CSM Forum Banner

Search found 1576 matches

by manishpn
Thu Nov 23, 2017 4:16 pm
Forum: PMP® Exam Lessons – Success Stories
Topic: Finaly achieved my PMP milestone 22-Nov 17, 4 Above Target and Closing Target.
Replies: 2
Views: 18

Re: Finaly achieved my PMP milestone 22-Nov 17, 4 Above Target and Closing Target.

Congratulations and thankyou for choosing izenbridge and sharing your experience which will benefit others
by manishpn
Wed Nov 22, 2017 8:01 pm
Forum: PMP® Open Forum
Topic: Close Project
Replies: 4
Views: 252

Re: Close Project

from where did you got this chronological order?
by manishpn
Wed Nov 22, 2017 7:59 pm
Forum: PMP® Open Forum
Topic: Saket - Risk Doubt
Replies: 4
Views: 556

Re: Saket - Risk Doubt

Dear Saket, Risk Management is an iterative process. Throughout the project we do periodic Risk Reassessment and try to identify New Risks. Thats correct So While doing Risk Reassessment the PM finds a previously Unidentified Risk, means a New Risk. So if he is given following 2 options what should...
by manishpn
Wed Nov 22, 2017 7:56 pm
Forum: PMP® Open Forum
Topic: Quick Data Required as per PMBOK5
Replies: 2
Views: 27

Re: Quick Data Required as per PMBOK5

Do anyone from Izenbridge has quick summary data on below . Data is available in PMBOK5 however needs to meander through multiple pages. i cannot understand your query 1. There are no notes on Cost, Communication and RIsk plan in PMBOK5... Is these plans needs to be highly detailed or as per need o...
by manishpn
Wed Nov 22, 2017 7:51 pm
Forum: PMP® Open Forum
Topic: Project Report And Project Record
Replies: 1
Views: 23

Re: Project Report And Project Record

Project file, Project records, Project closure docs, Historical info What is the relation among above docs? I know they are part of OPA. But are they subsets of each other? Project closure docs are usually like project documents while the project is still running They are all then filed as project ...
by manishpn
Wed Nov 22, 2017 7:46 pm
Forum: PMP® Open Forum
Topic: stakeholder 2
Replies: 1
Views: 8

Re: stakeholder 2

poor quality question and explanation provided is even worse, dont spend time on it
by manishpn
Sun Nov 19, 2017 5:32 pm
Forum: iZenBridge PMP Open Questions
Topic: Project Closure
Replies: 6
Views: 191

Re: Project Closure

there is no prescribed order, however releasing the team should be last option, PM can release some of the team in gradual manner but the cannot release entire team before lesssons learnt is complete.
by manishpn
Sat Nov 18, 2017 5:39 pm
Forum: iZenBridge PMP Open Questions
Topic: Situational Question
Replies: 5
Views: 149

Re: Situational Question

But this issue is not impacting project scope,cost and Time. Why do you assume that CR is needed only if it impacts baseline? Do not assume. Also when in doubt try to use elimination technque A) Inform immediately to client - This is not needed as informing client is only needed if there is some ma...
by manishpn
Thu Nov 16, 2017 8:11 pm
Forum: PMP® Queries and Tips
Topic: PMP Standard
Replies: 1
Views: 95

Re: PMP Standard

did not understand your question
by manishpn
Mon Nov 13, 2017 9:32 pm
Forum: PMP® Open Forum
Topic: procurement Q/A 2
Replies: 1
Views: 59

Re: procurement Q/A 2

the wording of this question is not good , it creates confusion ,

Of course if contract is T and M that will be biggest concern for the PM,
the contract type is not defined well in the process, so option C cant be true if its FP project where scope and cost are agreed in advance,
by manishpn
Mon Nov 13, 2017 9:19 pm
Forum: PMP® Open Forum
Topic: Procurement Q&A 1
Replies: 1
Views: 53

Re: Procurement Q&A 1

If I had to choose one for elimination I would choose risk log, however your reasoning is right and besides risk log can be in some of the contracts as well
by manishpn
Mon Nov 13, 2017 8:55 pm
Forum: PMP® Open Forum
Topic: Output of Perform Integrated Change Control Process
Replies: 2
Views: 77

Re: Output of Perform Integrated Change Control Process

yes its mistake/overlook good catch
by manishpn
Mon Nov 13, 2017 8:47 pm
Forum: PMP® Queries and Tips
Topic: Access to PMP forums)exclusive section)
Replies: 1
Views: 54

