Re: Risks in Contract Types!

In your project, you have been sub-contracting your development work to three consultancy firms. Which of the following statements about transferring risk to a contractor is not true? the question is asking which one of the following is FALSE. lets do elimination 1 Risk transference nearly always i...
by manishpn
Wed Jun 28, 2017 8:12 am
Forum: PMP® Open Forum
Topic: WORK AROUND IN RISK MANAGEMENT
Replies: 3
Views: 25

Re: WORK AROUND IN RISK MANAGEMENT

Management reserve is used for unkown unkonwn. so for risks which were not identified earlier management reserve can be used

however for risk which were identified but no response was planned, and for such risks when you use workarounds, management reserves cannot be used
by manishpn
Mon Jun 26, 2017 7:39 pm
Forum: PMP® Open Forum
Topic: Procurement problem
Replies: 2
Views: 44

Re: Procurement problem

This is not purely a procurement question, its about calculating target fees (profit) based on point of total assumption formula. Its rarely seen in exm however if you still want to try, i always recommend that you do your math and post it here for discussion, if you get ready answers for maths its ...
by manishpn
Mon Jun 26, 2017 7:36 pm
Forum: PMP® Open Forum
Topic: Benefit Cost Ratio - Interpretation Question
Replies: 9
Views: 651

Re: Benefit Cost Ratio - Interpretation Question

yes not a good quality question i must say,

but as i mentioned in last weeks clarification session we should always look for BCR ratio where Benifit is divided by cost.
by manishpn
Sun Jun 25, 2017 2:19 pm
Forum: PMP® Open Forum
Topic: Ethics Question
Replies: 3
Views: 48

Re: Ethics Question

Question : During an informal discussion Prooject Manager had with another PMP certificant, he mentioned how he was able to sit for the PMP Certification exam two years ago by using false contact hour certificates. PM should: 1 Report this to PMI 2 Report this to his supervisor 3 Do nothing, since ...
by manishpn
Sun Jun 25, 2017 2:17 pm
Forum: PMP® Open Forum
Topic: Ethics Question.
Replies: 3
Views: 38

Re: Ethics Question.

agree with makarand and Kapil .
by manishpn
Sun Jun 25, 2017 2:16 pm
Forum: PMP® Open Forum
Topic: Probability and Impact
Replies: 2
Views: 35

Re: Probability and Impact

These type of questions are rare in exam, I am not an expert on probability theory calculations,

if you are aware of the answer kindly share with others as well.

Please note that this is not related to depreciation or impact.
by manishpn
Sun Jun 25, 2017 2:13 pm
Forum: PMP® Open Forum
Topic: Stakeholder Engagement
Replies: 3
Views: 42

Re: Stakeholder Engagement

Stakeholder Unaware Resistant Neutral Supportive Leading Sponsor C D (What does this mean? stakeholder is at which level of engagement at this stage?) CEO C D Team Member C/D C = Current Engagement Level; D = Desired Engagement Level without really going into the details of the options , Sponsor en...
by manishpn
Fri Jun 23, 2017 8:18 pm
Forum: PMP® Open Forum
Topic: Benefit Cost Ratio - Interpretation Question
Replies: 9
Views: 651

Re: Benefit Cost Ratio - Interpretation Question

Yes I agree option A is the best choice
by manishpn
Fri Jun 23, 2017 8:15 pm
Forum: PMP® Open Forum
Topic: Stakeholder Engagement
Replies: 3
Views: 42

Re: Stakeholder Engagement

Not able to understand the matrix in question and options provided and what
If possible attach the picture of the question as your text is confusing
by manishpn
Mon Jun 19, 2017 11:07 am
Forum: PMP® Open Forum
Topic: Could not understand Schedule method, schedule model in Time Management
Replies: 1
Views: 85

Re: Could not understand Schedule method, schedule model in Time Management

Hi,

this is very broad topic and cnnot be typed and explained on forum.
Saket mentions about third party tools that are standard tools available in market
by manishpn
Mon Jun 19, 2017 11:03 am
Forum: PMP® Open Forum
Topic: Stakeholder Management
Replies: 6
Views: 143

Re: Stakeholder Management

I would pick: 1.Take into account risk tolerance (choosing the ans by elimination method) And to my understanding , working on Risk Tolerance would be PM and PM Teams responsibility rather than Sponsor/Customer , although Sponsor/Customer would contribute initially in giving their inputs for Risks ...
by manishpn
Sun Jun 18, 2017 8:20 pm
Forum: PMP® Open Forum
Topic: HR Management
Replies: 2
Views: 88

