 9
Views: 2758

Re: Communication Mgmt - Q

n2-n=30
n2-6n+5n=30
n2-6n+5n-30=0
n(n-6)+5(n-6)=0
(n+5)*(n-6)=0
n= -5 or n = 6

Since we cant have -5 its 6

Hence answer is 10+5+6 = 21
by SRIMENON9
Thu May 28, 2015 5:09 am
Forum: PMP® Open Forum
Topic: Scordo Q - Stakeholder Mgmt
Replies: 3
Views: 2215

Re: Scordo Q - Stakeholder Mgmt

Hi Celina, Where is this question from? I agree with your perspective. Infact, if we look at Manage Stakeholders Output, "Issue Log" is one of the them. I dont see any reason why the chances of updating Risk Register would be higher and hence that would seem a more likely answer. It is pos...
by SRIMENON9
Wed May 27, 2015 7:33 am
Forum: PMP® Open Forum
Topic: Float query
Replies: 7
Views: 2288

Re: Float query

Thanks Saket. Really appreciate your note. I will contribute going forth Getting back to the query, i first saw this question on Head First PMP and then when i started reading PMBOK in detail Ref - PMBOK page 177 ( 6.6.2.2) - Explanation of critical path Honestly i am unable to comprehend it at all,...
by SRIMENON9
Tue May 26, 2015 12:59 pm
Forum: PMP® Open Forum
Topic: Float query
Replies: 7
Views: 2288

Re: Float query

Unfortunately I have not taken any course from you yet but happy to post completing my pmp certification.Was hoping for some other options.Thanks anyways
by SRIMENON9
Tue May 26, 2015 10:26 am
Forum: PMP® Open Forum
Topic: Critical Path versus Critical Chain
Replies: 1
Views: 958

Critical Path versus Critical Chain

Whilst i understand critical path and chain from a theoretical perspective, i have a query on its practical use. Is Critical Chain not a more realistic way to work on a project? As i understand it, critical path does not look at resource availability and is looking at developing an optimal schedule....
by SRIMENON9
Tue May 26, 2015 10:17 am
Forum: PMP® Open Forum
Topic: Float query
Replies: 7
Views: 2288

Re: Float query

Sure thanks. Happy to be part of a clarification session but how do i take part in one of those and when is this scheduled?
by SRIMENON9
Mon May 25, 2015 6:04 pm
Forum: PMP® Open Forum
Topic: Float query
Replies: 7
Views: 2288

Float query

Can anyone explain this to me pls? A positive Total Float is caused when a backward pass is calculated from Schedule constraint that is later than early finish date that has been calculated during forward pass calculation.Negative Total float is caused when a constraint on the late dates is violated...