Search found 59 matches

by kniraj
Sat Jan 24, 2015 5:21 am
Forum: PMP® Open Forum
Topic: Funding Limit reconciliation
Replies: 4
Views: 3757

Re: Funding Limit reconciliation

My understanding ... It is like looking at the funding constraints of the project. Our cash flow may not be consistent throughout out the duration of the project and hence the spend needs to planned accordingly. For ex - in the first month the cash flow is only $x and project cannot spend more than ...
by kniraj
Wed Jan 21, 2015 3:44 am
Forum: PMP® Open Forum
Topic: PMP exam
Replies: 12
Views: 1786

Re: PMP exam

In general you will include the PM for the calculation of the communication channels. But again as mentioned in the above posts ... you need to read the question very carefully and then take that call. I got a few extremely tricky questions on communication channel calculation in the exam. So read a...
by kniraj
Mon Jan 19, 2015 4:10 am
Forum: PMP® Open Forum
Topic: Perk reward System
Replies: 1
Views: 405

Re: Perk reward System

Eric,
It would be formal process to identify the criteria for rewards and what those rewards would be.

I guess could include the policy as well as the actual system within the HR purview for managing the rewards. Hope that helps.
by kniraj
Mon Jan 19, 2015 4:07 am
Forum: PMP® Open Forum
Topic: Question for Discussion:Identify Req
Replies: 7
Views: 880

Re: Question for Discussion:Identify Req

You can also refer to the Pg 116 Section 5.2.2.7 where 'participant observer' and how it helps to get the hidden requirements out is mentioned.
by kniraj
Mon Jan 19, 2015 4:04 am
Forum: PMP® Open Forum
Topic: Rita: estimate activity resources
Replies: 1
Views: 445

Re: Rita: estimate activity resources

Dipti, Bottom-up estimates are the ones which are created by aggregating the estimates at the lower level components of the WBS. Hence if we are breaking the deliverable further and then estimating each of these lower level activities it is bottom-up estimation. Where as the top-down refer to estima...
by kniraj
Fri Jan 16, 2015 3:41 am
Forum: PMP® Open Forum
Topic: PMP exam in 7 days
Replies: 4
Views: 884

Re: PMP exam in 7 days

Do go through the areas where you had difficulty or low score. Make sure that you revise these areas well and as bs_pani said ... PMBOK read is a must.
by kniraj
Fri Jan 09, 2015 5:48 am
Forum: PMP® Open Forum
Topic: Project Staff Assignments
Replies: 1
Views: 694

Re: Project Staff Assignments

This extract is from the Section 9.2.3.1 Which is Acquire Project Team outputs (PMBOK 5). The Acquire Team process is concerned with identification of resources you need for the project work, get them on board and then assign responsibilities. So in the context of your question "include a proje...
by kniraj
Fri Jan 09, 2015 5:33 am
Forum: PMP® Open Forum
Topic: Project Administrative staff
Replies: 1
Views: 388

Re: Project Administrative staff

I think the administrative staff would largely be involved in tracking and reporting - basically a non-core project management activity.
by kniraj
Fri Jan 02, 2015 6:11 am
Forum: PMI-PBA Open Forum
Topic: PMI-PBA - Practice Guide and Other books
Replies: 4
Views: 1204

Re: PMI-PBA - Practice Guide and Other books

Great .. Congratulations ... ! Looking forward for the updates :)
by kniraj
Fri Jan 02, 2015 6:09 am
Forum: PMP® Exam Lessons – Success Stories
Topic: The three letters PMP !!!
Replies: 6
Views: 1392

Re: The three letters PMP !!!