Re: HR Management

I agree with both of you,
by manishpn
Sun Jun 18, 2017 8:18 pm
Forum: PMP® Open Forum
Topic: Communication Management
Replies: 1
Views: 54

Re: Communication Management

Briefing is a form of formal verbal communication

for example if the sponsor call for a briefing meeting with project team to communicate certain key messages, it is a formal way of communication
by manishpn
Sun Jun 18, 2017 8:12 pm
Forum: PMP® Open Forum
Topic: Control Quality
Replies: 1
Views: 56

Re: Control Quality

Question :Control Quality is the process of monitoring and recording results of executing the quality base activities to do the performance and recommend necessary changes. To evaluate control quality output data, the project team must ideally have a working knowledge of: 1 Prevention and Inspectio...
by manishpn
Sun Jun 18, 2017 7:14 pm
Forum: PMP® Open Forum
Topic: Stakeholder Management
Replies: 6
Views: 143

Re: Stakeholder Management

A project manager has to manage different stakeholder expectations. Project sponsor and customer are two very important stakeholders in any project. In this respect, which of the following is NOT the responsibility of both the project sponsor and the customer? 1 Take into account risk tolerance - T...
by manishpn
Fri Jun 16, 2017 5:15 pm
Forum: PMP® Open Forum
Topic: Validate Scope in Project scope management
Replies: 1
Views: 63

Re: Validate Scope in Project scope management

Please put more shadow with examples on validate scope as could not understand from video. Validate scope is the process in which the deliverable are accepted by the end user (end user who are authorized to accept the deliverable s will be mentioned in project management plan) So if you look at the...
by manishpn
Fri Jun 16, 2017 4:59 pm
Forum: PMP® Open Forum
Topic: Procurement Management (Early Termination of the Contract)
Replies: 1
Views: 74

Re: Procurement Management (Early Termination of the Contract)

yes you are correct it can happen for any of the 3 reason mentioned ,
by manishpn
Thu Jun 15, 2017 12:32 pm
Forum: PMP® Open Forum
Topic: CS MT 16
Replies: 3
Views: 96

Re: CS MT 16

Close Project or phase is the process of completing and concluding all activities across all of the process group to officially close the project. Which of the following activities are NOT performed during the process? 1. Action required to transfer completed product or operations. 2. Action requir...
by manishpn
Wed Jun 14, 2017 1:50 pm
Forum: PMP® Open Forum
Topic: Project Management Plan Template with demo data.
Replies: 1
Views: 66

Re: Project Management Plan Template with demo data.

its not possible to upload the plan i have due to confidential informations in it however you can see templates to link below http://www.projectmanagementdocs.com/project-planning-templates/project-management-plan.html#axzz4jz53wEN1 if you are PMI member there are templates on projectmanagement.com ...
by manishpn
Wed Jun 14, 2017 11:17 am
Forum: PMP® Queries and Tips
Topic: Monitoring and Control Process in Project Integration management
Replies: 1
Views: 73

Re: Monitoring and Control Process in Project Integration management

There are 11 process in M and C process group. Project integration management should be seen as an integrating/Binding layer for all the knowledge areas. So when we talk about Monitoring and Control Process in Project Integration management we are referring to overall project performance monitoring,...
by manishpn
Mon Jun 12, 2017 7:28 pm
Forum: PMP® Queries and Tips
Topic: Regarding the Percentage Calculation of SV and CV
Replies: 1
Views: 74

Re: Regarding the Percentage Calculation of SV and CV

narayanankuttytp wrote:Hi
How we can calculate CV percentage and SV percentage

CV = EV-AC/EV *100
SV = EV-PV/EV * 100

Is this formula is correct

Cost Variance (CV) = Earned Value (EV) − Actual Cost (AC)
and
CV % = Cost Variance (CV) ⁄ Earned Value (EV)

so your formula is also right
by manishpn
Mon Jun 12, 2017 7:25 pm
Forum: PMP® Open Forum
Topic: CS MT 16
Replies: 3
Views: 96

Re: CS MT 16

Close Project or phase is the process of completing and concluding all activities across all of the process group to officially close the project. Which of the following activities are NOT performed during the process. 1. Action required to transfer completed product or operations. 2. Action requir...
by manishpn
Mon Jun 12, 2017 7:20 pm
Forum: PMP® Open Forum
Topic: Christopher Scordo MT 16Q
Replies: 1
Views: 81

