Search found 1794 matches

by manishpn
Fri Aug 17, 2018 8:33 pm
Forum: PMP® Queries and Tips
Topic: contract related
Replies: 3
Views: 54

Re: contract related

remember that whenever a contract is involved, that contract is a legal document and any change to it has to go through a formal change.
so if a change in contract scope is requested it has to go through formal process.
option C is the right choice
by manishpn
Fri Aug 17, 2018 4:36 pm
Forum: PMP® Queries and Tips
Topic: contract related
Replies: 3
Views: 54

Re: contract related

Training to the customer was provided regarding the deliverable of the project. Project is almost finished and deliverable has been accepted. Customer wants the module or written training content, which was not included in the contract. What should you do? A. Tell customer that as it will take time...
by manishpn
Fri Aug 17, 2018 4:30 pm
Forum: PMP® Queries and Tips
Topic: Closing
Replies: 1
Views: 109

Re: Closing

You were working on a project that consisted of five major phases: analysis, design, development, testing, and implementation. The testing phase failed to meet the project sponsor’s expectations. Because of that failure, the sponsor canceled the project and you were asked to perform a closing proce...
by manishpn
Wed Aug 15, 2018 7:53 pm
Forum: PMP® Queries and Tips
Topic: Corrective actions
Replies: 4
Views: 195

Re: Corrective actions

approved CR does not necessary rectify a defective product,
corrective actions are more to bring project back on track
by manishpn
Wed Aug 15, 2018 7:28 pm
Forum: PMP® Queries and Tips
Topic: Quality Management
Replies: 1
Views: 111

Re: Quality Management

im not sure if error categories are terms in PMBOK
by manishpn
Wed Aug 15, 2018 3:44 pm
Forum: PMP® Queries and Tips
Topic: Corrective actions
Replies: 4
Views: 195

Re: Corrective actions

There were few change requests raised which resulted in corrected actions. All corrective actions must be implemented in Direct and manage project work. Which process does the effectiveness of implemented corrective actions gets evaluated: A. Direct and manage Project Work B. Monitor and Control Pr...
by manishpn
Wed Aug 15, 2018 6:46 am
Forum: PMP® Exam Lessons – Success Stories
Topic: Passed PMP Exam Today - 1st Attempt
Replies: 2
Views: 199

Re: Passed PMP Exam Today - 1st Attempt

congratulations and thanks for sharing, can also mention about the types and complexity of questions in exam and how many agile questions did you encounter?
by manishpn
Tue Aug 14, 2018 7:42 pm
Forum: PMP® Queries and Tips
Topic: Organisation type
Replies: 1
Views: 74

Re: Organisation type

The project manager has the lowest level of authority in a _______________ organization: A. Functional marked as correct B. Weak matrix C. Strong matrix D. Projectized Rita 9- PM's role in weak matrix and functional organization might be that of Project Expeditor and Coordinator. PMNOK6- PM authori...
by manishpn
Tue Aug 14, 2018 7:35 pm
Forum: PMP® Queries and Tips
Topic: Process groups
Replies: 1
Views: 55

Re: Process groups

All of the following are characteristics of Project Management Process Groups EXCEPT : A. Project Management Process Groups are linked by the outputs they produce. B. The Process Groups are seldom either discrete or one-time events; they are overlapping activities that occur throughout the project....
by manishpn
Tue Aug 14, 2018 7:21 pm
Forum: PMP® Open Forum
Topic: Scope Management
Replies: 3
Views: 158

Re: Scope Management

the idea behind the question it to tell students that Project management plan is built iteratively, so not all subsidiaries are in initial versions of PMP
by manishpn
Tue Aug 14, 2018 7:18 pm
Forum: PMP® Queries and Tips
Topic: control procurement
Replies: 3
Views: 129

Re: control procurement

hi its difficult to keep in exchanging and read long notes, i would recommend you watch Sakets videos to clear your generic doubts, and come up with precise queries on the forum , alternatively you can attend the clarification session and we can discuss
by manishpn
Mon Aug 13, 2018 7:33 pm
Forum: PMP® Open Forum
Topic: Scope Management
Replies: 3
Views: 158

Re: Scope Management

not sure what is the query?

did you read the explanation provided?
by manishpn
Mon Aug 13, 2018 7:31 pm
Forum: PMP® Queries and Tips
Topic: control procurement
Replies: 3
Views: 129