Hey Ranjit... Heartiest Congratulations ... !
by kniraj
Tue Dec 30, 2014 9:30 am
Forum: PMI-PBA Open Forum
Topic: PMI-PBA - Practice Guide and Other books
Replies: 4
Views: 1204

Re: PMI-PBA - Practice Guide and Other books

Thanks Saket .. I also got hold of the list of those 11 books recommended by PMI for this exam ... just wanted to know if you have any specific recommendation .. in case i want to go thru a few for an additional reference.
by kniraj
Mon Dec 29, 2014 12:58 pm
Forum: PMI-PBA Open Forum
Topic: PMI-PBA - Practice Guide and Other books
Replies: 4
Views: 1204

PMI-PBA - Practice Guide and Other books

The practice guide is out now ... so this is what we need to refer if we were to give the exam right ? Also which are the other books we need to refer... do we have a list available. Thanks
by kniraj
Mon Dec 29, 2014 11:34 am
Forum: PMP® Open Forum
Topic: Scheduling dependencies
Replies: 3
Views: 893

Re: Scheduling dependencies

Saket,
Could you please explain a bit more ... I was under the impression that Discretionary dependencies create arbitray float and these should be eliminated if we want to look at schedule optimization.
by kniraj
Mon Dec 29, 2014 11:23 am
Forum: PMP® Exam Lessons – Success Stories
Topic: Expert Advice required - PMP Exam countdown started
Replies: 11
Views: 2467

Re: Expert Advice required - PMP Exam countdown started

Thanks all for the wishes ...

I was on a break for the last couple of days... Have updated the Lessons Learned on a new thread.
by kniraj
Mon Dec 29, 2014 11:17 am
Forum: PMP® Exam Lessons – Success Stories
Topic: PMP Exam - Lessons Learned
Replies: 0
Views: 887

PMP Exam - Lessons Learned

The beginning My PMP journey started with my boss asking to take a look at this certification as it would help to formalize my skill as a project manager. This was in the month of July 2014. I explored the PMI site on the details and decided to take this challenge and get my certification before th...
by kniraj
Fri Dec 26, 2014 11:12 am
Forum: PMP® Exam Lessons – Success Stories
Topic: Expert Advice required - PMP Exam countdown started
Replies: 11
Views: 2467

Re: Expert Advice required - PMP Exam countdown started

Dear all, Pleased to inform you all that i cleared my PMP today .. (with 5Ps :) ) Many thanks to Saket and team for hosting such great forum and site thanks to Ranjit, Bhabani, Pankaj and all for the assistance provided Saket you should seriously consider writing a PMP Prep book ... the articles on ...
by kniraj
Thu Dec 25, 2014 4:35 pm
Forum: PMP® Open Forum
Topic: Scheduling dependencies
Replies: 3
Views: 893

Re: Scheduling dependencies

hi Narendra, Discretionary dependencies are preferred logic or something which is desired. Which means we CAN let go off such dependencies if there is a need to fast track the schedule. At times because the team would prefer to do a few activities in a certain sequence can generate a flow (arbitrary...
by kniraj
Thu Dec 25, 2014 1:33 pm
Forum: PMP® Open Forum
Topic: Contract Type and Risk
Replies: 10
Views: 1579

Re: Contract Type and Risk

Thanks .. this is also very nicely shown in Rita's 8th ed. Pg 479 .. Its a graph good one
by kniraj
Thu Dec 25, 2014 9:58 am
Forum: PMP® Open Forum
Topic: Contract Type and Risk
Replies: 10
Views: 1579

Re: Contract Type and Risk

The question is from HeadFirst (200 free) and it says T&M while I marked it as option A i.e. CPFF

Thanks ...
by kniraj
Thu Dec 25, 2014 5:27 am
Forum: PMP® Open Forum
Topic: Contract Type and Risk
Replies: 10
Views: 1579

Contract Type and Risk

Which of the following contracts has the MOST risk for the buyer?
A Cost plus fixed fee (CPFF)
B Time and Materials (T&M)
C Cost plus award fee (CPAF)
D Fixed price (FP)

It would be option A right ?
by kniraj
Thu Dec 25, 2014 4:05 am
Forum: PMP® Open Forum
Topic: Projectized or Matrix Organization
Replies: 5
Views: 917

