Search found 4 matches

by Rajender
Sat Jul 12, 2014 2:40 pm
Forum: PMP® Open Forum
Topic: Time Management - Question
Replies: 6
Views: 1867

Re: Time Management - Question

Thanks Sunku, this explains. So this is not really calculation should go by the definitions.
by Rajender
Sat Jul 12, 2014 9:16 am
Forum: PMP® Open Forum
Topic: Question for Discussion-Risk Sources
Replies: 4
Views: 1438

Re: Question for Discussion-Risk Sources

my two cents. Process Analysis is one of Tools & Technique for QAssurance and more of concerned abt standards and guidlines. Question is about souces of risk, probably with elimination process other 3 options are components of Project and so D could be the answer.
by Rajender
Sat Jul 12, 2014 8:56 am
Forum: PMP® Open Forum
Topic: Time Management - Question
Replies: 6
Views: 1867

Re: Time Management - Question

I believe Yes It is B from the explanation given. Below is the explanation First, compute the standard deviation :σ =P-O/6 or 36-6/6=5 days Next, compute PERT expected time P+(ML)+O/6 or 36+4(21)+6/6=21 days Finally, determine range of outcomes using 1σ:21-5 = 16 days and 21+5 = 26 daysSimply define...
by Rajender
Sat Jul 12, 2014 7:07 am
Forum: PMP® Open Forum
Topic: Time Management - Question
Replies: 6
Views: 1867

Time Management - Question

Please help me with the below question. Activity A has a pessimistic (P) estimate of 36 days, a most like (ML) estimate of 21 days, and an optimistic (O) estimate of 6 days. What is the probability that activity A will be completed in 16 to 26 days A. 55.70 B.68.26 C.95.46 D. 99.73 Ans : B. I did ca...