Re: Christopher Scordo MT 16Q

You just taken over a project from another project manger about 6 months into a 12 month project. As a PM you get to know the 6 staffs member are relatives of the previous project manager. What is the course of action of new project manager? A. Notify stake holders about probability of nepotism. B....
by manishpn
Mon Jun 12, 2017 7:18 pm
Forum: PMP® Open Forum
Topic: Risk management (Risk and Issue)
Replies: 1
Views: 53

Re: Risk management (Risk and Issue)

what is the question here?
by manishpn
Wed May 24, 2017 4:27 pm
Forum: Oliver 75 PMP Questions
Topic: Oliver 75 - 46th Question
Replies: 4
Views: 1274

Re: Oliver 75 - 46th Question

You should not be too much worried about 3 point estimates , the important thing is critical chain method in the option, its used when resources are scarce, critical path method is not effective when resources are scarce 3 point estimates is anyways good and there is already mention in question that...
by manishpn
Thu May 18, 2017 5:35 pm
Forum: PMP® Exam Lessons – Success Stories
Topic: Passed PMP Test
Replies: 2
Views: 405

Re: Passed PMP Test

Congratulations and do share your journey and experience in exam that will help other students
by manishpn
Wed May 17, 2017 8:34 am
Forum: PMP® Open Forum
Topic: Confidence Level
Replies: 4
Views: 338

Re: Confidence Level

Hi, Critical path of the project has 3 activities in sequence . Activity A has optimistic estimate as 8,pessimistic as 16 and most likely as 12.Activity B has optimistic estimate as5,Pessimistic estimates as15 and most likely estimate as 0.Activity C has optimistic estimate as 10,pessismistic estim...
by manishpn
Sun May 14, 2017 8:51 am
Forum: PMP® Open Forum
Topic: how to access scordo pmp exa prep questions
Replies: 1
Views: 173

Re: how to access scordo pmp exa prep questions

Hi Rajat,

Kindly write email to Support@izenbridge.com
by manishpn
Fri May 12, 2017 3:29 pm
Forum: PMP® Open Forum
Topic: Can someone help on this
Replies: 7
Views: 460

Re: Can someone help on this

yes you are correct
by manishpn
Wed May 10, 2017 5:50 pm
Forum: PMP® Mock Exams Open Questions
Topic: Rita - Quality Question
Replies: 3
Views: 351

Re: Rita - Quality Question

A project has faced major difficulties in the quality of its deliverables. Management now states that quality is the most important project constraint. If another problem with quality were to occur, what would be the BEST thing for the project manager to do? A. Fixed the problem as soon as possible...
by manishpn
Wed May 10, 2017 4:16 pm
Forum: PMP® Queries and Tips
Topic: Perform Integrated Change Control
Replies: 7
Views: 737

Re: Perform Integrated Change Control

I would say that application area will have least impact on way changes are controlled from the options provided,
by manishpn
Wed May 10, 2017 4:09 pm
Forum: PMP® Queries and Tips
Topic: Who provide Resource for a Project
Replies: 5
Views: 518

Re: Who provide Resource for a Project

Hi, I came through below question in a quiz- Who provides Resources for a Project A. Project Manager B. Sponsor C. Stakeholder D. Project Team I my opinion, it should be Project Manager who has authority to provide the resources for a project PM is responsible to ramp up team and other resources fo...
by manishpn
Wed May 10, 2017 4:08 pm
Forum: PMP® Queries and Tips
Topic: 100 % rule
Replies: 3
Views: 358

Re: 100 % rule

ok but 100% rule is very important to understand :)
by manishpn
Wed May 10, 2017 4:07 pm
Forum: PMP® Queries and Tips
Topic: decision tree analysis
Replies: 3
Views: 445

Re: decision tree analysis

I would go with option A, As decision tree analysis is primarily used to understand the impact of scenarios that are known
by manishpn
Wed May 10, 2017 3:35 pm
Forum: PMP® Queries and Tips
Topic: your cousion is one of three short listed candidates
Replies: 5
Views: 425

Re: your cousion is one of three short listed candidates

good point but I still think its too early to inform your boss
by manishpn
Wed May 10, 2017 3:31 pm
Forum: PMP® Queries and Tips
Topic: Scope question from rita fast trak v8
Replies: 3
Views: 243

Re: Scope question from rita fast trak v8

I dont think option #4 is right
by manishpn
Wed May 10, 2017 3:29 pm
Forum: PMP® Queries and Tips
Topic: EVM Question
Replies: 5
Views: 729

Re: EVM Question

narayanankuttytp wrote:Hi

I need help for that question, How we got the AC,EV,
PV

That information is already provided in the question,

What help you need in specific?
by manishpn
Wed May 10, 2017 3:28 pm
Forum: PMP® Open Forum
Topic: Can someone help on this
Replies: 7
Views: 460

Re: Can someone help on this

nazrulq wrote:10% time increased = 11 months =EV
10% cost increased = 250 000 * 1.1 =275 000 =AC
SPI =10/11=.91
CPI =250/275=.91



please read question carefully
Calculate CPI and SPI at the time of project completion.