Re: Projectized or Matrix Organization

The question says that the resources have come from a pool of resources and will be released for reassignment. To me both seem to be projectized organization. In a matrix, the resources would come from different functional areas and will go back to their own functional areas or for that matter they ...
by kniraj
Wed Dec 24, 2014 4:19 pm
Forum: PMP® Open Forum
Topic: Projectized or Matrix Organization
Replies: 5
Views: 917

Projectized or Matrix Organization

You are managing a complex project which requires some highly skilled resources on embedded design. You obtain these resources from the organization pool specifying the duration for which they would be required. Once your project activity is complete you need to free these resources for reassignment...
by kniraj
Wed Dec 24, 2014 3:30 pm
Forum: PMP® Open Forum
Topic: Framework and PM Processes
Replies: 8
Views: 1199

Re: Framework and PM Processes

It could be option 4 is because ... We can try to get permission for publishing / sharing the template and if the permission is denied we can further decline the request. There is no harm in trying to ask for the permission - does not conflict with ethics. This is my view...
by kniraj
Wed Dec 24, 2014 3:27 pm
Forum: Oliver 75 PMP Questions
Topic: Oliver 75 - 36th Question
Replies: 4
Views: 1187

Re: cost of quality

Pallavi,
Do refer to the COQ table on the page 235 of PMBOK5. The COQ elements and categorization is clear. Also i have so far not seen any question out of the items listed there ... Hope that helps...
by kniraj
Wed Dec 24, 2014 3:20 pm
Forum: PMP® Open Forum
Topic: Develop Project Charter for a new phase ? -
Replies: 6
Views: 1051

Re: Develop Project Charter for a new phase ? -

Yes, I agree.. it is confusing.. This is from pmstudy.com
by kniraj
Tue Dec 23, 2014 12:13 pm
Forum: PMP® Open Forum
Topic: Develop Project Charter for a new phase ? -
Replies: 6
Views: 1051

Re: Develop Project Charter for a new phase ? -

Thanks Ranjit, I was under the impression that Charter would define the entire project at once (all phases etc..) Identify Stakeholders could be done for every phase as you rightly mentioned.
by kniraj
Tue Dec 23, 2014 12:12 pm
Forum: PMP® Open Forum
Topic: Payback Period
Replies: 5
Views: 843

Re: Payback Period

Many Thanks Pankaj. but we see that the outflows continue after 3rd year as well and are more than the inflows - Don't we need to take that into consideration - on an overall basis we see that inflows are lesser than the outflows.
by kniraj
Tue Dec 23, 2014 8:45 am
Forum: PMP® Open Forum
Topic: Payback Period
Replies: 5
Views: 843

Payback Period

A project manager is assigned to a project early in the project lifecycle. One of the things that must be done is to do a justification for the project. Since very little information is known about the project, the estimates are considered to be rough estimates. The following table is the project ma...
by kniraj
Tue Dec 23, 2014 6:59 am
Forum: PMP® Open Forum
Topic: Develop Project Charter for a new phase ? -
Replies: 6
Views: 1051

Develop Project Charter for a new phase ? -

I still think that the Project charter is not required for every phase. Please see the Question and explanation. Please provide your views as well .. thanks
charter-question.PNG
Charter Questions
charter-question.PNG (125.39 KiB) Viewed 1051 times

Charter_Explain.PNG
Solution
Charter_Explain.PNG (93.26 KiB) Viewed 1051 times
by kniraj
Sat Dec 20, 2014 9:36 am
Forum: PMP® Open Forum
Topic: Oliver Lehman - Q73
Replies: 2
Views: 992

Oliver Lehman - Q73

During project planning, you are presented with the following diagram that depicts a cumulative likelihood distribution for the duration of a project: oliver73.PNG What kind of conclusion can you draw from the information depicted in it? o The likeliness that the project will finish exactly at the d...
by kniraj
Thu Dec 18, 2014 10:45 am
Forum: PMP® Open Forum
Topic: Corrective / Preventive question - Scorodo Lite14
Replies: 2
Views: 592