Re: Access to PMP forums)exclusive section)

email to support@izenbridge.com, they can help you.
by manishpn
Sun Nov 12, 2017 9:43 am
Forum: PMP® Open Forum
Topic: how to study/remember ITTO
Replies: 1
Views: 153

Re: how to study/remember ITTO

by manishpn
Wed Nov 08, 2017 6:41 pm
Forum: PMP® Open Forum
Topic: Projet manager influencing factors causing change
Replies: 7
Views: 221

Re: Projet manager influencing factors causing change

I am getting confused on two conflicting points in monitoring and control , below are the points: 1) PM should influence factors causing change 2) PM should control changes and impacts of the changes Why would a PM influence change, it will lead to changes to so many other KAs ? how can you control...
by manishpn
Wed Nov 08, 2017 6:17 pm
Forum: iZenBridge PMP Open Questions
Topic: Time managment
Replies: 2
Views: 130

Re: Time managment

Management informed the project manager that some of the resource assigned to the project would be transferred to another project within the next week,how should the project manager proceed? 1.Fast track the project 2.Issue a change request 3.Try to redo the plan without the resources,and document ...
by manishpn
Sun Nov 05, 2017 2:36 pm
Forum: PMP® Open Forum
Topic: Projet manager influencing factors causing change
Replies: 7
Views: 221

Re: Projet manager influencing factors causing change

yes i just wanted to know which book is referred to so I can set the context right
by manishpn
Sun Nov 05, 2017 11:01 am
Forum: PMP® Mock Exams Open Questions
Topic: Project Cost Management Mock Test
Replies: 2
Views: 387

Re: Project Cost Management Mock Test

yes thats correct
ev = 90% of 2000000
pv = 2000000
by manishpn
Sun Nov 05, 2017 10:59 am
Forum: PMP® Open Forum
Topic: Projet manager influencing factors causing change
Replies: 7
Views: 221

Re: Projet manager influencing factors causing change

which book are you referring to ?
by manishpn
Sun Nov 05, 2017 10:50 am
Forum: iZenBridge PMP Open Questions
Topic: Question on 47 Processes
Replies: 1
Views: 144

Re: Question on 47 Processes

except for some formula no need to memorize anything for PMP need to understand the logic
read this blog

https://www.izenbridge.com/blog/pmp-itto/
by manishpn
Sun Nov 05, 2017 9:09 am
Forum: PMP® Queries and Tips
Topic: Rita Book conflict on Definition as compared to PMBOK
Replies: 4
Views: 179

Re: Rita Book conflict on Definition as compared to PMBOK

go with PMBOK,
simple to remember:

corrective is reactive approach
preventive is proactive approach
by manishpn
Tue Oct 31, 2017 3:55 pm
Forum: PMP® Open Forum
Topic: Earned Value Management (EVM)
Replies: 2
Views: 155

Re: Earned Value Management (EVM)

its an overlook , good catch
Cost is key component in EVM calculations
by manishpn
Tue Oct 31, 2017 12:36 pm
Forum: PMP® Queries and Tips
Topic: Activity Cost Estimates
Replies: 1
Views: 101

Re: Activity Cost Estimates

usually at the activity level we do not add indirect/Fixed cost as its practically difficult to associate such costs to an activity.

However project may have guidelines on how to split indirect cost across different activities,
by manishpn
Tue Oct 31, 2017 12:28 pm
Forum: iZenBridge PMP Open Questions
Topic: Project Closure
Replies: 6
Views: 191

Re: Project Closure

this is not a good quality question, we do not not know if the deliverable were accepted, completed does not necessarily means its accepted If I assume ALL deliverables are accepted then we are in CLOSE Project phase and then it makes sense to update final lessons learnt before releasing team member...
by manishpn
Wed Oct 25, 2017 3:34 pm
Forum: PMP® Open Forum
Topic: Stakeholder Role
Replies: 1
Views: 99

Re: Stakeholder Role

The role of each stakeholder is determined by whom? The stakeholder and the sponsor The project manager and the sponsor The team and the project manager The project manager and the stakeholder Stakeholder provide requirement and have positive and negative influence. How to determine role of stakeho...
by manishpn
Wed Oct 25, 2017 3:16 pm
Forum: PMP® Open Forum
Topic: Gold Plating
Replies: 1
Views: 103

