Sat May 12, 2018 4:55 pm
Forum: PMP® Queries and Tips
Topic: Schedule Mgmt
Replies: 2
Views: 78

Re: Schedule Mgmt

not sure what is the question , post entire questions or refer to which section in rita is the question coming from
if you want to shorten the duration of the project, you should try to shorten the activities on CP.
by manishpn
Sat May 12, 2018 4:48 pm
Forum: PMP® Queries and Tips
Topic: Duration Estimates
Replies: 3
Views: 108

Re: Duration Estimates

PMBOK says ‘Duration estimates do not include any lags or leads however it may include some indication of the range of possible results. For example: A range of 2 weeks ± 2 days, which indicates that the activity will take at least 8 days and not more than 12 (assuming a 5-day work week); or A 15% ...
by manishpn
Sat May 12, 2018 4:42 pm
Forum: PMP® Queries and Tips
Topic: Quality Management
Replies: 1
Views: 44

Re: Quality Management

Can you please explain the below statement from Quality Management chapter (Rita) with an example- The costs of conformance should be lower than the costs of nonconformance. Thanks! its simple ensure that projects quality plan is good enough to ensure deliverable's are of required quality. so it wo...
by manishpn
Sat May 12, 2018 4:39 pm
Forum: PMP® Queries and Tips
Topic: Planning Process
Replies: 3
Views: 115

Re: Planning Process

Hi there, Please help me understand how come 'Change Request' is the output of below mentioned Planning Process Group processes - Define Activities Develop Schedule Plan Risk Responses Plan Procurement Mgmt. Thanks! When you look at any process in PMBOK, you need to understand and appreciate that t...
by manishpn
Sat May 12, 2018 4:22 pm
Forum: PMP® Queries and Tips
Topic: General query
Replies: 3
Views: 117

Re: General query

Input like ‘Enterprise environmental factor’ and T&T ‘Meetings’ have not been mentioned in the PMBOK for Implement risk response.Similarly, ‘Expert Judgement’ is not specifically mentioned in PMBOK 6 as T&T for Monitor Risk ITTO. We heard Saket mentioning in videos that EEF will be always t...
by manishpn
Fri May 11, 2018 10:09 am
Forum: PMP® Exam Lessons – Success Stories
Topic: I have achieved my PMP credentials(Sixth Edition) on 8th May in first attempt with overall Above Target.
Replies: 1
Views: 148

Re: I have achieved my PMP credentials(Sixth Edition) on 8th May in first attempt with overall Above Target.

Congratulations and thanks for detailed sharing of lessons learnt.
Can you tell us how many questions from Agile practice guide did you receive?
by manishpn
Fri May 11, 2018 10:06 am
Forum: PMP® Open Forum
Topic: Difference beween Risk Matrix, Risk Register & Risk Report
Replies: 2
Views: 399

Re: Difference beween Risk Matrix, Risk Register & Risk Report

We do not have a term called risk matrix in PMBOK, wrt risk KA we have Probability and impact matrix, as poonam described and also mentioned in PMBOK6 11.3.2.6 its a grid representation of the Impact and probability of each risk , that can help us get risk factor of each risk Risk Register can be te...
by manishpn
Fri May 11, 2018 9:55 am
Forum: PMP® Open Forum
Topic: Questions
Replies: 1
Views: 842

Re: Questions

what is the source, Faster response time can also be a benefit.
by manishpn
Thu May 10, 2018 10:26 am
Forum: PMP® Queries and Tips
Topic: Query
Replies: 1
Views: 116

Re: Query

by manishpn
Sun May 06, 2018 7:50 pm
Forum: PMP® Queries and Tips
Topic: Control Procurement : Difference between inspection, audit and procurement performance review
Replies: 1
Views: 143

Re: Control Procurement : Difference between inspection, audit and procurement performance review

Hello, Please let me know if my understanding is correct for following tools in control procurement Inspection - Is review of deliverable by seller. Usually checklist is prepared to do inspection., Inspection is T and T used in 3 different KA , as far as procurement is concerned its veryfying the d...
by manishpn
Thu May 03, 2018 6:09 am
Forum: PMP® Queries and Tips
Topic: do not find video for procurement strategy and procurement management plan in quampus
Replies: 2
Views: 554

Re: do not find video for procurement strategy and procurement management plan in quampus

it should be included in plan procurement management process , have you checked?
by manishpn
Mon Apr 23, 2018 5:21 pm
Forum: PMP® Open Forum
Topic: configuration management activities
Replies: 1
Views: 389

Re: configuration management activities

we have discussed it on February 17th, PMP Clarification and October 28th, PMP Clarification you can refer to recording also it has been discussed before http://forum.izenbridge.com/viewtopic.php?f=10&t=6014&p=22181&hilit=configuration+management#p22181 http://forum.izenbridge.com/viewto...
by manishpn
Mon Apr 23, 2018 5:12 pm
Forum: PMP® Open Forum
Topic: Creating wbs after project charter development
Replies: 4
Views: 335

