chennai Banner

Search found 1425 matches

by manishpn
Fri Jul 28, 2017 1:39 pm
Forum: PMP® Open Forum
Topic: Level of Effort
Replies: 1
Views: 14

Re: Level of Effort

this video of saket can help.

https://www.youtube.com/watch?v=vBlCmVw6OZ4

for types of effort start from time 34:00
also there is a blog on izenbridge on effort types

https://www.izenbridge.com/blog/introdu ... d-efforts/
by manishpn
Fri Jul 28, 2017 1:35 pm
Forum: PMP® Open Forum
Topic: Cost Management Practice
Replies: 2
Views: 8

Re: Cost Management Practice

Agree with Kapil.

ETC on a given date is the money (cost) that is needed to complete the project from this date
EAC is the total cost (from the start of project) that the project will incur till completion
by manishpn
Fri Jul 28, 2017 1:33 pm
Forum: PMP® Open Forum
Topic: Process Group wise
Replies: 2
Views: 18

Re: Process Group wise

Hi All, I am planning to take my PMP exam mid of next month, as per the learning plan from Izenbridge, I am at now "Master" stage, watching videos and parallelly reading PMBOK and Rita too. Due to my work, personal schedule and the key is my PMP exam overdue is going to end of October, I ...
by manishpn
Thu Jul 27, 2017 10:54 am
Forum: PMP® Open Forum
Topic: Discounted Cash Flow
Replies: 1
Views: 31

Re: Discounted Cash Flow

by manishpn
Tue Jul 25, 2017 2:40 pm
Forum: PMP® Open Forum
Topic: Flow Chart
Replies: 2
Views: 49

Re: Flow Chart

kindly look at sakets video on quampus, chapter 5 lesson #4, this shud help you create a flow.

let us know
by manishpn
Tue Jul 25, 2017 2:35 pm
Forum: PMP® Open Forum
Topic: Conflict Management
Replies: 1
Views: 35

Re: Conflict Management

Main causes in conflict according to the order 1. Schedule 2. Priorities 3.Manpower 4.Technical 5.Procedure 6. Personalities 7.Cost. According to Rita Mulchay cost is before personalities but other source said least conflict cause is Cost. Do not worry much PMP does not ask u to memorize. Most reco...
by manishpn
Mon Jul 24, 2017 3:30 pm
Forum: PMP® Exam Lessons – Success Stories
Topic: Passed PMP Today !!
Replies: 4
Views: 136

Re: Passed PMP Today !!

congratulations, kindly share your experience and journey for benefit of others
by manishpn
Mon Jul 24, 2017 12:20 pm
Forum: PMP® Open Forum
Topic: Special cause/ Assignable Cause (Quality)
Replies: 1
Views: 41

Re: Special cause/ Assignable Cause (Quality)

When Data point or points are out side any control limit even on specification limit range. That is called a Special cause. Special/assignable cause is when the process is out of control and an action has to be taken to bring it back in control process can be out of control in case there is a data ...
by manishpn
Mon Jul 24, 2017 12:01 pm
Forum: PMP® Open Forum
Topic: Quality/Risk
Replies: 2
Views: 37

Re: Quality/Risk

PMBOK does not prescribe any specific sequence, moreover quality planning is done in planning phase where we identify quality standard and requirements and this need is included in WBS, also the question mentions that we are in project execution phase and hence I will also pick option #1. Do you hav...
by manishpn
Mon Jul 24, 2017 11:55 am
Forum: PMP® Queries and Tips
Topic: questions from project scope manangement
Replies: 3
Views: 58

Re: questions from project scope manangement

aparna2017 wrote:thanks manish

could you please share video link for requirement collection techniques

It should be included in learning material videos from izenbridge available on quampus, don recall exact name

by manishpn
Mon Jul 24, 2017 11:51 am
Forum: PMP® Queries and Tips
Topic: Queries from project Frame work
Replies: 6
Views: 78

Re: Queries from project Frame work

Hi Saket I raised this question as i could not get c;lear picture while answering to the assessment questiions A drug manufacturing organization has several R &D projects running across the organization. Many of these projects are run from multiple locations while some of them are run in tight ...
by manishpn
Mon Jul 24, 2017 11:48 am
Forum: PMP® Queries and Tips
Topic: Queries from project Frame work
Replies: 6
Views: 78

Re: Queries from project Frame work

1. what is difference between Project coordinator and expeditor?why we have two roles? In weak matrix organization there can be 2 roles ( PMBOK collects data from what is observes from industry so we should not really worry why we have 2 roles rather understand them) Simple way to remember - There ...
by manishpn
Sun Jul 23, 2017 7:37 pm
Forum: PMP® Queries and Tips
Topic: questions from project scope manangement
Replies: 3
Views: 58