Re: Gold Plating

The Project Manager determines at the end of the project that five additional functionalities and two areas of performance have been added to the project. The client has expressed satisfaction with the project. What does this mean in the terms of success of the project? The Project was a big succes...
by manishpn
Wed Oct 25, 2017 3:10 pm
Forum: PMP® Open Forum
Topic: PMP Mock Test
Replies: 1
Views: 93

Re: PMP Mock Test

Its a good question and is a bit deep in Statistical area. I am not an expert in this area and cant really comment on it confidently confidence level can be understood that how confident PM wants to be that the actual mean falls within PM confidence interval? confidence level can be 90%, 95% and 98%...
by manishpn
Sat Oct 21, 2017 7:36 pm
Forum: PMP® Open Forum
Topic: Change Control
Replies: 8
Views: 334

Re: Change Control

If i had to choose I will choose option C since the defect is not in deliverable, however as I said its difficult to choose
by manishpn
Sat Oct 21, 2017 7:35 pm
Forum: PMP® Open Forum
Topic: Q&A HR 1
Replies: 4
Views: 171

Re: Q&A HR 1

I agree,
it would be good to know reasoning behind option B, what explanation is provided?
by manishpn
Fri Oct 20, 2017 5:59 am
Forum: PMP® Open Forum
Topic: Change Control
Replies: 8
Views: 334

Re: Change Control

a. Corrective action:-Corrective action is after prevention. Prevention is already take as machine wear and tear happened before expected time. b. Defect repair:- defect of product not produced yet thus ,it is not valid. 'order to replace the damaged parts of machinery', when a part of machine is d...
by manishpn
Thu Oct 19, 2017 4:50 pm
Forum: PMP® Open Forum
Topic: Change Control
Replies: 8
Views: 334

Re: Change Control

this one a thin line between defect repair and preventive.
'showing signs of wear and damage much earlier than expected' 'order to replace the damaged parts of machinery'

the above information makes me more inclined towards defect repair as an option
by manishpn
Tue Oct 17, 2017 7:42 pm
Forum: PMP® Open Forum
Topic: Whats the correct answer?
Replies: 8
Views: 432

Re: Whats the correct answer?

I provided my answer above it should be option #3
by manishpn
Tue Oct 17, 2017 7:36 pm
Forum: PMP® Open Forum
Topic: Workaround
Replies: 3
Views: 280

Re: Workaround

:)
by manishpn
Tue Oct 17, 2017 7:35 pm
Forum: PMP® Open Forum
Topic: Project Closure Documents
Replies: 3
Views: 180

Re: Project Closure Documents

Q. Project is near to completion, Project charter is the document which authorized the project in the beginning. The contractor has his own Project Charter to implement the project. Now customer needs to verify the project deliverables as mentioned in the project charter. To which document PM to re...
by manishpn
Tue Oct 17, 2017 7:27 pm
Forum: iZenBridge PMP Open Questions
Topic: Mock Test
Replies: 3
Views: 269

Re: Mock Test

Project management is an integrative undertaking that requires each ______________ and ___________ process to be appropriately aligned and connected with other processes to facilitate coordination. A . Process and knowledge areas B. Project and product C. Product and knowledge areas D. Phases and k...
by manishpn
Tue Oct 17, 2017 6:18 pm
Forum: iZenBridge PMP Open Questions
Topic: EVM question
Replies: 1
Views: 128

Re: EVM question

AC = 10 hours * 10 team Member *4 Days
= 400
by manishpn
Tue Oct 17, 2017 6:04 pm
Forum: PMP® Queries and Tips
Topic: Management reserve
Replies: 2
Views: 176

Re: Management reserve

Management reserve is not transparent to PM, so when you get approval to use Management reserve how much % of reserve is left is not known to PM and PM should not worry about it. usually Management reserve is not part of performance measurement so even if some Mgmnt reserve is approved when an unkno...
by manishpn
Sun Oct 15, 2017 8:23 am
Forum: PMP® Queries and Tips
Topic: To Complete Performance Index (TCPI)
Replies: 5
Views: 208

Re: To Complete Performance Index (TCPI)

Just use BAC for second as well, no need to calculate EAC as you do not know what type of variance it is.
by manishpn
Sat Oct 14, 2017 12:26 pm
Forum: PMP® Queries and Tips
Topic: To Complete Performance Index (TCPI)
Replies: 5
Views: 208