Re: Creating wbs after project charter development

Thank you seema , my question was “why to include “develop project charter” work package in the wbs? “ . Since the charter has been already developed before the creation of wbs. I hope I clarified the question. Thank you again. the reason is simple WBS should capture all the effort and deliverable ...
by manishpn
Fri Apr 20, 2018 8:31 pm
Forum: PMP® Open Forum
Topic: Agile mindset and Agile practice guide
Replies: 4
Views: 1286

Re: Agile mindset and Agile practice guide

Hi Team, Please let us know how relevant Lesson 15 & 16 of the course, Agile mindset and Agile practice guide are from PMP exam point of view. Thanks! As of now we do not have enough data points , however based on feedback received from PMBOK6 passed candidate there has been 1-2 Agile related q...
by manishpn
Wed Apr 18, 2018 6:31 pm
Forum: PMP® Open Forum
Topic: Please reply
Replies: 3
Views: 203

Re: Please reply

Thanks for your reply but i have a confusion here.. In manage team process we have team performance assessment as an input. In develop team process we have also team performance assessment as an output and recognition and rewards as tools and techniques. not able to judge between manage team and de...
by manishpn
Wed Apr 18, 2018 6:24 am
Forum: PMP® Open Forum
Topic: Stakeholder Engagement Plan
Replies: 1
Views: 137

Re: Stakeholder Engagement Plan

should be D

13.2.1.3
by manishpn
Wed Apr 18, 2018 6:15 am
Forum: PMP® Open Forum
Topic: Please reply
Replies: 3
Views: 203

Re: Please reply

this is quiet easy, you should attempt it first and then we can discuss
by manishpn
Sun Apr 15, 2018 4:48 pm
Forum: PMP® Open Forum
Topic: Scope Management
Replies: 4
Views: 442

Re: Scope Management

good discussion
by manishpn
Sun Apr 15, 2018 4:47 pm
Forum: PMP® Open Forum
Topic: Question
Replies: 3
Views: 508

Re: Question

When do you perform stakeholder analysis? A. When defining the project scope B.When developing the project charter C.When creating the project management plan D.When putting changes through change control stakeholder analysis is a continuous process, it starts when Project charter is developed, mat...
by manishpn
Sun Apr 15, 2018 4:44 pm
Forum: PMP® Open Forum
Topic: Query - Risk Management
Replies: 1
Views: 241

Re: Query - Risk Management

You have joined the project during end of planning phase as previous Project manager has left organization and you are presenting project plan subsidiaries and some project documents to steering group for approval. While discussing risk register there is disagreement between 2 influential stakehold...
by manishpn
Sun Apr 15, 2018 4:32 pm
Forum: PMP® Open Forum
Topic: Query
Replies: 1
Views: 244

Re: Query

should be D
acknowledgement does not mean agreement
by manishpn
Sun Apr 15, 2018 4:30 pm
Forum: PMP® Open Forum
Topic: Query
Replies: 1
Views: 262

Re: Query

as project progresses we know more and accuracy level is expected to improve and variance level is expected to decrease, option A seems to be correct.
by manishpn
Sun Apr 15, 2018 4:28 pm
Forum: PMP® Open Forum
Topic: Execution Process Group Question
Replies: 1
Views: 254

Re: Execution Process Group Question

Hi , I have answered this as option C but the answer in the mock was option D. Please advise. During executing, change requests are raised in the project. The project manager is implementing these changes by following the change management plan. Which parameter/s should be implemented? Choose the b...
by manishpn
Sun Apr 15, 2018 4:22 pm
Forum: PMP® Open Forum
Topic: Closing Process Group Question
Replies: 2
Views: 331

Re: Closing Process Group Question

Hi , Please advise the correct options for below questions. 1. Which one of the following is the last step of project closing? A- Archive Project Documents - this would be best choice from given options B- Measure customer satisfaction at the end of the project - This is questionable as sometimes c...
by manishpn
Sun Apr 15, 2018 4:17 pm
Forum: PMP® Open Forum
Topic: Query
Replies: 2
Views: 332

Re: Query

by manishpn
Sun Apr 15, 2018 4:02 pm
Forum: PMP® Open Forum
Topic: Questions related to Risk Quantitative Analysis
Replies: 1
Views: 228

Re: Questions related to Risk Quantitative Analysis

there is no separate source and you need not worry too much on sigma (as there is not always a question on this in exam)
with regards to deviation we have it covered in our mock questions
by manishpn
Sun Apr 15, 2018 3:37 pm
Forum: PMP® Open Forum
Topic: Query on Develop Project Charter
Replies: 1
Views: 197

Re: Query on Develop Project Charter

the question has been discussed before

viewtopic.php?f=11&t=307&p=956&hilit=3000+MW#p956
by manishpn
Sun Apr 15, 2018 3:36 pm
Forum: PMP® Open Forum
Topic: Closing PG Query
Replies: 1
Views: 231

Re: Closing PG Query

comparing actual work don against PMP is done is M and C project work

whereas in closing project or phase the PM if ALL the work is completed as part of that project or Phase
by manishpn
Sun Apr 15, 2018 3:32 pm
Forum: PMP® Open Forum
Topic: Procurement Management Query
Replies: 2
Views: 245

Re: Procurement Management Query

Sandy is the project manager and managing procurement for vending machines for IZENBRIDGE office. Contract is signed and delivery is expected to come. When he checks he got confused he received fifteen machine on place of ten. He go back and check the contract which says “vendor to supply ten (15) ...
by manishpn
Sun Apr 15, 2018 3:28 pm
Forum: PMP® Open Forum
Topic: Need clarification on PERT diagram question
Replies: 1
Views: 223

Re: Need clarification on PERT diagram question

I am not sure if research projects only use Finish to start relationship i,e everything has to be sequential.