Re: questions from project scope manangement

Please help in suggesting key word to distinguish Validation and verification this video may help https://www.youtube.com/watch?v=2dliqro66Ew Which of the following describes the evaluation of whether or not a product, service, or system complies with a regulation, requirement, specification, or im...
by manishpn
Sun Jul 23, 2017 11:31 am
Forum: PMP® Open Forum
Topic: Time Management Practice
Replies: 5
Views: 57

Re: Time Management Practice

hi komal draw your plan and upload the picture here this way it is easy to learn
by manishpn
Sun Jul 23, 2017 9:28 am
Forum: PMP® Queries and Tips
Topic: PMP Exam Preparation -26th July 2017
Replies: 3
Views: 155

Re: PMP Exam Preparation -26th July 2017

Dear Manish Good morning. Thank you for the time yesterday over the webinar. I have postponed by exam to 2nd August as I have not prepared enough at this time. However my plan would be still the same as per my earlier post. In view of time limitations, I have some uncompleted questions from VMEdu c...
by manishpn
Sun Jul 23, 2017 9:25 am
Forum: PMP® Open Forum
Topic: Customers Validation
Replies: 1
Views: 33

Re: Customers Validation

Question A customer has given you a contract statement of work for a complex , eight month project that has a few unknowns. The customer has asked you to just "get it done" & only wants to see you at the end of eight months when you deliver the final project. Which of the following is...
by manishpn
Sat Jul 22, 2017 11:54 am
Forum: PMP® Open Forum
Topic: Regarding PMP experience filling in application
Replies: 1
Views: 36

Re: Regarding PMP experience filling in application

try our calculator to check your eligibility

https://www.izenbridge.com/pmp/eligibilitycalculator/


if you are eligible you can write for support@izenbridge.com for help with application
by manishpn
Sat Jul 22, 2017 11:35 am
Forum: PMP® Open Forum
Topic: Range of Estimates
Replies: 2
Views: 46

Re: Range of Estimates

Rough order of Estimate went down from -25 % - 75% to new Definitive estimate -10% - + 10%. Old Budgeted Range was $3M to $5M . What could be the new range while using definitive estimate. Answer : Calculate the Mean = (3+5) x .5 = $4M New Range = .9x4 = $3.6 M and 1.1 x 4 = $4.4 New Range $3.6M to...
by manishpn
Sat Jul 22, 2017 11:32 am
Forum: PMP® Open Forum
Topic: Expert Judgement
Replies: 1
Views: 35

Re: Expert Judgement

usually PM has to be careful approaching any competition as this may potentially spill sensitive information about the project. I have never in my life taken an expert advice from competition :) so it would be rare situation where a competition is approached for advice, for e.g. in some countries ba...
by manishpn
Sat Jul 22, 2017 11:27 am
Forum: PMP® Open Forum
Topic: Contract Award
Replies: 1
Views: 25

Re: Contract Award

When Contract is awarded by Procurement Department and Procurement Manager along with Contract Administrator is responsible awarding contract though Project Manager's participation is sometimes required. But who will finally sign off for the contract from buyer side.Project Sponsor's involvement as...
by manishpn
Sat Jul 22, 2017 10:09 am
Forum: PMP® Open Forum
Topic: Pareto Chart
Replies: 1
Views: 25

Re: Pareto Chart

Pareto Principle does not demand that the 80:20 ratio applies to every situation, and neither is the model based on a ratio in which the two figures must add up to 100. So the examples used here are not statistical facts; the 80-20 ratio is used to show that the Pareto distribution principle can be ...
by manishpn
Sat Jul 22, 2017 10:00 am
Forum: PMP® Open Forum
Topic: Project Selection Method
Replies: 1
Views: 28

Re: Project Selection Method

Which of the following project selection methods is not a comparative approach (or benefit measurement model)? A Linear programming this method is contraint optimization method, refer to thread http://forum.izenbridge.com/viewtopic.php?f=10&t=1901&p=6967&hilit=Linear+programming#p6967 C...
by manishpn
Sat Jul 22, 2017 9:43 am
Forum: PMP® Open Forum
Topic: Ethics Question
Replies: 3
Views: 39

Re: Ethics Question

As I said question is not of good quality but understand that option #3 is only an option if situation in question mentions that PM is lacking experience to many any decisions due to lack of experience,
by manishpn
Sat Jul 22, 2017 9:32 am
Forum: PMP® Open Forum
Topic: Stakeholders Engagement
Replies: 1
Views: 82

Re: Stakeholders Engagement

One stakeholder comes to you and asks why this project is delayed? You explain that we are proceeding as per schedule, but he shows you the project charter and dates given in project charter is already passed by, what is wrong here? 1.Project Manager is not taking care of commitments made in projec...
by manishpn
Fri Jul 21, 2017 6:27 pm
Forum: PMP® Queries and Tips
Topic: PMP Exam Preparation -26th July 2017
Replies: 3
Views: 155

