Re: Thank you, Saket for the great videos!

OK, will check out. Thanks again, Saket.
by tecklung
Fri Oct 17, 2014 4:21 am
Forum: PMP® Exam Lessons – Success Stories
Topic: Thank you, Saket for the great videos!
Replies: 3
Views: 926

Thank you, Saket for the great videos!

Hi Saket, Would like to inform that I passed my exam yesterday and I want to let you know that you are doing very good deeds by making those PMP videos on Youtube. Great stuff as they help me absorb a lot better. Many thanks, Saket! I did a write-up in the LinkdedIn group on my exam experience:- htt...
by tecklung
Sun Oct 12, 2014 9:26 am
Forum: PMP® Open Forum
Topic: On Standard Deviations
Replies: 5
Views: 1206

Re: On Standard Deviations

Thanks all for the help. I manage to understand the concept.
by tecklung
Thu Oct 09, 2014 1:02 am
Forum: PMP® Open Forum
Topic: CPM Question
Replies: 11
Views: 2327

Re: CPM Question

Good stuff, Saket! Innovative response too! Super Liked!
by tecklung
Tue Oct 07, 2014 3:50 am
Forum: PMP® Open Forum
Topic: Calculating Contingency Reserve
Replies: 6
Views: 1606

Re: Calculating Contingency Reserve

Thanks Saket! Understood now.
by tecklung
Mon Oct 06, 2014 3:53 am
Forum: PMP® Open Forum
Topic: Calculating Contingency Reserve
Replies: 6
Views: 1606

Re: Calculating Contingency Reserve

Thanks again, Sakat. Quote " The contingency reserve may be a percentage of the estimated cost, a fixed number, or may be developed by using quantitative analysis methods. " Could you advise during the calculation using quantitative analysis methods, do we calculate the estimation of cost/...
by tecklung
Sun Oct 05, 2014 1:02 pm
Forum: PMP® Open Forum
Topic: Calculating Contingency Reserve
Replies: 6
Views: 1606

Re: Calculating Contingency Reserve

Thanks, Sakat. I was referring to the cost aspect of the Contingency Reserve. What you have mentioned is the schedule aspect. Could you further advise the costing aspect?
by tecklung
Sun Oct 05, 2014 2:53 am
Forum: PMP® Exam Lessons – Success Stories
Topic: cleared PMP exam today ...........
Replies: 10
Views: 1902

Re: cleared PMP exam today ...........

Congrats, Achal! Thanks for sharing your learning experience.
by tecklung
Sun Oct 05, 2014 2:51 am
Forum: PMP® Open Forum
Topic: On Standard Deviations
Replies: 5
Views: 1206

On Standard Deviations

Dear all, I would like to deduce standard deviations and their associated % and make a list to memorize from the below question from a Mock Exam. Can I say that... 1 Standard Deviation = 68% 2 Standard Deviations = 95% 3 Standard Deviations = 99% Do correct me if I am wrong. Thanks. QUESTION If you ...
by tecklung
Sun Oct 05, 2014 2:47 am
Forum: PMP® Open Forum
Topic: Calculating Contingency Reserve
Replies: 6
Views: 1606

Calculating Contingency Reserve

Dear all, Have been practicing some mock questions and come to learn that the calculation of the amount of contingency reserve can done at project level or activity level . So, I would imagine that these approach can be done respectively:- a) percentages based on a previous similar project b) The su...
by tecklung
Sun Oct 05, 2014 2:43 am
Forum: PMP® Exam Lessons – Success Stories
Topic: PMP Exam Day
Replies: 8
Views: 2913

Re: PMP Exam Day

Congrats Umesh! BTW, a silly question. Could you advise?

Are we allow to stand up and stretch a bit during the exam?
by tecklung
Sun Oct 05, 2014 2:41 am
Forum: PMP® Open Forum
Topic: HR Question
Replies: 3
Views: 675

Re: HR Question

Hi bandarna, The PM is actually planning for Project HR Management. The HR Management Plan includes:  Roles and Responsibilities <---------  Role and Authority Level(s) <---------  Responsibility Areas (RACI) <---------  Skills and Competencies  Lines of Reporting  External and Internal resour...