Now think and answer
by manishpn
Tue May 09, 2017 7:56 am
Forum: PMP® Open Forum
Topic: PMBOK DIAGRAM 5-10 AND 5-14 KINDLY EXPLAIN
Replies: 2
Views: 196

Re: PMBOK DIAGRAM 5-10 AND 5-14 KINDLY EXPLAIN

Great.
PMBOK sometimes has explicit inputs and sometimes the required inputs are part of PMP.

So if you look carefully you will be able to get your answers within the book.
by manishpn
Fri May 05, 2017 9:38 am
Forum: PMP® Queries and Tips
Topic: Rules for performance measurement
Replies: 1
Views: 216

Re: Rules for performance measurement

"One of the rule for Performance measurement There are multiple ways a project can measure the completion of work/earned value. Which rules the project will use has to be specified in the project management plan. for e.g. when do you consider an activity has earned value, it could be x% of ear...
by manishpn
Fri May 05, 2017 7:25 am
Forum: PMP® Open Forum
Topic: Can someone help on this
Replies: 7
Views: 460

Re: Can someone help on this

please try to attempt this question with your own understanding and we can discuss .
for all match and other calculations you should attempt (thats the best way to learn) rather than getting answers/
by manishpn
Fri May 05, 2017 7:16 am
Forum: PMP® Queries and Tips
Topic: Business case in Phase 2 of Project
Replies: 1
Views: 160

Re: Business case in Phase 2 of Project

when Project has to start with next phase it has to consider if the original business case is still valid or not. This is critical (especially for big projects) where business case validity is key before moving on an executing remaining phases within the project. looks at some of the previous thread...
by manishpn
Wed May 03, 2017 7:32 pm
Forum: PMP® Mock Exams Open Questions
Topic: cost of quality questions
Replies: 4
Views: 338

Re: cost of quality questions

Hi....going by the defect logic 'C' seems correct to me too. ....and that also conforms to Fig 8.2 of PMBOK. But , my question was more regarding the 'D' part pf the PDCA cycle where DO lies in executing process as per Fig 8.2 of PMBOK...also the arrow from the inspection box points towards conform...
by manishpn
Wed May 03, 2017 4:52 pm
Forum: PMP® Open Forum
Topic: Rita - Risk Quality Question
Replies: 2
Views: 202

Re: Rita - Risk Quality Question

You are finding it difficult to evaluate the exact cost impact of risks. You should evaluate on a(n): A. Quantitative basis B. Numerical basis C. Qualitative basis D. Economic basis I have chosen A, but the answer is C this question is play of words. The question mentions that PM is finding it diff...
by manishpn
Wed May 03, 2017 4:41 pm
Forum: PMP® Exam Lessons – Success Stories
Topic: Milestone achieved - PMP Pass
Replies: 3
Views: 401

Re: Milestone achieved - PMP Pass

congratulations and thanks for choosing izenbridge.
Do share you experience and journey for benefit of others.
by manishpn
Tue May 02, 2017 8:36 am
Forum: PMP® Mock Exams Open Questions
Topic: Rita - Quality Question
Replies: 3
Views: 309

Re: Rita - Quality Question

I agree this is a very confusing question and I would not go with option B, since work packages are complete, it is implied that quality needs are taken care in that. there is no clear option to choose from and explanation provided in rita is also not convincing. the starting statement that Work pac...
by manishpn
Mon May 01, 2017 3:26 pm
Forum: PMP® Open Forum
Topic: how to access scordo questions from pmi site
Replies: 3
Views: 303

Re: how to access scordo questions from pmi site

I dont think its available for member for free anymore, not 100% sure though
by manishpn
Mon May 01, 2017 3:23 pm
Forum: PMP® Exam Lessons – Success Stories
Topic: cleared PMP exam in first attempt on 28th Apr
Replies: 2
Views: 394

Re: cleared PMP exam in first attempt on 28th Apr

this is good news.
congratulations on your success and wish you all the very best

thanks for choosing izenbridge and sharing your journey and experience.
by manishpn
Sat Apr 29, 2017 8:09 am
Forum: PMP® Open Forum
Topic: how to access scordo questions from pmi site
Replies: 3
Views: 303

Re: how to access scordo questions from pmi site

please email to support@izenbridge.com if you are our paid member