Re: control procurement

With PMBOK6 Close procurement has been moved from close project or phase to control procurement and that to from a process to an output this time. I assume that activities of close procurement still remains the same. The only difference seem to be is that those activities have been moved under Cont...
by manishpn
Mon Aug 13, 2018 10:17 am
Forum: PMP® Queries and Tips
Topic: Procurement Mgmt
Replies: 2
Views: 92

Re: Procurement Mgmt

Six months after you formally closed an office relocation project, you receive a phone call from a collection agency indicating that your company refuses to pay the invoices of one of the vendors. What would be the best course of action for you to take? A. Revisit the Close Procurements process of ...
by manishpn
Sun Aug 12, 2018 7:02 pm
Forum: PMP® Queries and Tips
Topic: Procurement Mgmt
Replies: 1
Views: 77

Re: Procurement Mgmt

Q34 from Rita 9th edition- The 80,000 contract specifies that the seller will bill the buyer at 10,000 per month. Seller completed the project work faster than planned. Therefore, they bill the buyer for 15,000 for the work performed in the last month. The buyer should- A. Send a breech of contract...
by manishpn
Sun Aug 12, 2018 6:49 pm
Forum: PMP® Queries and Tips
Topic: Resource Mgmt
Replies: 1
Views: 47

Re: Resource Mgmt

Not all inputs and all T and T are used in the first pass of the process. when creating SND for the first time, the resource requirement are estimated but when actual resources are identified based on the availability and competance the SND will be optimized for e.g : to complete a WEB page PM estim...
by manishpn
Sat Aug 11, 2018 2:25 pm
Forum: PMP® Queries and Tips
Topic: Lessons learned
Replies: 1
Views: 116

Re: Lessons learned

Due to a tight project schedule, a project manager did not document lessons learned all through the project. However, at the end of the project, he finally documented the lessons learned. Your comment on this would be: A. This is ok. At a minimum, lessons learned should be documented at the end of ...
by manishpn
Sat Aug 11, 2018 2:20 pm
Forum: PMP® Queries and Tips
Topic: Cost
Replies: 1
Views: 52

Re: Cost

bad quality question , whats the source?
by manishpn
Sat Aug 11, 2018 2:19 pm
Forum: PMP® Queries and Tips
Topic: WBS
Replies: 1
Views: 63

Re: WBS

Hi Manish, Can you help me finding the right answer to this one along with a reason- You are decomposing your WBS into smaller pieces of work. What is one item that does NOT describe how far the work should be decomposed? A. Until it can be realistically estimated B. Can’t be subdivided any further...
by manishpn
Sat Aug 11, 2018 2:13 pm
Forum: PMP® Queries and Tips
Topic: Stakeholder Engagement
Replies: 1
Views: 49

Re: Stakeholder Engagement

Please help me with the answer- Jane is managing an office refurbishment project. All of the project stakeholders have been identified and classified. The stakeholder management plan has also been approved. Jane is managing a project for the first time in her life and she is relying on the PMBOK gu...
by manishpn
Sat Aug 11, 2018 2:07 pm
Forum: PMP® Queries and Tips
Topic: Contracts
Replies: 1
Views: 44

Re: Contracts

What similarity exists between a cost-reimbursable contract and a time and material contract? A. They are open ended . B. The closure date is part of the contract. C. They have fixed bonus rates. D. They can never grow in value. Can you please explain what are open ended contracts in reference to o...
by manishpn
Sat Aug 11, 2018 1:54 pm
Forum: PMP® Queries and Tips
Topic: Resource Mgmt
Replies: 3
Views: 134

Re: Resource Mgmt

This is not izenbridge question. By Human Resource Mgmt Plan in question we mean 'Resource Mgmt Plan' as the name has been modified now. By your reply it seems option 1 should be the correct answer of this question- option 1nd 2 both are correct HR plan specified how resources will be utilized . - ...
by manishpn
Sat Aug 11, 2018 1:51 pm
Forum: PMP® Queries and Tips
Topic: Project Funding Requirements
Replies: 1
Views: 78

Re: Project Funding Requirements

Which of the following statements are FALSE regarding project funding requirements? A. Funding requirements are derived from cost baselines B. Portions of management reserve can be include in each funding step C. The total funds required are the cost baseline plus the management contingency reserve...
by manishpn
Fri Aug 10, 2018 8:16 am
Forum: PMP® Exam Lessons – Success Stories
Topic: Passed PMP - First Attempt - around 50 Days Study !
Replies: 2
Views: 255

Re: Passed PMP - First Attempt - around 50 Days Study !