Re: PMP Exam Preparation -26th July 2017

Dear All I would be sitting for my PMP exam on the 26th July 2017. I have just concluded my knowledge area quiz and would be attempting the following, Sorry for the late response as i was on vacation. 1. Run Thorough quickly each knowledge area again through the slides/PMBOK where applicable and at...
by manishpn
Fri Jul 21, 2017 5:05 pm
Forum: PMP® Open Forum
Topic: Ethics Question
Replies: 3
Views: 39

Re: Ethics Question

Question: Project Manager has given high authority to take decisions but in project decision he has lack of experience. In this regards, what project manager has to do: 1. Take decision even though he has lack of experience. 2. Seek for Expert Judgement 3. Inform the higher management about his lac...
by manishpn
Fri Jul 21, 2017 4:56 pm
Forum: PMP® Open Forum
Topic: Stakeholder Engagement
Replies: 1
Views: 49

Re: Stakeholder Engagement

Question Rob, is Project Manager for a Satellite development program which runs for 4 years and it has been decided to split it in logical phases to make it more manageable. There is a cost cutting initiative in his organization and Rob finally got his budget approved from Martin (his sponsor) afte...
by manishpn
Fri Jul 21, 2017 4:54 pm
Forum: PMP® Open Forum
Topic: Estimation Techniques
Replies: 1
Views: 25

Re: Estimation Techniques

How we can decide estimation techniques based on project execution in specific industry? Means how to decide technique for software project or construction ? Estimation technique are usually not dependent on which industry is project been executed. but based on how much knowledge Project has from p...
by manishpn
Fri Jul 21, 2017 4:41 pm
Forum: PMP® Open Forum
Topic: PMP APPLICATION 4500 HOURS
Replies: 2
Views: 66

Re: PMP APPLICATION 4500 HOURS

by manishpn
Fri Jul 21, 2017 4:40 pm
Forum: PMP® Open Forum
Topic: Exam Question
Replies: 3
Views: 58

Re: Exam Question

yes you can get such questions in exam ,
by manishpn
Tue Jul 11, 2017 2:41 pm
Forum: PMP® Queries and Tips
Topic: Sponsoring entity
Replies: 1
Views: 121

Re: Sponsoring entity

The project charter should be authored by the sponsoring entity. (PMBOK 5E, pg-67) If our organization’s portfolio manager received SoW & agreement from a buyer organization's procurement dept, then who is the Sponsoring entity? BR// Jahirul Not sure about your question. if someone receives SOW...
by manishpn
Tue Jul 11, 2017 2:39 pm
Forum: PMP® Open Forum
Topic: Practiced Conflict Resolution System
Replies: 2
Views: 108

Re: Practiced Conflict Resolution System

I dont think there is any recommendation or statistics collected to support this, however if i go with elimination then option 1 and 2 are eliminated as it has force.

from 3 and 4. I will prefer 4, as Authoritative is not a conflict resolution technique
by manishpn
Tue Jul 11, 2017 2:32 pm
Forum: PMP® Open Forum
Topic: Close Project
Replies: 1
Views: 88

Re: Close Project

I have explained in this in clarification session, some of the team members can be released at the start of project closure. however final step would be to release the remaining team from project
by manishpn
Tue Jul 11, 2017 2:30 pm
Forum: PMP® Open Forum
Topic: Human Resource Management
Replies: 1
Views: 65

Re: Human Resource Management

Except for personal matters, PM can delegate all other tasks , especially in large projects,

I would not waste my time on such questions
by manishpn
Tue Jul 11, 2017 2:26 pm
Forum: PMP® Open Forum
Topic: Expected Monetary value
Replies: 2
Views: 90

Re: Expected Monetary value

we encourage the students to do the math by yourself and lets than discuss.

If you get ready answer for maths you will not be able to learn
by manishpn
Tue Jul 11, 2017 2:11 pm
Forum: PMP® Exam Lessons – Success Stories
Topic: Passed PMP - First attempt - 3P & 2 MP
Replies: 2
Views: 340

Re: Passed PMP - First attempt - 3P & 2 MP

Congratulations, and thanks for providing your feedback, we will work on your suggestions
by manishpn
Tue Jul 11, 2017 2:08 pm
Forum: PMP® Exam Lessons – Success Stories
Topic: Passed PMP
Replies: 2
Views: 152

Re: Passed PMP

congratulations and wish you all the best
by manishpn
Sun Jul 09, 2017 12:30 pm
Forum: PMP® Open Forum
Topic: Scope
Replies: 3
Views: 88