Re: Corrective / Preventive question - Scorodo Lite14

Thanks Amit ... I got confused :(
by kniraj
Thu Dec 18, 2014 10:34 am
Forum: PMP® Open Forum
Topic: Conflict
Replies: 1
Views: 385

Re: Conflict

Collaboration refer to incorporating multiple view points and insights from different perspectives. Smoothing will focus on the areas of agreements rather than disagreements and try to come to consensus. Hence in your question the PM is trying to first get views from all and then reach a certain con...
by kniraj
Wed Dec 17, 2014 12:54 pm
Forum: PMP® Open Forum
Topic: Q : 17th december
Replies: 8
Views: 1254

Re: Q : 17th december

I think Rita say's option 1 - Determine the reporting structure
by kniraj
Wed Dec 17, 2014 12:53 pm
Forum: PMP® Open Forum
Topic: Calculation qts
Replies: 7
Views: 837

Re: Calculation qts

Dipti,
You have to subtract, but not 25 and 75 ... but 25% and 75% of the estimate.

lower range = 200000*0.25 = 50,000 hence 200000-50000 = 150000
upper range = 200000*0.75 = 150000 hence 200000+150000 = 350000
by kniraj
Wed Dec 17, 2014 6:54 am
Forum: PMP® Open Forum
Topic: Corrective / Preventive question - Scorodo Lite14
Replies: 2
Views: 592

Corrective / Preventive question - Scorodo Lite14

During a project update meeting, one of the key stakeholders expressed his displeasure over the recently produced deliverables. 1% of the produced deliverables had minor defects. This stakeholder has been a resisting stakeholder so far. What must the project manager do in order to bring the future p...
by kniraj
Wed Dec 17, 2014 6:34 am
Forum: PMP® Open Forum
Topic: Calculation qts
Replies: 7
Views: 837

Re: Calculation qts

Order of magnitude estimate is -25% to +75% and hence the answer b is the closest.
by kniraj
Tue Dec 16, 2014 6:49 am
Forum: PMP® Exam Lessons – Success Stories
Topic: Expert Advice required - PMP Exam countdown started
Replies: 11
Views: 2467

Re: Expert Advice required - PMP Exam countdown started

Thanks Bhabani, I have so far taken around 4 full tests - the timed ones with 200 questions (Head First, PM Study, PMP Exam Simulator, Simpli Learn) and they were in the range of 75% on avg. I found quite a few questions on these tests very heavy on ITTO and some questions were totally out of the PM...
by kniraj
Tue Dec 16, 2014 4:50 am
Forum: PMP® Exam Lessons – Success Stories
Topic: Expert Advice required - PMP Exam countdown started
Replies: 11
Views: 2467

Expert Advice required - PMP Exam countdown started

Dear all, I am scheduled to give the exam in the next 10 days ... any thoughts on what should i focus on most in these 10 days. So far i have gone thru the PMBOK twice and several other stuff on the net. Gave multiple exams and my score on the IIL Exam Prep and Scorodo is around 80-84% and other sit...
by kniraj
Tue Dec 16, 2014 4:08 am
Forum: PMP® Exam Lessons – Success Stories
Topic: Now I have an updated signature :)
Replies: 6
Views: 1375

Re: Now I have an updated signature :)

Heartiest congratulations bhabani !
by kniraj
Sun Dec 14, 2014 6:12 am
Forum: PMP® Open Forum
Topic: Critical path method - Test questions
Replies: 1
Views: 575

Critical path method - Test questions

Does anyone have a few practice questions on the CPM for the PMP exam. I am scheduled to give the exam shortly want to go thru a few questions and practice.
by kniraj
Sun Dec 14, 2014 5:51 am
Forum: PMP® Open Forum
Topic: Configuration Management - PMStudy.com
Replies: 3
Views: 884