Congratulations and well deserved, w.r.t our Mocks : First Mock is intended to be on tougher side to ensure that our students are well prepared. Also note that PMI keeps changing its exam question pattern every few months , some months before questions were very lengthy and same can happen in future...
by manishpn
Thu Aug 09, 2018 12:25 pm
Forum: PMP® Queries and Tips
Topic: Project phases
Replies: 3
Views: 186

Re: Project phases

I would disagree with that statement, phases can overlap
by manishpn
Tue Aug 07, 2018 6:31 pm
Forum: PMP® Queries and Tips
Topic: Cost Mgmt
Replies: 2
Views: 94

Re: Cost Mgmt

Hi Manish, I need your assistance in reference to this question- _______ are not necessarily used to establish the cost baseline of a project. o Schedule activity or work package cost estimates o The work breakdown structure and WBS dictionary o The project schedule and resource calendars. o The ri...
by manishpn
Tue Aug 07, 2018 6:23 pm
Forum: PMP® Queries and Tips
Topic: Cost Mgmt
Replies: 2
Views: 94

Re: Cost Mgmt

Hi Manish, I need your assistance in reference to this question- _______ are not necessarily used to establish the cost baseline of a project. o Schedule activity or work package cost estimates o The work breakdown structure and WBS dictionary o The project schedule and resource calendars. o The ri...
by manishpn
Tue Aug 07, 2018 5:55 pm
Forum: PMP® Queries and Tips
Topic: PERT
Replies: 1
Views: 48

Re: PERT

This question from Oliver is quiet controversial, I am not an expert in statistics but us has been debated a lot. Since almost all Math questions in exam are nowadays very simple you should not spend a lot of time on such questions Data given is P = O for Activity 1 is 18 & Activity 2 is 24. let...
by manishpn
Tue Aug 07, 2018 5:32 pm
Forum: PMP® Queries and Tips
Topic: EVM
Replies: 1
Views: 71

Re: EVM

typical variance
ETC = Work remaining / Cost performance indicator

ETC = (BAC – EV) / CPI
= 1000000/0.833
= 1200000

EAC = AC + EAC
= 120000+120000
by manishpn
Tue Aug 07, 2018 5:01 pm
Forum: PMP® Queries and Tips
Topic: Project phases
Replies: 3
Views: 186

Re: Project phases

what mock are your referring to ?
by manishpn
Mon Aug 06, 2018 11:00 am
Forum: PMP® Queries and Tips
Topic: Project management audit
Replies: 4
Views: 392

Re: Project management audit

ok so does this solve your query?
by manishpn
Fri Aug 03, 2018 6:37 pm
Forum: PMP® Open Forum
Topic: Fast Tracking
Replies: 8
Views: 1636

Re: Fast Tracking

Questions without a logic does not come in Exam,

look at crashing definition in PMBOK, its a schedule shortening technique,

I would not spend time on such questions which are of not good quality
by manishpn
Fri Aug 03, 2018 6:35 pm
Forum: PMP® Queries and Tips
Topic: Project management audit
Replies: 4
Views: 392

Re: Project management audit

to be honest I do not understand the question and its quality. I think maybe question asks which option is not true. What is the source and what is the explanation provided for option C Hi Manish, Can you please explain why option A cannot be correct in this case? The Project Management Office (PMO)...
by manishpn
Sun Jul 29, 2018 6:25 pm
Forum: PMP® Queries and Tips
Topic: Stakeholder Mgmt
Replies: 1
Views: 173

Re: Stakeholder Mgmt

you are correct, is this izenbridge question then it has to be rectified
by manishpn
Sun Jul 29, 2018 6:24 pm
Forum: PMP® Queries and Tips
Topic: Resource Mgmt
Replies: 3
Views: 134

Re: Resource Mgmt

we dont have human resource management plan anymore n PMBOK6

resource management plan mentions how resources in the project will be estimated, acquired, managed and used/utilized.