Re: Scope

In construction project, PM is creating documents that will define the product or report status on product completion. These can also be referred to as: 1 Project documents 2 Project management plan 3 Scope baseline 4 Scope management plan Correct Answer 1. My Answer is option 4. Can somebody Ellua...
by manishpn
Sun Jul 09, 2017 12:19 pm
Forum: PMP® Open Forum
Topic: Ethical Question
Replies: 6
Views: 161

Re: Ethical Question

YOu need to understand that Project management is industry agnostic skill. which means a project manager is not certified to work only in construction or IT When you get certified by PMI its for project management across board. Remember this for Exam. So for given question option #3 is best as if yo...
by manishpn
Sun Jul 09, 2017 12:16 pm
Forum: PMP® Open Forum
Topic: Reg output of Plan Communications Management
Replies: 2
Views: 82

Re: Reg output of Plan Communications Management

Yes I agree with Dsharma, When project develops CMP, there can be additional requirements on project on the way and means of communications. For example , if there is a requirement for video conference calling , then team needs to set it up which may need time also note that even resource requiremen...
by manishpn
Thu Jul 06, 2017 7:11 pm
Forum: PMP® Open Forum
Topic: Control Schedule
Replies: 4
Views: 140

Re: Control Schedule

kapil.bhauryal wrote:I will go with Option 3. Project manager takes the anticipated changes through the change control process.


I agree with Kapil.

please refer to Pag 186 in PMBOK.
by manishpn
Thu Jul 06, 2017 5:53 pm
Forum: PMP® Open Forum
Topic: Project Status updates
Replies: 2
Views: 90

Re: Project Status updates

Question :Your project is in the execution stage. NPV of your project is -$150,000 and IRR is 4%. CPI is 1.3 and SPI is 0.7 What is the recommended action? 1 Cancel the project since NPV is negative 2 Cancel the project since IRR is very low 3 Crash your project 4 Try to improve the NPV as far as m...
by manishpn
Wed Jul 05, 2017 5:00 pm
Forum: PMP® Open Forum
Topic: Quality
Replies: 6
Views: 138

Re: Quality

Question : Which of the following statements about "Quality" and "Grade" is correct? A. Grade is a rank given to entities having the same functional use but different technical characteristics. B. Low quality product may be of high grade. C. Low grade product may be of high qual...
by manishpn
Wed Jul 05, 2017 4:51 pm
Forum: PMP® Open Forum
Topic: Quality
Replies: 6
Views: 138

Re: Quality

VCAB wrote:Can question like this come the exam!!!!!

Usually not in the same format but a situation can come which can challenge your knowledge about quality and Grade
by manishpn
Wed Jul 05, 2017 5:25 am
Forum: PMP® Open Forum
Topic: Similiarity IT/Construction Project Management
Replies: 2
Views: 88

Re: Similiarity IT/Construction Project Management

You are a project manager in an IT company. You have recently received an offer as a project manager in a construction company offering a 20% salary increase. You have excellent technical knowledge in the IT field, but do not have much exposure to the construction industry. In this context, 1 You s...
by manishpn
Mon Jul 03, 2017 11:51 am
Forum: PMP® Open Forum
Topic: Project Closure
Replies: 2
Views: 99

Re: Project Closure

I would agree with Kapil.

As far as contract scope is completed and all obligations fulfilled PM should move for contract closure.
by manishpn
Sat Jul 01, 2017 7:45 am
Forum: PMP® Open Forum
Topic: Project Status
Replies: 2
Views: 115

Re: Project Status

In the home construction project, the CPI is 0.80 and SPI are 1.2. What could be the best possible reason? 1 A critical resource went on sick leave for a long period of time, which had not been anticipated earlier. 2 The cost of raw materials required for construction increased by 15%. You had anti...
by manishpn
Thu Jun 29, 2017 9:29 am
Forum: PMP® Mock Exams Open Questions
Topic: Avoiding Vs Mitigating Risk
Replies: 6
Views: 385

Re: Avoiding Vs Mitigating Risk

based on the information provided its difficult to conclude for sure but my impression is that adding resource to project is a risk mitigation as, its only going to reduce the probability or impact of risk not eliminate it, Risk avoidance is on other hand actions taken by project to eliminate risk t...
by manishpn
Thu Jun 29, 2017 9:14 am
Forum: PMP® Open Forum
Topic: PMI Code of Ethics
Replies: 2
Views: 104

Re: PMI Code of Ethics

The Project Manager is discussing her project with a close friend and colleague in the same company. She is worried that your project is behind schedule and over budget. Her(PM) colleague explained how she was able to bring her project back on schedule by taking out some non-critical tasks from the...
by manishpn
Thu Jun 29, 2017 8:43 am
Forum: PMP® Open Forum
Topic: Project Network Diagram
Replies: 1
Views: 78

Re: Project Network Diagram

i would request you to draw your own SND take a picture and upload it, then we can discuss

Go to advanced search