I did not find that in any official PMI publications
by manishpn
Sun Apr 15, 2018 3:19 pm
Forum: PMP® Open Forum
Topic: Please Evaluate the quality of this question
Replies: 1
Views: 193

Re: Please Evaluate the quality of this question

Below is a question posted by a PMP preparation company that my employer enrolled us for a bootcamp. I got many questions wrong on this guy's test, which is fine. But I want to know how is the queslity of this question in comparison to actual PMP exam. To me, this question was very very ambiguous. ...
by manishpn
Sun Apr 15, 2018 3:06 pm
Forum: PMP® Open Forum
Topic: 3 Types of Efforts
Replies: 1
Views: 258

Re: 3 Types of Efforts

refer to our blog

http://www.izenbridge.com/blog/introduc ... d-efforts/

and let me know if there is still confusion
by manishpn
Thu Apr 05, 2018 5:47 am
Forum: PMP® Open Forum
Topic: Communication dispute
Replies: 1
Views: 177

Re: Communication dispute

kindly post entire question for us to help you,
by manishpn
Mon Mar 26, 2018 10:07 am
Forum: PMP® Exam Lessons – Success Stories
Topic: cleared PMP exam on 22nd March
Replies: 2
Views: 334

Re: cleared PMP exam on 22nd March

congratulations on your PMP success
by manishpn
Sun Mar 25, 2018 2:41 pm
Forum: PMP® Exam Lessons – Success Stories
Topic: Cleared PMP Exam on 22nd March 2018.
Replies: 1
Views: 244

Re: Cleared PMP Exam on 22nd March 2018.

congratulations and wish you all the best
do share your experience..
by manishpn
Thu Mar 22, 2018 12:51 pm
Forum: PMP® Exam Lessons – Success Stories
Topic: PMP success story in 49 days - 3rd March
Replies: 1
Views: 340

Re: PMP success story in 49 days - 3rd March

congratulations and thank you for choosing Iznebridge
by manishpn
Wed Mar 21, 2018 10:49 am
Forum: PMP® Exam Lessons – Success Stories
Topic: PASSED MY PMP ON FIRST ATTEMPT
Replies: 2
Views: 383

Re: PASSED MY PMP ON FIRST ATTEMPT

congratulations and thanks for choosing izenbridge
by manishpn
Wed Mar 21, 2018 10:48 am
Forum: PMP® Exam Lessons – Success Stories
Topic: Earned my PMP credential
Replies: 1
Views: 274

Re: Earned my PMP credential

congratulations on your success
and thanks for choosing izenbridge
by manishpn
Wed Mar 14, 2018 9:41 pm
Forum: PMP® Exam Lessons – Success Stories
Topic: PMP Cleared on 12th of March 2018.
Replies: 1
Views: 397

Re: PMP Cleared on 12th of March 2018.

congratulations Altaf and thanks for sharing your experience.
thanks for choosing Izenbridge and wish you all the best
by manishpn
Sun Mar 11, 2018 9:06 am
Forum: PMP® Open Forum
Topic: Query
Replies: 3
Views: 350

Re: Query

Could anybody please explain me answer to this question. Shon is a project manager for a strategic initiative in pharmaceutical company developing cancer drugs. There is perennial challenge in finding resources with right competence within the organization. While Shon’s focus is to manage constrain...
by manishpn
Sat Mar 10, 2018 5:34 pm
Forum: PMP® Open Forum
Topic: Query
Replies: 3
Views: 350

Re: Query

its not that difficult can you make an attempt?
by manishpn
Mon Mar 05, 2018 9:51 pm
Forum: PMP® Open Forum
Topic: Question
Replies: 3
Views: 508

Re: Question

i was waiting for others to start discussion,

would you like to attempt with a reasoning so we can have good discussion
by manishpn
Mon Mar 05, 2018 9:49 pm
Forum: PMP® Exam Lessons – Success Stories
Topic: Cleared PMP in 1st Attempt with Above Target in all Domains
Replies: 4
Views: 807

Re: Cleared PMP in 1st Attempt with Above Target in all Domains

congratulations and thanks for choosingizenbridge
by manishpn
Thu Mar 01, 2018 5:39 pm
Forum: PMP® Open Forum
Topic: End of Phase - what would you do first
Replies: 4
Views: 428

Re: End of Phase - what would you do first

I agree with PMBalaji as well. For new phase to start, initiating process is followed again. So, I also marked Develop Project Charter because what if business need has now changed, hence there may be a change to the SOW etc. These factors need to be re-evaluated. But, per Scardo, the answer was Id...