if this is Izenbridge question it has to be rectified
by manishpn
Sun Jul 29, 2018 6:19 pm
Forum: PMP® Queries and Tips
Topic: Procurement Mgmt
Replies: 1
Views: 94

Re: Procurement Mgmt

Why does a project procure? Sometimes to make it faster (Schedule) If project lacks competence to deliver a certain part of project (Scope) and also it is done sometimes if the budget is constrained and PM needs to look at cheaper alternatives (Budget) So procurement may be done for all above 3 reas...
by manishpn
Sun Jul 29, 2018 6:15 pm
Forum: PMP® Queries and Tips
Topic: Scope validation
Replies: 1
Views: 155

Re: Scope validation

not sure what the issues is?
Project is not run for any individuals satisfaction, satisfaction i subjective,
The deliverable have to be compared to tangible project requirements
by manishpn
Sun Jul 29, 2018 6:13 pm
Forum: PMP® Exam Lessons – Success Stories
Topic: Hurray...!! Finally passed PMP exam on 29/07/2018 ..!
Replies: 3
Views: 264

Re: Hurray...!! Finally passed PMP exam on 29/07/2018 ..!

congratulations on your success, enjoy it

How many questions did you find on Agile and on trends.
by manishpn
Wed Jul 25, 2018 10:12 am
Forum: PMP® Open Forum
Topic: Closing Process Group Question
Replies: 4
Views: 821

Re: Closing Process Group Question

Please let me know the correct order/steps in the closing process. As per one website, the order is: 1. Confirm that all the requirements have been met as per the PMP 2. Close Procurements. Within this process, multiple action are involved such as: 2.a. Verify the product. 2.b. Issue formal accepta...
by manishpn
Wed Jul 25, 2018 10:04 am
Forum: PMP® Open Forum
Topic: Fast Tracking
Replies: 8
Views: 1636

Re: Fast Tracking

crashing is also done to compress the schedule, so i would not spend more time on such questions
by manishpn
Wed Jul 18, 2018 3:38 pm
Forum: PMP® Queries and Tips
Topic: EVM Question
Replies: 1
Views: 400

Re: EVM Question

they have used AC + (BAC - EV) formula, used when variance is atypical
however as thumb rule if nothing is explicitly mentioned we should assume variance is typical
by manishpn
Wed Jul 18, 2018 3:28 pm
Forum: PMP® Queries and Tips
Topic: Sample template for Request for proposal
Replies: 1
Views: 181

Re: Sample template for Request for proposal

RFP document can range from few pages to several depending on the scope of the WOrk to be bought.
What kind of template are you looking for?
by manishpn
Wed Jul 18, 2018 2:33 pm
Forum: PMP® Open Forum
Topic: Fast Tracking
Replies: 8
Views: 1636

Re: Fast Tracking

the question makes little sense to me, unless maybe I am missing something.

If the network diagram cannot be changed , no technique can be useful as resource leveling or compression technique will eventually optimize/change the plan
by manishpn
Wed Jul 18, 2018 2:23 pm
Forum: PMP® Open Forum
Topic: plan stakeholder engagement
Replies: 4
Views: 446

Re: plan stakeholder engagement

if I Have to choose best options, it would be A, creating and maintaining relationship with stakeholder is important, option C wont be possible if you dont have good working relation with the stakeholders
by manishpn
Mon Jul 16, 2018 12:46 pm
Forum: PMP® Queries and Tips
Topic: Change mgmt
Replies: 1
Views: 192

Re: Change mgmt

the statement says typically and not always, so as a thumb rule if the change is not impacting baseline it can skip CCB, however PM still need to do holistic impact analysis of the change
by manishpn
Mon Jul 09, 2018 8:03 pm
Forum: PMP® Open Forum
Topic: PMP Agile guide & final exam
Replies: 1
Views: 219

Re: PMP Agile guide & final exam

Understanding of Agile related adaption and tailoring for each knowledge area is needed, Agile guide is a good to read if you have time,
by manishpn
Mon Jul 09, 2018 5:00 pm
Forum: PMP® Open Forum
Topic: plan stakeholder engagement
Replies: 4
Views: 446

Re: plan stakeholder engagement

if you need faster response post in exclusive section I would suggest you refer to PMBOK6 based questions , Based on options provided first 3 are true, to certain extent, option B is also subset of the overall stakeholder engagement strategy though Project does not only focus on negative stakeholder...