Re: Configuration Management - PMStudy.com

Thanks ... much clear now after the video and also when Rajnit mentioned that Configuration is for versions and not contents etc .. the key word here :)
by kniraj
Thu Dec 11, 2014 7:31 pm
Forum: PMP® Open Forum
Topic: Configuration Management - PMStudy.com
Replies: 3
Views: 884

Configuration Management - PMStudy.com

You are the project manager of a pharmaceutical company responsible for releasing a new drug in the market. While managing the project, you have created several documents (e.g., project management plan; risk registers and other registers; project calendars; change management documentation; etc.). Al...
by kniraj
Tue Dec 09, 2014 3:27 am
Forum: PMP® Open Forum
Topic: Head First - Conflict Resolution
Replies: 5
Views: 852

Re: Head First - Conflict Resolution

Thanks for the explanation.
by kniraj
Sat Dec 06, 2014 8:02 am
Forum: PMP® Open Forum
Topic: Head First - Conflict Resolution
Replies: 5
Views: 852

Head First - Conflict Resolution

You have been hired by a contractor, who wants you to manage a construction project for one of their clients. The project team has been working for two months, and is 35% done with the job. Two of your team members come to you with a conflict about how to handle the ongoing maintenance for a piece o...
by kniraj
Sat Dec 06, 2014 7:59 am
Forum: PMP® Open Forum
Topic: Benefit Cost Ratio - Interpretation Question
Replies: 10
Views: 1294

Re: Benefit Cost Ratio - Interpretation Question

Thanks Bhabani and Ranjit ... At times it can be risky to take the questions and answers available in the net. :)
by kniraj
Fri Dec 05, 2014 1:54 pm
Forum: PMP® Open Forum
Topic: Benefit Cost Ratio - Interpretation Question
Replies: 10
Views: 1294

Benefit Cost Ratio - Interpretation Question

You are reviewing several feasibility reports.One report shows a benefit cost ratio of 2.1.This means: A. The costs are 2.1 times the benefits. B. The profit is 2.1 times the costs C. The payback is 2.1 times the costs. D. The cost is 2.1 times the profit. The correct answer is D, but I would like t...
by kniraj
Tue Dec 02, 2014 1:09 pm
Forum: PMP® Open Forum
Topic: Earned Value - SPI at project completion
Replies: 5
Views: 1054

Re: Earned Value - SPI at project completion

Ranjit and Saket, Thanks .. will go thru the videos once i reach home :) I plan to give the exam on the 26th Dec so currently giving as many mock exams as possible
by kniraj
Mon Dec 01, 2014 5:51 pm
Forum: PMP® Open Forum
Topic: Earned Value - SPI at completion (q2)
Replies: 1
Views: 443

Earned Value - SPI at completion (q2)

One more.
Your 3-year project finished 4 months early. What is your final SPI?
[list=]
0.89
1.13
1.04
1
[/list]

I calculated 0.89, but the correct answer is 1 again ... is it that the SPI after completion will always be 1 ... ?
by kniraj
Mon Dec 01, 2014 5:48 pm
Forum: PMP® Open Forum
Topic: Earned Value - SPI at project completion
Replies: 5
Views: 1054

Earned Value - SPI at project completion

You are completing your final project report. You include information on the final variances. If the project was scheduled to take 12 months, and it finished in 14 months, what would your final SPI results be? [list=]1 1.17 0.86 Not enough information to determine[/list] The answer is 1, can someone...
by kniraj
Mon Dec 01, 2014 5:46 pm
Forum: PMP® Open Forum
Topic: S curve
Replies: 1
Views: 458

Re: S curve

Saket has a youtube video https://www.youtube.com/watch?v=pC1-TwwKkq8 Then there is Dave Litten http://www.brighthubpm.com/monitoring-projects/51982-understanding-the-s-curve-theory-for-project-management-monitoring/ Also http://www.brighthubpm.com/monitoring-projects/51982-understanding-the-s-curve...