Re: To Complete Performance Index (TCPI)

cant really say without looking at the question

can you share which question are you referring to
by manishpn
Fri Oct 13, 2017 5:14 pm
Forum: PMP® Queries and Tips
Topic: To Complete Performance Index (TCPI)
Replies: 5
Views: 208

Re: To Complete Performance Index (TCPI)

you should always use EAC for TCPI calculation, ofcourse if your EAC is still equal to BAC then BAC can be used
by manishpn
Fri Oct 13, 2017 5:12 pm
Forum: PMP® Exam Lessons – Success Stories
Topic: Hurrah - Passed PMP Exam in first Attempt - Oct 6
Replies: 2
Views: 601

Re: Hurrah - Passed PMP Exam in first Attempt - Oct 6

Hi prem congratulations and thanks for sharing your experience, I am sure it will help others as well
by manishpn
Sun Oct 08, 2017 8:03 pm
Forum: PMP® Open Forum
Topic: Process Analysis vs Root cause Analysis
Replies: 2
Views: 196

Re: Process Analysis vs Root cause Analysis

Pg.247 of PMBOK...says process analysis includes root cause analysis-a specific technique used to identify a problem,discover underlying cause that lead to it and develop preventive action. Should I conclude that when u want to find root cause ..use Ishikawa and when analyse root cause use process A...
by manishpn
Sat Oct 07, 2017 6:28 pm
Forum: PMP® Open Forum
Topic: SPI=.8 CPI= 1 , Deliverables Status!
Replies: 2
Views: 185

Re: SPI=.8 CPI= 1 , Deliverables Status!

If SPI = .8 , CPI=1 and project is closed out in my understanding; all deliverables are not given but the project is on budget. If project is closed when SPI was 0.8, it means that all deliverable were not complete as EV was less than PV When EV and PV becomes equal i.e. when SPI =1 all deliverable...
by manishpn
Sat Oct 07, 2017 5:55 pm
Forum: iZenBridge PMP Open Questions
Topic: residual risk and secondary risk difference
Replies: 2
Views: 278

Re: residual risk and secondary risk difference

please refer to thread with discussion on this
viewtopic.php?f=11&t=5054&p=18761&hilit=residual+risk#p18758

there are many more discussions that have happened in this this regards on forum
by manishpn
Sat Oct 07, 2017 5:17 pm
Forum: PMP® Queries and Tips
Topic: Responsible and Accountable
Replies: 1
Views: 167

Re: Responsible and Accountable

Responsible: Responsible means the person(s) assigned is/are the ones to carry out and finish the task There can be more than one people responsible for an activity/task Accountable: Accountable means the person assigned is Accountability CANNOT be shared, meaning that there is only ONE individual ...
by manishpn
Wed Oct 04, 2017 5:06 pm
Forum: PMP® Open Forum
Topic: Whats the correct answer?
Replies: 8
Views: 432

Re: Whats the correct answer?

The question has little information to confidently point at an option, however my inclination is towards option #3 You are given charge of a new project by your senior managment.what is the best thing to do? 1.start planning - Before you start planning you need to know who are the critical stakehol...
by manishpn
Mon Oct 02, 2017 9:55 pm
Forum: PMP® Open Forum
Topic: Sponsor : most applicable responsibility
Replies: 7
Views: 308

Re: Sponsor : most applicable responsibility

What is the MOST applicable responsibility of a Project Sponsor? A.To ensure the project is within the budget, schedule, scope and quality standards - This is operation day to day tasks and is mainly PMS role B.To achieve the project objectives - This is primarily PM with help of Sponsor and other ...
by manishpn
Sat Sep 30, 2017 5:35 pm
Forum: Oliver 75 PMP Questions
Topic: Oliver 75 - 75th Question
Replies: 7
Views: 2904

Re: Oliver 75 - 75th Question

oliver mentions that Activity E is dangling activity which is also true and also option C is true I am also not sure why option C was ruled out. Activity F can start when activity E is 60% complete then no one really has dependency on when activity E will complete A dangle activity is a "loose&...
by manishpn
Tue Sep 26, 2017 4:38 pm
Forum: PMP® Open Forum
Topic: Initiating Process group Mock Test
Replies: 1
Views: 158

Re: Initiating Process group Mock Test

this question has been discussed before and Saket has answere it
refer to thread below

viewtopic.php?f=11&t=307&p=956&hilit=3000+MW#p956

Go to advanced search